CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: James Funk, Director
Subject: Resolution awarding contract to
C ".,' I"' C Lambco Engineering, Inc. for storm drain
; i . .... I . ~ rl L outlet structure repair on 40th Street, Phase
I, per Plan No. 10320
Dept: Development Services
Date: November 20. 2001
File: 4.7256
MCC Date: December 17, 2001
Synopsis of Previous Council Action:
7/9/01 Allocation of $50,000 in the 2001/02 Capital Improvement Program (CIP) for 40'h
Street storm drain (Account Nos. 248-368-5504-7256).
Recommended Motion:
Adopt Resolution.
-h~
Contact person: Mehran Sepehri, Senior Civil Engineer
Phone:
~1?7
Supporting data attached: Staff Report, Map, & Resolution
Ward:
~
FUNDING REQUIREMENTS: Amount: $50,000.00
Source: (Acct. No.) 248-368-5504-7256
Acct. Description: Storm drain outlet structure re air on 40th Street.
Finance:
Council Notes:
'l'~~~\-'S'\s
Agenda Item No. I g
Jell n JOJ
.'
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Resolution awarding contract to Lambco Engineering, Inc. for storm drain outlet structure
repair on 40th Street, Phase I, per Plan No. 10320.
Background:
This project consists of the repair and installation of rip-rap at the 401h Street storm drain outlet
structure east of "H" Street. Rip-Rap is the loose rock placed in front of the outlet structures
to prevent erosion. This structure which has been damaged and eroded due to the effect of
previous storms and is currently in need of immediate repair prior to the next heavy storm.
Staff is proposing to move forward with the Phase I repair as soon as possible to prevent
further damage to the outlet structure. Due to time constraints, the complete reconstruction and
repair can not be done during the rainy season; Phase II of this project will be completed after
the rainy season.
Plan and specifications for this project are complete and the project is ready to be awarded.
The estimated project costs are as follows:
Construction Cost $28,900.00
Contingencies $5,000.00
Design (Phase I & II), Inspection, and Contract $16,100.00
Administration
Total $50,000.00
This project was advertised locally in the San Bernardino County Sun Newspaper, Construction
Trend Newspaper, the City's web site, and with the San Bernardino Area Chamber of
Commerce. The following three companies responded:
Name of Bidder City Amount of Bid
Lambco Engineerinl!:, Inc Santa Ana $28,900.00
4 Con Engineerin2: Fontana $39,000.00
Sim Engineering, Inc. Fall Brook $43,000.00
Engineering Estimate $30,000.00
Based on a review of the sealed competitive bids received, staff has determined that Lambco
Engineering, Inc., the apparent lowest bidder, has met the minimum requirements of the
specifications and bid guidelines, and therefore recommends that the Mayor and Common Council
award the referenced contract accordingly.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Financial Impact:
Funding for this project in the amount of $50,000 has been included in the FY 01-02 budget
from the Storm Drain Construction Fund. All costs incurred will be charged to Account No.
248-368-5504-7256 (Storm Drain Outlet Structure Repair on 40th Street).
Recommendation:
Adopt Resolution.
City of San Bernardino, California
Department of Public Works, Division of Engineering
November 27, 2001
File No. 1.7256
W.O. No. 7256
DWG. No. 10320
Storm Drain Outlet Structure Repair
On
40th Street -- Phase I
T"
, "
~ '././0 '. to
'.J- 0 "--.. en ~
,,! J~ 0.:::;' ~
';:'/lIfs :~'~~
'</f' ErA~" .
~/~ 'ff" ......f.., '....1/;> /
f'''' "> ", oS' ~ .. ,',
~ _--~-,.,.. f !. "" ~ /<."'~/ /1'"'-
"'(' '.J' '..... '-, -...-' J....(V S'lir~
0;:( ~ ',-'/'/,~~'" _..,-'"l'\.~fl'1l \ ... ...__ ~r,.......--,,,
:r: _,y",,\ -..."\..... "l<lDI!~ ".
