From: ROGER G. HARDGRAVE
De~: Public Works/Engineering
Date: . 6-1-88
Subject:
Approval of Change Order No. ONE--
Installation of Traffic Signals
on University Parkway, at College
Avenue and Hallmark Parkway, per
Plan No. 7246--DONALD C. HUBB
dba JESSE HU88S & SONS
Synopsis of Previous Council action:
06-16-86 -- Protest hearing closed and finding made that public health
and safety require installation of traffic signals at
University Parkway & Hallmark Parkway.
11-03-86 -- Transfer of $5,000 from Account No. 772-301-24505, to
Account No. 242-362-57376, "Signals - University Parkway
& College Avenue approved.
05-11-87 Plans approved and authorization granted to advertise for
bids.
07-20-87 Finding made that installation of traffic signals at
University Parkway & College Avenue is needed for health &
safety reasons. (Continued on second page)
Recommended motion:
That Change Order No. ONE to the contract with Donald C.
Hubbs Co. for the installation of a storm drain and traffic
signals on University Parkway, at College Avenue and
Hallmark Parkway, per plan No. 7246, be approved, authorizing
the Contractor to remove and dispose of unsuitable existing
A.C. pavement, for an increase in the contract price of
$1,107.68, from $289,257.00 to $290,364.68.
cc: Jim Robbins
Andy Green
~d~
<~ S'
19natu re
Ward:
5025
5 & 6
Contact person: Roger G. Hardgrave
Supportinlldataattached: Staff Report & CCO #1
FUNDING REOUIREMENTS: Amount: $1,107.68
Traffic Signals on
Ilnivf>r~il:y Parkway [a Collf>gf> AVf>_ l!. Hallmark
Phone:
Source: 248-368-57816
Finance,LWwJ j;>-------
Council Notes:
75-0262
Agenda Item No.
-~
If"
~IT~ OF SAN _RNBcDINO - REQUEST ~ COUNCIL ACTION
STAFF REPORT
During the construction of street improvements at
University Parkway and College Avenue, a portion of the exist-
ing pavement on College Avenue was discovered to be temporary
cold mix. This pavement was placed by a developer in order to
feather into his permanent pavement. In order to achieve an
acceptable street, it was necessary to remove the temporary
material and replace with permanent paving.
Contract Change Order No. One authorizes the Contractor
to remove and dispose of the existing temporary A.C. pavement
and prepare the subgrade to the proper depth, for an increase
in the price of $1,107.68, increasing the contract price from
$289,257.00 to $290,364.68.
This final estimate of cost contains an amount of
$10,743.00 for contingencies, which can be used to finance this
additional cost.
We recommend that Change Order No. One be approved.
SYNOPSIS OF PREVIOUS COUNCIL ACTION Continued:
10-05-87
Finding made that installation of traffic signals at
University Parkway & Hallmark Parkway is needed for
health & safety reasons.
11-02-87 -- Resolution No. 87-390 adopted awarding a contract
for the bid price of $289,257.00.
6-1-88
75-0264
Storm Drain & ~ffiC Signals
Project: on University Parkway at College Avenue
& Hallmark Parkway
Plan No. 7246
o
Date: 5-31-88
Ftle No. 1.376 & 2.120
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. ~
(Change necessitated because of field conditions)
TO:
Donald C. Hubbs, Inc.
P. O. Box 490
Rialto, CA 92376
Gentl_n:
You are hereby authorized and directed to remove and dispose
of existing asphalt on College Avenue as directed by the
Engineer on a time and materials basis for the net price of
$1,107.68. .
Total extra work cost added to contract .............................$ 1,107.68
Previous Contract Price .............................................$ 289,257.00
Amended Cost Price ......................~.............................$ 290,364.68
Additional time to complete contract due to change order ............
-0-
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
Title:
By:
ROGER G. HARDGRAVE
Director of Public Works/City Engr.
Accepted Date:
Approved Date: