CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: James Funk, Director
Subject: Resolution awarding contract to
Malton Construction for street and storm
C .. . . 'L drain improvements at 13th Street and "G"
. / . I ... I . "I Street, per Plan No. 10220-A and
authorization for the Director of Finance to
amend the FY 2001102 budget.
MCC Date: December 17, 2001
Dept: Development Services
Date: November 27, 2001
File: 4.7204
Synopsis of Previous Council Action:
7/9/01 Allocation of $50,000 in the 2001/02 Capital Improvement Program (CIP) for 13th Street and
"0" Street Cross Outter and Improvements (Account No. 248-368-5504-7204).
10/15/01 Reject all bids submitted for the installation of cross gutter & improvements at 13'" Street &
"0:' Street, revise plans and specifications, and re-advertise for bids.
Recommended Motion:
I) Adopt Resolution.
2) That the Mayor and Common Council authorize the Director of Finance to amend the FY 2001102
budget to transfer $15,000 from Account No. 248-368-5504-7257 (Town Creek Tunnel Storm Drain
Repair) to Account No. 248-368-5504-7204 by (13th Street and "0" Street C~Outter and
Impro'=~'). -H ~
James Funk
Contact person: Mehran Sepehri, Senior Civil Engineer
Phone:
'il?7
Supporting data attached: Staff Report, Map, & Reso.
Ward:
?
FUNDING REQUIREMENTS: Amount: $65,000.00
Source: (Acct. No.) 248-368-5504-7204
Acct. Description: 13th Street and "G" Street Cross Gutter and
Improvements.
Finance: ~dfLtl/ &~
Council Notes:
~... "-CO\' 3'1 '-/
I J.)li}oi
Agenda Item No. '9
.. .
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Resolution awarding contract to Malton Construction for street and storm drain improvements
at 131h Street and "G" Street, per Plan No. 10220-A and authorization for the Director of
Finance to amend the FY 2001/02 budget.
Background:
This project consists of removal, repair, and installation of the street sections and cross gutter
on 13th Street and "G" Street at the intersection. This section of road experiences significant
vehicular traffic and the original pavement sections have deteriorated. A new cross gutter is
needed to allow a greater volume of storm water to cross this intersection and improve the
cross slope. This intersection is currently in poor condition, which is why staff is proposing to
move forward with this project as soon as possible.
This project was initially designed to include the reconstruction of adjacent ramps to meet
current Americans with Disabilities Act standards. The project was bid and the apparent low
bid far exceeded the construction cost budgeted for the project, which was developed based
only on the cross gutter and intersection improvements.
Subsequently, staff recommended, and the Council approved, rejecting all bids and redesigning
and rebidding the project to more closely meet the project budget constraints. The current
apparent low bid falls reasonably close to the original estimated construction cost. However,
the design, contract administration, inspection costs, and the costs associated with rebidding
the project necessitate an intrafund budget transfer of $15,000.
Plan and specifications for this project are complete and the project is ready to be awarded.
The estimated project costs are as follows:
Construction Cost $44,330.00
Contin~encies $6,000.00
Desi~n, InsDection, and Contract Administration * $14,670.00
Total $65,000.00
* Includes preliminary design costs expended in FY 00/01 in the approximate
amount 0[$10,200.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
This project was advertised locally in the San Bernardino County Sun Newspaper, Construction
Trend Newspaper, the City's web site, and with the San Bernardino Area Chamber of
Commerce. The following eight companies responded:
Name of Bidder City Amount of Bid
Malton Construction Riverside $44,330.00
Holland-Lowe Construction San Bernardino $61,348.05
Ayala and Sons, Inc. San Bernardino $65,232.05
EBS Inc. Corona $65,474.00
CDE Resources, Inc. San Bernardino $65,665.00
Laird Construction Co., Inc. Rancho Cucamonga $69,250.00
JDC Inc. Rancho Cucamonga $77 ,583.00
Cherokee Lancaster $90,373.70
Engineering Estimate $49,770.00
Based on review of the sealed competitive bids received, staff has determined that Malton
Construction, the apparent lowest bidder, has met the minimum requirements of the specifications
and bid guidelines, and therefore recommends that the Mayor and Common Council award the
referenced contract accordingly.
Financial Impact:
Funding for this project, in the amount of $50,000 was original budget in FY 2000/01 in the
Storm Drain Construction Fund. Approximately $10,200 of the funds were expended in FY
2000/01 and the remaining $39,800 was carried over into FY 2001/02. It is now estimated
$54,800 will be needed in FY2001/02 to complete this project so a budget amendment in the
amount of $15,000 is needed. In order to accommodate the design, construction, inspection,
and contract administration, staff recommends that an additional $15,000 be transferred from
Account No. 248-368-5504-7257 (Town Creek Tunnel Storm Drain Repair) to Account No.