'%.i/l(IC'eJluec;." /..'" '~~" "I;:Vlo:!V "I(
ft: ~----r~~~" ~~ + ----~-~fI~~,____~
~"V"J N:S. ~ ~ .'~"
/' /1oJ 4lr...... j
....~ e'-,. /.... ~ '
~':;<{"'., -.Irq /..:- 0
.p/'!Y'N/~"'" \.\)GE LlNE ~/'
Tf 'o~/.:'"ff;~ "~I~" ~ },.-------
RilACf~! <1" ",I~ /
Dri , -i"
~i~_ .~"
/.~ I
..-....--~-
/'
1"//
/'
1 " 1E1 co ell!:z
;Z ;Z ;Z I'~ ~I :zl ~ ~,,! i rr1
· '''.--r~-'''+-+-~ Jr 1'1"1
I I I. I"'''
tz:: trio :2:1 ,.'ll~\~ 2
c::a ~ :,..J ~ Ic:5p......
..., I LW I <[ I_.JI'
':it...! '--;;;, "'J "1'''
i:= ~I! ::ili ~ ,'_:pI
81_,~!I ;----~1~-=.\ - -_~C=-~_~j-FS
)400 I: I., 1 I
" '300 1400,
\. :3l ~i ~i:-.
I ., '.m'.\ d:! 2:;,<( ....I.
t:ITItE.}J/)U~i/tto/ ~ - ~ ' ~
/ r ~-r'r 1""~(7 ;Z LL~,..,.~l1lST"'--
>-_ J'--^^~...,LLjf~b- .;..dI~tL '!
. ~~~=::~~-=~':::'=:~'~~_~.~ff:tf'_-_~)j'-
~! ~c::.<::H::1 rYJ,~~I;1!O..,.
>, , SKrlA\l....>',
."'-...-:..._:..:...-_:;.:,..;....-~ .----. ~
-OR
ST
...,1
I
I~
l~
VICINITY
MAP
N. T.S.
-
\.....
.,-,
"-
,
ce(Q)~V
I.
1
2
RESOLUTION NO.
RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
3 BERNARDINO AWARDING A CONTRACT TO LAMBCO ENGINEERING, INC.
4 FOR STORM DRAIN OUTLET STRUCTURE REPAIR ON 40TH STREET PHASE I,
PER PLAN NO. 10320.
5
BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE
6 CITY OF SAN BERNARDINO AS FOLLOWS:
7
SECTION 1. Lambco Engineering, Inc, is the lowest responsible bidder for. storm
11 but such award shall be effective only upon being fully executed by both parties. All other
12 bids, therefore, are hereby rejected. The Mayor is hereby authorized and directed to execute
13
said contract on behalf of the City; a copy of the contract is on file in the office of the City
14
Clerk and incorporated herein by reference as fully as though set forth at length.
15
16
17
18
19
SECTION 2. This contract and any amendment or modifications thereto shall not take
effect or become operative until fully signed and executed by the parties and no party shall be
obligated hereunder until the time of such full execution. No oral agreements, amendments,
modifications or waivers are intended or authorized and shall not be implied from any act or
20
21 course of conduct of any party.
22 SECTION 3. This resolution is rescinded if the parties to the contract fail to execute it
23 within sixty (60) days of passage of the resolution.
/--
,
'--
f"'""'"
'-
r
'-
.
1 RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
2 BERNARDINO AWARDING A CONTRACT TO LAMBCO ENGINEERING, INC.
FOR STORM DRAIN OUTLET STRUCTURE REPAIR ON 40TH STREET PHASE I,
3 PER PLAN NO. 10320.
4
5
6
7
8
9
10
I HEREBY CERTIFY that the foregoing Resolution was duly adopted by the Mayor and
Common Council of the City of San Bernardino at a
meeting thereof, held on the _day
of _,2001, by the following vote, to wit:
Council Members:
AYES
NAYS
ABSTAIN
ABSENT
ESTRADA
LIEN
11
12
MC GINNIS
13 SCHNETZ
14
15
16
17
18
19
SUAREZ
ANDERSON
MC CAMMACK
City Clerk
20
21
22
23
, 2001.
