CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
Dept:
Public Works/Engineering
REC'O.-I\tHHN.nr;:. t
SUbJec :
\981 JAN - 8 Fl1 3: c: 0
Approval of Plans & Authorization to
Advertise for Bids -- Improvement of
Patton Park South, per Plan No. 7169
From:
ROGER G. HARDGRAVE
Date: 1-08-87
Synopsis of Previous Council action:
June, 1986 -- Allocation of $125,000 from CDBG funds approved, to complete
improvement of Patton Park South.
Recommended motion:
That the plans for improvement of Patton Park South,
in accordance with Plan No. 7169, be approved, and the
Director of Public Works/City Engineer authorized to
advertise for bids.
cc: Ray Schweitzer
W. Knudson
K. Henderson
A. Ramos
Contact person:
Roger G. Hardgrave
Phone:
5025
7
Supporting data attached:
Staff Report
Ward:
FUNDING REQUIREMENTS:
Amount: $120,000
Source: (ACCT. NO.) 121-544-57595
(ACCT. DESCRIPTION) Patton Park South - Phase III
Finance: l{)c~- r1 /5~?~e">'l./
~p-
Council Notes:
75.0262
Agenda I tem No.
z
~
-
CIT { OF SAN BERNARDINO - REQUE~ r FOR COUNCIL ACl.ON
STAFF REPORT
Plans for the completion of the improvement of Patton Park South
have been prepared by a landscape architect, and the project is ready to be
advertised for bids. The project consists, in general, of grading, installing
irrigation system, hydrospraying turf, security lighting and constructing a
trash enclosure.
Listed below is an estimate of the total project cost:
Construction Contract
Engineering & Inspection (W.O. #1783)
Sub-Total
Contingencies (5%)f
$ 104,385
10,400
$ 114,785
5,215
$ 120,000
An amount of $125,000 was allocated from Community Development Block
Grant Funds, under Account #121-544-57595, to finance the cost of these improve-
ments. The current balance is approximately $120,000.
We recommend that the plans be approved and authorization granted to
advertise for bids.