248-368-5504-7204. Staff is still researching alternative design methodologies for repair of the
Town Creek Storm Drain, but it is estimated that the budget remaining will accommodate the
associated FY 2001/02 design costs. All costs incurred for this project will be charged to
Account No. 248-368-5504-7204 (13th Street and "G" Street cross gutter and improvements).
Recommendation:
Adopt Resolution.
Street Improvements
At
13th STREET
And
"G" STREET
Z1:;; .. i ~ z'
; 100 . l.Ll """. 310". 1100 i 10 1 I GUT i
ST it(A\'<'~!iJI _~ ~ ' sr I <( :;:.! 'I'~' i' =3;: l
- -'-'f---~ \It l.ri ZLSI ~--- I .,:(! ,n, ;3 -~ i 1
'iI, 70~ \......-::,.- .... ..~. , ! 'Lsd I \L "--rl ...(! .L.
.JL_. L2I; ~W' I' .... . 20TH ST<----+...j..'~- l~--~'r- ,\ I j
l.-~,~<__z .. - F:ll1jr;--;- ~ ST i I ~ :(:'1' jj ~!
w r,"fRS W1! "'<-.--- C> .- '/'- ,'. - ~_-i I ,Ii \
----. ---...... -. -.'~.., . ~ en! ~9rn .;", I. o:E. .:i.19THc
, I~'! . w - I _. l:i11 ~ .-::,:~r._.L
'--f '''1 SAN. w J i 18TH ~;ii' i STi._ !.LI ....4-1.8HI
, ;11' s.! BERNAlIDlNO "--rcl",.-- <:<r--!../JOT t.,!'! 100
-856 -i--~--l HS 1w ~\ >: 'I 10'
...!_J!/!'_. ~-t--,:z: R w rr 1m ~l ""H.Jr i ~~J,~l
.;...slU ~ ,)) . '----J1-" -0,._" ,- ~. .... , .,~!;')I
, :MJf11Jl! .." Wi"''' I.. ~l'
,.ro.- 'IS! >-tiflT:1'....j$ 1 1lJlLl.. . I, ~E _'1..~_!
~- --=t=~~~==r----- I ~'~~ . -'"'. . \ i r-~l
L.L! . EVANS.LlT. 115nl! :ii;
i l.-"j I 5 '+-'TT1jQ'!
.l~...._.!I~~,.___.~J.:[ ~j i! ;
1~1,?( ~1,~_~~~rV'l-RG;lAl1}1ho;1 .]~ Ym-j ~\ .;L~ Unm_
.'::iGINl..M ~i .:=,. 'I
-1L vPig~.I~~~l i --$"- 1! w '~L^~.L~_ ~ ~ "
~T ." I. I g I \[^- o~' "'2a01 5T E'
i 1~ !::1 il13TH 0
." ," 100 i
OJ I I ~()Ol >J ~\ ':001 ,21 zl ~ ;
~l... i "'I t- l lL.-1Q.l.A Pi. Lt! I W
:L l.-L:'.SI '" -- V; E \
I w "'i loa 50a 400 i lJ~ O~TI '>l_~L ~oo %1
r--------jo Ll-: ?<f g , - I
VICINITY
MAP
N. T.s.
<'
,..
~(Q)[P)W
1
2
RESOLUTION NO.
',- RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
3 BERNARDINO AWARDING A CONTRACT TO MALTON CONSTRUCTION, FOR
4 STREET IMPROVEMENTS AT 13th STREET AND "G" STREET, PER PLAN NO.
l0220-A.
5
-~
......
27
;r"";.
...... 28
BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE
6 CITY OF SAN BERNARDINO AS FOLLOWS:
7
8
SECTION 1. Malton Construction, is the lowest responsible bidder for street
improvements at J3'h Street and "G" Street, per Plan No. 10220-A. A contract is awarded
9
10 accordingly to said bidder in a total amount of $44,330 with a contingency amount of $6.000
11 but such award shall be effective only upon being fully executed by both parties. All other
12 bids, therefore. are hereby rejected. The Mayor is hereby authorized and directed to execute
13
said contract on behalf of the City; a copy of the contract is on file in the office of the City
14
Clerk and incorporated herein by reference as fully as though set forth at length.
15
SECTION 2. This contract and any amendment or modifications thereto shall not take
16
17 effect or become operative until fully signed and executed by the parties and no party shall be
18
19
obligated hereunder until the time of such full execution. No oral agreements. amendments,
modifications or waivers are intended or authorized and shall not be implied from any act or
20
course of conduct of any party.
21
22 SECTION 3. This resolution is rescinded if the parties to the contract fail to execute it
23 within sixty (60) days of passage of the resolution.
24 III
25
26
III
/9'
/2 -/1-0/
,.
~,.."..,
'-
1 RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
2 BERNARDINO AWARDING A CONTRACT TO MALTON CONSTRUCTION, FOR
STREET IMPROVEMENTS AT 13th STREET AND "G" STREET, PER PLAN NO.
3 10220-A.
