HomeMy WebLinkAbout14-Public Works CI" Y OF SAN BERNARD' '10 - REQUr IT FOR COUNCIL AC ION File No. 3.14-10 From: ROGER G. HARDGRAVE, Director Subject: Approval of Change Order No. One and Approval and Acceptance of Work -- Installation of Relief Sewer in Circle Road, North of Edgehill Road, per Plan No. M. GRBAVAC CONSTRUCTION De~: Public Works/Engineering Date: August 24, 1988 Synopsis of Previous Council action: June, 1987 Allocation of $50,000 in 1987-88 Sewer Line Construction Fund Budget approved. 03-07-88 04-04-88 Finding of need for health and safety reasons made. Plans approved and authorization granted to advertise for bids. 05-16-88 Resolution No. 88-155 adopted, awarding a contract for the low bid price of $32,520.00. Recommended motion: 1. That Change Order No. One to the contract with M. Grbavac Construction, for Installation of Relief Sewer in Circle Road, North of Edgehill Road, in accordance with Plan No. 7450, be approved authorizing extra work due to an unknown utility interference, for an increase in the contract price of $949.01, from $32,520.00 to $33,469.01. 2. That the work be approved and accepted and that final payment in the amount of $3,388.90 (inclusive of Contract Change rder No.1, . the amount of $949.01) be authorized at the expiration of the lien period. Contact person: Roger G. Hardgrave Phone: 5025 Supporting data attached: Staff Report & Change Order #1 Ward: 5 FUNDING REQUIREMENTS: Amount: ~4;J.Ol (Acct. DescriPtion) - --, J6S 57726 2~~ ()OO 'l.O I~:>. 32."1 '1',' " ). S- '31,> S''ln (.r _I ''t. 'JO Rel~ef sew~c~ Road Finance: ,-..,...-- Source: (ACCL No.) 24 S Council Notes: 75-0262 Agenda I tem No. /'1 CI~ .~ OF SAN BERNARD[ 0 - REQUl iT FOR COUNCIL AC _ 40N STAFF REPORT During the excavation of the trench for installation of the sewer main in Circle Road, the Contractor hit a gas lateral line. The Gas Company was unaware of the exi stence of the 1 atera1 si nce it serves a house that does not front on the street. Therefore, this lateral was not shown on the Plans or marked on the ground. The Contractor was forced to cease operations and to standby until the Gas Company personnel repaired the gas leak. It was necessary for the Contractor to keep hi s crew on the jOb site in order to backfi 11 the excavation and leave the job site in a safe manner at the end of the day. The total loss to the Contractor's operati ons was 5 1/2 hours totaling $949.01 in labor and equipment. Due to the unusual location of the gas lateral, we believe that the Contractor cou1 d not have anti ci pated the exi stence of the 1 i ne, and exercised due care in the performance of his operations. The Standard Speci fi cati ons states that a Change Order wi 11 be issued for unknown physical conditions differing from those ordinarily encountered as inherent in work of the character being performed. We believe the Contractor's time and material price of $949.01 is reasonable and justified. The total estimated project cost includes $5,550.00 in contingencies, which will be used to finance the cost for this Change Order. All work was satisfactorily completed as of July 22,1988. The contract was awarded for the low bid price of $32,520.00. The actual fi na 1 pri ce is $33,889.01, due to the increase authori zed by Change Order No. One, and an additional 10 feet of sewer lateral over the estimated quantity in the bid document. We recommend that the work be approved and accepted and that final pay- ment be authorized at the expiration of the lien period, and Contract Change Order No. One be approved. 8/24/88 7.5-0264 Project: Plan No. Keller ~ewer 1n ~lrCle North of Edgehi Road 7450 KUdU 1j/~~/1j1j File No. 3.14-10 ENGINEERING DIVISION DEPARTMENT OF PUBLIC WORKS CITY OF SAN BERNARDINO. CALIFORNIA CONTRACT CHANGE ORDER NO. ~ (Change necessitated because of field conditions) TO: Mladen Grbavac Construction 311 W. Longden Avenue Arcadia, CA. 91006 Gentlemen: In accordance with Section 3-4 of the Standard Specifications, you are hereby authori zed compensati on for standby time for an unmarked gas lateral line at station 14+27, on a time and material basis, in accordance with daily extra work report for 6-28-88, totaling $949.01. Total extra work cost added to contract .............................$ 949.01 Previous Contract Price .............................................$ 32,520.00 Amended Cost Pri ce .................................................. $ 33,469.01 Additional time to complete contract due to change order ............ 1 Day CONTRACTOR: CITY OF SAN BERNARDINO: By: By: ROGER G. HARDGRAVE Director of Public Works/City Engr. Title: Accepted Date: Approved Da te: 8/24/88