The foregoing resolution is hereby approved this
day of
Judith Valles, Mayor
City of San Bernardino
24 Approved as to
25 form and legal content:
26 JAMES F. PENMAN,
27
28
City Attorney
By: Qh><A r. f~
o
CITY OF SAN BERNARDINO
Interoffice Memorandum
CITY CLERK'S OFFICE
Records and Information Management (RIM) Program
DATE:
December 19,2001
TO:
Mehran Sepehri, Senior Civil Engineer
FROM:
Michelle Taylor, Senior Secretary
RE:
Transmitting Documents for Signature - Resolution 2001-373
At the Mayor and Common Council meeting of December 17, 2001, the City of San Bernardino
adopted Resolution 2001-373 - Resolution awarding a contract to Lambeo Engineering, Inc., for
storm drain outlet structure repair on 40th Street Phase L per Plan No. 10320.
I am providing you with one certified copy of Resolution 200 l~ and four (4) original bound
contracts. Please obtain signatures where indicated and return one fully executed original
contract to the City Clerk's office as soon as possible.
Please be advised that the resolution and contract will be null and void if not executed
within 60 days, or by February 15,2002.
If you have any questions, please do not hesitate to contact me at ext. 3206. Thank you.
I hereby acknowledg.e receipt of the above mentioned documents.
Signed: -( /}'rV' ~
. ! z.- J u I tp 1 Please sign and return.
Date:
~
** FOR OFFICE USE ONLY - NOT A PUBLIC DOCUMENT **
RESOLUTION AGENDA ITEM TRACKING FORM
Meeting Date (Date Adopted): 1"2- \l-<:) \ Item #
Vote: Ayes 1-(.0 Nays G-
Change to motion to amend original documents:
\'6
Abstain
Resolution ~ __?OC> 1- 3 '13______
..-e--
Absent_~___
Reso. # On Attachments: I Contract term: ~
Note on Resolution of Attachment stored separately: X"'_
Direct City Clerk to (circle I): PUBLISH. POST. RECORD WCOUNTY
Date Sent to Mayor:
1"2--1 'b~ () \
Date of Mayor's Signature: 12-1"1--01
Date ofClerk/CDC Signature: 1'2--/4-0,
NullNoid After:
By: _=:._~_
Reso Log Updated
~/
Seal Impressed: ____ __-:::::__________~__.__
Date Memo/Letter Sent for Signature: 12 - 2.0 -<::, \
60 Day Reminder Letter Sent on 30th day:
90 Day Reminder Letter Sent on 45th day:
See Attached: / Date Returned: . I-~,,\ -0:>-
See Attached:
See Attached:
Request for Council Action & Staff Report Attached:
Updated Prior Resolutions (Other Than Below):
Updated CITY Personnel Folders (64t3, 6429, 6433,10584,10585, t2634):
Updated CDC Personnel Folders (5557):
Updated Traffic Folders (3985, 8234,655,92-389):
Copies Distributed to:
City Attorney ,,/
Parks & Rec.
Code Compliance Dev. Services ,./'
Police Public Services Water
Notes:
f'wI\D COl1'rf.Pc...1
Yes ./ No By
Yes No ~ By
Yes No --.L By
Yes No V- By
Yes No/
EDA
Finance /
-~
J118tfI.p,J
MIS
Others:
BEFORE FILING, REVIEW FORM TO ENSURE ANY NOTATIONS MADE HERE ARE TRANSFERRED TO THE
YEARLY RESOLUTION CHRONOLOGICAL LOG FOR FUTURE REFERENCE (Contract Term. etc.)
Ready to File: ~ Date: ).- \ -0:)