,CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
Dept: Facilities Management
O"""'''''L
hi .....1.11;-1
Subject: Resolution Authorizing the Purchasing
Manager to execute Change Order No. One with R.
Moody Construction, Inc, for adding two 3.5-ton
HV AC units and other minor contract changes in the
total amount of$7,930 at City Yards.
From: James Sharer, Director
Date: October 9,2001
Synopsis of Previous Couocil Actioo
12/18/00 Adopted Resolution No. 2000-350 for the execution of a contract with R. Moody Construction,
Inc. for remodeling ofthe City Yard Locker RoomlWarehouse at 234 North Mountaio View
Street in Sao Bernardino, in the total amount of $247,625.
Recommended Motion:
James Sharer
Adopt Resolution
Contact person:
Phone:
384-5244
Supporting data attached: Staff Report
Ward(s): 1
FUNDING REQUIREMENTS:
Amount: $7,930.00
Source: Facilities Management
~:06-0~~
~ara Pachon -
Council Notes:
17 i-C-.C:> ... 2t'0/ - ,'<,.~9
Agenda Item No.~
Ills/D}
.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
SUBJECT
Authorize the Purchasing Manager to execute Change Order No. One with R. Moody Construction, Inc. for
adding two 3.5-ton HV AC units and other minor contract changes in the total amount of$7,930 at City Yards.
BACKGROUND
On December 18, 2000, The City of San Bernardino Council adopted Resolution No. 2000-350 authorizing the
execution of a contract with R. Moody Construction, Inc. for the remodeling of the City Yard Locker-
Room/Restroom Facility at 234 North Mountain View, in San Bernardino. The remodel project included not only
the restroom and locker room facilities, but also roof reconstruction and kitchen upgrades.
During the reconstruction of the roof and prior to installation of the heating, ventilation, and air conditioning
(HV AC) unit, it came to staffs attention that it would be more efficient and lower overall operating (electrical)
costs to install two 3.5 ton HV AC units instead of adding one 3-ton unit to the existing 5-ton system that was 15-
years old. The increased capital cost for this change is $3,800.
Additionally, it was discovered that 400 square feet of concrete floor in the old shower and restrooms needed to
be replaced due to significant defects including cracking and lifting. The cost of this additional work is $1,600.
Previous to its current use as a locker room and warehouse, this facility was used as an automotive repair shop.
Occasionally, the hydraulic lifts, which raised the vehicles for inspection of their undercarriages, were lifted too
high for the sloped roof and damage to some of the structural columns and steel supports resulted. This damage
was noticed when the demolition phase of the roof began and repair was required. The cost to perform this work
amounts to $2,080.
An additional gas line for the cook top and a bank of cabinet drawers, at a cost of $450, are required to complete
the kitchen remodeling.
The total amount of these changes is $7,930,00.
FINANCIAL IMP ACT
The cost of this change order request is $7,930, which will be funded by the Facilities Management's budget
001-321-5706-0000.
RECOMMENDATION (S):
Adopt Resolution.
,..-'"
(
\......
C13
20
21 1/1
22
III
23
24 11/
25
C 26
27
28
~(Q)l?V
'.
RESOLUTION NO.
2
RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY 0
SAN BERNARDINO AUTHORIZING THE EXECUTION OF CHANGE ORDER NO
ONE TO THE CONTRACT WITH R. MOODY CONSTRUCTION, INC. FOR T
ADDITION OF TWO 3.5-TON HVAC UNITS AND OTHER MINOR CONTRA
CHANGES AT THE CITY YARD IN THE AMOUNT OF 57,930.00.
3
4
5
6
BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE CITY
7 OF SAN BERNARDINO AS FOLLOWS:
8
9
SECTION 1. The Purchasing Manager is hereby authorized and directed to execute
10 Change Order No. One to the existing contract with R. Moody Construction, Inc. for the addition
11 of two 3.5-ton HV AC units, a gas line, a bank of cabinet drawers, removal and replacement of
12 400 square feet of concrete, and repair of roof colurnns and supports at the City Yard Locker-
room Restroom Facility at 234 North Mountain View in San Bernardino per Specification No.
14
FOl-42 and per the quotations dated June 18,2001 for $3,800.00, June 4,2001 for $3,680.00,
15
16 and July 18,2001 for $450 in the total amount of $7,930.00.
17
SECTION 2. The authorization to execute the above-referenced Change Order No. One
18
to the contract with R. Moody Construction, Inc. for the aforementioned changes is rescinded if
19
not issued within sixty (60) days of the passage of this resolution.
c
c
C2
RESOLUTION ... AUTHORIZING EXECUTION OF CHANGE ORDER NO
ONE TO THE CONTRACT WITH R. MOODY CONSTRUCTION, INC. FO
2 ADDITION OF TWO 3.5-TON HVAC UNITS AND OTHER MINOR CONTRAC
CHANGES AT THE CITY YARD IN THE AMOUNT OF $7,930.00.
3
4
I HEREBY CERTIFY that the foregoing resolution was duly adopted by the Mayor and
Common Council of the City of San Bernardino at a meeting thereof,
held on the day of ,2001, by the following vote, to wit:
5
6
7 Council Members:
ABSTAIN
ABSENT
AYES
NAYS
8 ESTRADA
9 LIEN
10 MCGINNIS
SCHNETZ
SUAREZ
12 ANDERSON
13 McCAMMACK
11
14
15
16
City Clerk
17
18
The foregoing resolution is hereby approved this
day of
,2001.
