CITY OF SAN BER"ARDINO -
REQUESTII:OR COUNCIL ACTION
File . 7.37-65
From:
ROGER G. HARDGRAVE
Subject:
Approval of Plans & Authorization
to Advertise for Bids - Rehabili-
tation of Johnson Hall Community
Center, per Plan No. 8800
,.r "pt:
"bate:
Public Works
8-24-92
Synopsis of Previous Council action:
June, 1990 -- Allocation of $40,000 from CDBG Funds, approved in
1990/91 Budget for renovation of Johnson Hall Com-
munity Center.
Recommended motion:
That the plans for rehabilitation of Johnson Hall Community
Center, in accordance with Plan No. 8800, be approved: and the
Director of Public Works/City Engineer authorized to advertise
for bids.
c,
cc: Shauna Clark
Ken Henderson
Annie Ramos
Contact person:
Roqer G. Hardqrave
Phone:
Supporting data attached: Staff Report
Ward:
5025
6
FUNDING REQUIREMENTS:
Amount: $21,500 (Community D~velopment Block Grant Funds)
Source: (Acct, No.)
munity Center
Acct, Descri tion Renovation of Johnson Hall Com-
Finance:~~u-, r l!edf 7;~
Council Notes:
C'.
"
75.0262
Agenda Item No
1
CITY OF SAN BER"~RDINO - REQUEST"'.tJR COUNCIL ACTION
~
STAFF REPORT
1"
\,
Plans for the rehabilitation of Johnson Hall Corrununity
Center have been prepared by the Public Works Department, and the
project is ready to be advertised for bids. The project
consists, in general, of replacing the ceiling lights and acous-
tical tiles, installing a drinking fountain, and various other
items.
Below is an estimate of the total project cost:
Construction Contract
Engineering & Inspection (W.O. #1470)
Sub-Total
Contingencies (20%)f
TOTAL ESTIMATED PROJECT COST
$ 16,485
1,715
$ 18,200
3,300
$ 21,500
f1
,-,jo'
An amount of $40,000 was allocated in CDBG funds for the
rehabili tation of Johnson Hall Corrununi ty Center. Contracts for
installation of an air-conditioning system and tubular steel
fence have been financed from this amount. The available balance
is about $19,000, which means that supplemental funds in the
amount of $2,500 may be needed to fully finance the total esti-
mated project cost. We recorrunend that the provision of supple-
mental funds be deferred until the bids are opened and the actual
low bid price is known.
We recorrunend that the plans be approved and authorization
granted to advertise for bids.
"...
I
....1'
8-24-92
75-0264
~