CITy' OF SAN BERNARDINO
Fil No. 6.141-K
- REQUEST FOR COUNCIL ACTION
From: ROGER G. HARDGRAVE
Subject:
REC'O.-AOMfff. OFF.
Public Works/Engineeri~q801
1::1 a rfOV -9 PH 4: 10
11-08-88
Approval of Change Orders ONE &
TWO Installation of
Ballfield Lighting at Fisca1ini
Field per Plan No. 7332 --
GEORGE JUGOVIC CONSTRUCTION
Dept:
Dlte:
Synopsis of Previous Council action:
June, 1987 Allocation of $117,090 from 1987/88 CDBG Program for
installation of new lights approved.
Finding made the installation of new lights is needed
for health' and safety reasons.
Directed to conduct full environmental impact report.
Staff directed to prepare environmental assessment
and $5,000 authorized for preparation of technical
studies.
Report entitled "Noise Assessment Study of Sprint
Baseball Games" accepted.
Negative Declaration adopted and authorization given
to advertise for bids.
Resolution No. 88-394 adopted awarding a contract for
the low bid price of $94,157.00, for the Basic Bid.
Reappropriation of $25,000, from Account No. 121-544
-57597, "Handicapped Ramps," & approximately $11,238
from CDBG Contingency Account, approved.
09-21-87
09-21-87
10-05-87
03-21-88
06-06-88
10-08-88
11-07-88
Recommended motion:
cc: J. Robbins
J. Richardson
A. Green
K. Henderson
A. Ramos
That Change Order No's one & Two to the contract with
George Jugovic Construction, for the installation
of ballfield lighting at Fiscalini Field, per Plan
No. 7332, be approved; authorizing the contractor to
install 4 outfield lights at a net increase in the
contract price of $42,32. , from $94 7. 0 to
$136,485.00.
M
Contact person:
Roger Hardgrave
Phone:
5025
Supporting data attached:
Staff Report, ceo One & Two Ward:
2
FUNDING REQUIREMENTS:
Amount:
$42,328.00
Source: (Acct. No.)
121-544-57596
(Acct. DescriPtion)
Fiscalini Field Lighting
Finance: O~ ;:.jr-./
System
Council Notes:
75-0262
Agenda Item No.
/6
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
The contract for installation of
was awarded for the Basic Bid only, due
finance the replacement of all lights.
were included in the Basic Bid, with
designated as Additive Alternate "A".
lights at Fiscalini Field
to insufficient funds to
The four infield towers
the four outfield towers
A price of $62,328.00 was included in the low bid for
Additive Alternate "A". The Colony Village development, at Barton
Road and Hunts Lane, improved a baseball field. This field has a
much higher lighting level than required. Therefore, the Parks
and Recreation Department has proposed that four of the eight
poles at Colony Village be removed and furnished to the Contractor
for Fiscalini Field. Removal of these poles and transporting them
to Fiscalini Field would be done by City Forces.
The Contractor has quoted a credit of $20,000, for the
City furnishing the four poles. Lighting fixtures would still be
furnished by the Contractor. We have checked the purchase price
for poles, and determined that the credit of $20,000 is fair and
reasonable. Inclusion of the four outfield poles, furnished by
the City, would increase the contract price by $42,328.00.
At the Council meeting of 11-07-88, the amount of $25,000
was reappropriated from Account No. 121-544-57597, "Handicapped
Ramps at Various Locations," and the approximate amount of $11,238
was appropriated from the CDBG Contingency Account, to finance the
cost for adding the four outfield poles to the contract.
Change Order No One will add Additive Alternate "A" to the
contract, at an increase in the cost of $62,328, and Change Order
No. Two will authorize a credit of $20,000 for the City furnishing
the four poles.
We recommend that Change Orders No. 1 & 2 be approved.
11-08-88
75-0264
~
~\1lwC:. .L.':" - i .. ~'~
. project: BALLFIELD LIGHTIrlG IMPROVErlENTS
TO FISCALINI BASEBALL FIELD
File NO.6 .141-K
Plan No.
7332
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIfORNIA
CONTRACT CHANGE ORDER NO. Q!lL..
(Change. necessitated because of field conditions)
TO: GEORGE JUGOVIC CONSTRUCTION CO.
23014 ERWIN STREET
WOODLAND HILLS, CA. 91367
Gentlemen:
You are hereby authorized and directed to remove and install
(4)four otufield poles and light fixtures in accordance with
Additive Alternate "A" of the Bid Schedule for Plan No. 7332
for the Lump Sum price of $62,328.00.
Total extra work cost added to contract .............................$ 62.32R nn
Previous Contract Price .............................................$ 94,157.00
Amended Cost Price ..................................................$ 156,485.00
Additional time to complete contract due to change order ............ -0-
CONTRACTOR:
CITY OF SAN BERNARDINO:
8y:
Title:
8y:
ROGER G. HARDGRAVE
Director of Public Works/City Engr.
Accepted Date:
Approved Date:
~
project: BALLFIELD UGH" 'G H1PROVE~1ENTS
TO FICALINI BA~~JALL FIELD
P11ft No.
7332
Da te: 9-16-88
File No.
6.141-K
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. TWO
.-
(Change necessitated because of field conditions)
TO: GEORGE JUGOVIC CONSTRUCTION CO.
23014 ER~JlN STREET
WOODLAND HILLS, CA. 91367
Gentlemen:
You are hereby authorized and directed to install four (4) Owner
furnished steel poles and light fixtures, along with all appurtenant
facilities as called for on the Plans and Special Provisions
No. 7332, at a net decrease in the contract price of $20,000.00.
Total extra work cost added to contract .............................$ (20,000.00)
Previous Contract Price .............................................$ 156,485.00
Amended Cos t Pri ce .................................................. $ 136. 485 . 00
Additional time to complete contract due to change order ............
-0-
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
Title:
By:
ROGER G. HARDGRAVE
Director of Public Works/City Engr.
Accepted Date:
Approved Date: