CI" Y OF SAN BERNARD' '10 - REQUr IT FOR COUNCIL AC ION
File No. 3.14-10
From: ROGER G. HARDGRAVE, Director
Subject:
Approval of Change Order No. One
and Approval and Acceptance of
Work -- Installation of Relief
Sewer in Circle Road, North of
Edgehill Road, per Plan No.
M. GRBAVAC CONSTRUCTION
De~: Public Works/Engineering
Date: August 24, 1988
Synopsis of Previous Council action:
June, 1987
Allocation of $50,000 in 1987-88 Sewer Line Construction
Fund Budget approved.
03-07-88
04-04-88
Finding of need for health and safety reasons made.
Plans approved and authorization granted to advertise
for bids.
05-16-88
Resolution No. 88-155 adopted, awarding a contract for
the low bid price of $32,520.00.
Recommended motion:
1. That Change Order No. One to the contract with M. Grbavac Construction,
for Installation of Relief Sewer in Circle Road, North of Edgehill Road,
in accordance with Plan No. 7450, be approved authorizing extra work
due to an unknown utility interference, for an increase in the contract
price of $949.01, from $32,520.00 to $33,469.01.
2. That the work be approved and accepted and that final payment in the
amount of $3,388.90 (inclusive of Contract Change rder No.1, .
the amount of $949.01) be authorized at the
expiration of the lien period.
Contact person:
Roger G. Hardgrave
Phone:
5025
Supporting data attached: Staff Report & Change Order #1 Ward:
5
FUNDING REQUIREMENTS:
Amount:
~4;J.Ol
(Acct. DescriPtion)
- --,
J6S 57726 2~~ ()OO 'l.O I~:>. 32."1 '1',' "
). S- '31,> S''ln (.r _I ''t. 'JO
Rel~ef sew~c~ Road
Finance: ,-..,...--
Source: (ACCL No.) 24 S
Council Notes:
75-0262
Agenda I tem No.
/'1
CI~ .~ OF SAN BERNARD[ 0 - REQUl iT FOR COUNCIL AC _ 40N
STAFF REPORT
During the excavation of the trench for installation of the sewer main
in Circle Road, the Contractor hit a gas lateral line.
The Gas Company was unaware of the exi stence of the 1 atera1 si nce it
serves a house that does not front on the street. Therefore, this
lateral was not shown on the Plans or marked on the ground.
The Contractor was forced to cease operations and to standby until the
Gas Company personnel repaired the gas leak. It was necessary for the
Contractor to keep hi s crew on the jOb site in order to backfi 11 the
excavation and leave the job site in a safe manner at the end of the
day. The total loss to the Contractor's operati ons was 5 1/2 hours
totaling $949.01 in labor and equipment.
Due to the unusual location of the gas lateral, we believe that the
Contractor cou1 d not have anti ci pated the exi stence of the 1 i ne, and
exercised due care in the performance of his operations. The Standard
Speci fi cati ons states that a Change Order wi 11 be issued for unknown
physical conditions differing from those ordinarily encountered as
inherent in work of the character being performed.
We believe the Contractor's time and material price of $949.01 is
reasonable and justified. The total estimated project cost includes
$5,550.00 in contingencies, which will be used to finance the cost for
this Change Order.
All work was satisfactorily completed as of July 22,1988. The
contract was awarded for the low bid price of $32,520.00. The actual
fi na 1 pri ce is $33,889.01, due to the increase authori zed by Change
Order No. One, and an additional 10 feet of sewer lateral over the
estimated quantity in the bid document.
We recommend that the work be approved and accepted and that final pay-
ment be authorized at the expiration of the lien period, and Contract
Change Order No. One be approved.
8/24/88
7.5-0264
Project:
Plan No.
Keller ~ewer 1n ~lrCle
North of Edgehi Road
7450
KUdU
1j/~~/1j1j
File No.
3.14-10
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO. CALIFORNIA
CONTRACT CHANGE ORDER NO. ~
(Change necessitated because of field conditions)
TO: Mladen Grbavac Construction
311 W. Longden Avenue
Arcadia, CA. 91006
Gentlemen:
In accordance with Section 3-4 of the Standard Specifications, you are
hereby authori zed compensati on for standby time for an unmarked gas
lateral line at station 14+27, on a time and material basis, in
accordance with daily extra work report for 6-28-88, totaling $949.01.
Total extra work cost added to contract .............................$
949.01
Previous Contract Price .............................................$ 32,520.00
Amended Cost Pri ce .................................................. $ 33,469.01
Additional time to complete contract due to change order ............
1 Day
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
By:
ROGER G. HARDGRAVE
Director of Public Works/City Engr.
Title:
Accepted Date:
Approved Da te:
8/24/88