4
I HEREBY CERTIFY that the foregoing Resolution was duly adopted by the Mayor and
5
Common Council of the City of San Bernardino at a
6
7
8
meeting thereof, held on the _day
of _,2001, by the following vote, to wit:
ABSTAIN ABSENT
Council Members:
NAYS
AYES
9 ESTRADA
10
LIEN
11
MC GINNIS
12
13 SCHNETZ
14 SUAREZ
r
\.... 15 ANDERSON
16
c
MC CAMMACK
17
18
19
20
21
22
23
24
Approved as to
25 form and legal content:
26 JAMES F. PENMAN,
City Clerk
The foregoing resolution is hereby approved this
day of
, 2001.
Judith Valles, Mayor
City of San Bernardino
27
City Attorney
28 By: L 1-.k
(J
CITY OF SAN BERNARDINO
Interoffice Memorandum
CITY CLERK'S OFFICE
Records and Information Management (RIM) Program
DATE:
December 19,2001
TO:
Mehran Sepehri, Senior Civil Engineer
FROM:
Michelle Taylor, Senior Secretary
RE:
Transmitting Documents for Signature - Resolution 2001-374
At the Mayor and Common Council meeting of December 17, 2001, the City of San Bernardino
adopted Resolution 2001-374 - Resolution awarding a contract to Malton Construction for
street improvements at 13th Street and "G" Street, per Plan No. J0220A.
",1'1
I am providing you with one certified copy of Resolution 2001-J89 and four (4) original bound
contracts. Please obtain signatures where indicated and return one fully executed original
contract to the City Clerk's office as soon as possible.
Please be advised that the resolution and contract will be null and void if not executed
within 60 days, or by February 15,2002.
If you have any questions, please do not hesitate to contact me at ext. 3206. Thank you.
I hereby acknowledge receipt of the above mentioned documents.
Signed: f~ tfrAAM/
1z--I-tfJIOI
, I
Please sign and return.
Date:
CITY OF SAN BERNARDINO
Interoffice Memorandum
CITY CLERK'S OFFICE
Records and Information Management (RIM) Program
DATE:
February I, 2002
TO:
Mehran Sephri, Senior Civil Engineer
FROM:
Michelle Taylor, Senior Secretary
RE:
Resolution 2001-374 - Agreement with Malton Construction
Our office has not received the executed contract with Malton Construction for street
improvements at 13th Street and "G" Street, per Plan No. 10220A, which was approved at the
Mayor and Common Council meeting held on December 17, 2001.
Please forward the executed contract to the City Clerk's office, to my attention; otherwise,
please submit a memo detailing its status.
Note: The resolution and agreement will be null and void if not executed by February 15, 2002.
If you have any questions, please call me at ext. 3206.
. ,
'.
.
.
** FOR OFFICE USE ONL Y - NOT A PUBLIC DOCUMENT **
RESOLUTION AGENDA ITEM TRACKING FORM
Meeting Date (Date Adopted): 1"2 -I '1- 0 \ Item #
Vole: Ayes \-I" Nays-&-
Change to motion to amend original documents:
I 9 Resolution'; ~? CO l-=J'> '1 ~~_ .._._
Abstain -&-. Absent 'l
-------------.
Reso. # On Attachments: ~ Contract tenm:
Note on Resolution of Attachment stored separately: ,/"
Direct City Clerk to (circle 1): PUBLISH. POST. RECORD W,COUNTY
NullNoid After_roQQ~.;,J2-1.s-9.?____
By: _.=___
Date Sent to Mayor:
12-l'lo:~ClI
Reso. Log Updated:
Seal Impressed: ____
,/'
/
Date of Mayor's Signature: 12- \'1-01
Date ofClerk/CDC Signature: ('2.-1 '1-0 \
Date Memo/Letter Sent for Signature:
~ Reminder Letter Sent on}lUlHlliy:
90 Day Reminder Letter Sent on 45th day:
/2.-"20-<0 I
!)-\-o..?-
See Attached: / Date Returned: d.. - f) -IJ ".
See Attached: ~
See Anached:
Request for Council Action & StalT Report Attached: Yes /
Updated Prior Resolutions (Other Than Below): Yes
Updated CITY Personnel Folders (6413, 6429, 6433,10584,10585,12634): Yes
Updated CDC Personnel Folders (5557): Yes
Updated Traffie Folders (3985,8234,655.92-389): Yes
No By
No ,/ By
No ~ By
No / By
No ""T By
Copies Distributed to:
Cily Attorney ~
Parks & Rec.
Code Compliance Dev. Services -L. EDA
Police Public Services Water
Finance
MIS
Others:
fY1 eM12.1'r>J
Notes:
'&011 0 CD",IU,c."(
BEFORE FILING. REVIEW FORM TO ENSURE ANY NOTATIONS MADE HERE ARE TRANSFERRED TO THE
YEARLY RESOLUTION CHRONOLOGICAL LOG FOR FUTURE REFERENCE (Contraet Term. ete.)
Ready to File: ~
Date: ?-I '1/0:i.-
Revised 01112/01