19
20
2]
22
Judith Valles, Mayor
City of San Bernardino
Approved as to form and legal content:
23
;J.
24
25
"-
es F. Penman, City Attorney
27
28
c
c
c
PROPOSAL
R. MOODY CONSTRUCTION, INC.
License #774281
June 18,2001
JOB: Locker RoomIWarehouse
234 S. Mountain View
San Bernardino, CA
City of San Bernardino
300 North D Street
San Bernardino, CA 92418
OWNER:
Attn: Jim Sharer
Here are your three options for H.V.AC. at the locker rooms per Ken
We propose to furnish and instal1 all materials necessary to do the following:
I. Original plan per our quote of adding one (3) ton unit to go with
existing unit and all new duct work. $12,100.00
.'"
Removing existing unit that is very old and installing (1) new
Carrier 7.5 ton unit with aU new ducts and registers.
V. Removing existing unit and installing (2) new 3.5 ton Carrier
gas/electric split systems. This will allow you to control the
temperature in the locker roomlbathrooms separate from the
lunch and meeting rooms.
All of these options include gas piping and condensate drains as needed.
Respectfully submitted:
T ?--I~~~
Ronald L. Moody :Si/,
$15,200.00
$15~::: i
f ~?f{)O-
39821 Lincoln Street, Cherry Valley, CA 92223
(909) 769-3752 (909) 769-3712 fax
PROPOSAL
C R. MOODY CONSTRUCTION, INC.
License #774281
June 4, 2001
JOB: Locker RoomIWarel1ouse
234 S. Mountain View
San Bernardino. CA
OWNER: City of San Bernardino
300 North D Street
SanBernardino. CA 92418
Attn: Jim Sharer
We propose to furnish and instaI1 aU materials necessary to do the following:
c
I. Remove and replace 400 s.t: of concrete floor at
Old shower and rcstrooms:
$ 1,600.00
$ 2,080.00
2. Replace bent steel pur1ios and structural columns:
TOTAL
S 3,680.00
Respectfully submitted:
n-l~-7
Ronald L. Moo Y. ~ent
c
39821 Lincoln Street, Cherry Valley, CA 92223
(909) 769-3752 (909) 769-3712 fax
/""'"
\-.
c
c
FROM : l"OODY Ct>l5TRUCT I Cl'l
PHJNE NO. : 'l097693712
Jul. 18 2001 08:53AM p~
[-..--------
R. MOODY CONSTRUCTION, INC.
License #774281
PROPOSAL
July 18,2001
JOB: Locker Room/Warchouse
234 S. Mountain Vicw
San Bernardino, CA
OWNER: City of San Bernardino
300 North D Street
San Bernardino, CA 92418
Attn: Jim Sharer
We propose to furnish and install all materials necessary to do the foUowing:
Cost increase to insta11 additional gas !iDe for cook top and add blIIlk of drawers in cabiDct.
TOTAL
$ 450.00
Respectfully submitted:
n--l~
Ronald L. M Y-, ident
39821 Lincoln Street, Cherry Valley, CA 92223
(909) 769-3752 (909) 769-3712 fax
.
** FOR OFFICE USE ONLY - NOT A PUBLIC DOCUMENT **
RESOLUTION AGENDA ITEM TRACKING FORM
Meeting Date (Date Adopted): \ \-'1--0\ Item # 2Z Resolution # 2 <J()\ -339
Vote: Ayes 1- (p Nays '\ Abstain .-e--- Absent B-
Change to motion to amend original documents: -
Reso. # On Attachments: / Contract term: -
Note on Resolution of Attachment stored separately: ===----
Direct City Clerk to (circle I): PUBLISH, POST, RECORD W/COUNTY
Date Sent to Mayor: It-\ - 0 ,
Date of Mayor's Signature: \ 1-, -() I
Date of ClerklCDC Signature: \ \- ,-D \
Date mo/Letter Sent for Signature:
60 Day Reminder Letter Sen 0
90 Day Reminder Letter Sent on 45th day:
See Attached:
See Attached:
ched:
Request for Council Action & StatT Report Attached:
Updated Prior Resolutions (Other Than Below):
Updated CITY Personnel Folders (6413, 6429, 6433,10584,10585,12634):
Updated CDC Personnel Folders (5557):
Updated Traffic Folders (3985, 8234, 655, 92-389):
Copies Distributed to:
City Attorney /
Parks & Rec.
Code Compliance
Dev. Services
Police Public Services
Water
Notes:
NullNoid After: <OCl Oi\/.s } 1-4---02...
By: -
Reso. Log Updated:/ _
Seal Impressed: /
Date Returned: -
Yes 1 No By
Yes No --L By
Yes NOL By
Yes No ;: By
Yes No_ By
EDA
Others:
Finance /
fio,cll{11 ~
MIS
BEFORE FILING. REVIEW FORM TO ENSURE ANY NOTATIONS MADE HERE ARE TRANSFERRED TO THE
YEARLY RESOLUTION CHRONOLOGICAL LOG FOR FUTURE REFERENCE (Contract Term, etc.)
Ready to File: IY\\ Date: $
Revised 01/12/01