CITY OF SAN BER,QRDINO - REQUEST P6R COUNCIL ACTION
, File No. 3.14-18
Approval of Plans & Authorization
From: ROGER G. HARDGRAVE Subject: to Advertise for Bids - Installa-
tion of Sewer Main in Redlands
Dept: Public Works Blvd., from Hunts Lane to Club
Way, per Plan No. 8774
Date: 9-02-92
Synopsis of Previous Council action:
June, 1991 - Allocation of $200,000, under Account No. 245-365-
57885 in the 1991/92 Sewl'!r Line Construction Fund
approved.
02-03-92 Resolution No. 92-42 adopted authorizing execution of
an Agreement with URS Consultants, Inc. for
professional design services.
Recommended motion:
That the plans for installation of a sewer main in Redlands
Boulevard, from Hunts Lane to Club Way, in accordance with Plan
No. 8774, be approved; and the Director of Public Works/City
Engineer be authorized to advertise for bids.
cc: Shauna Clark
Bernie Kersey
Contact person:
Roqer G. Hardqrave
Phone:
5025
Supporting data attached:
Staff Report
Ward:
3
FUNDING REQUIREMENTS:
Amount: $145,000 (Sewer Line Construction Fund)
Source: (Acct. No.)
245-365-57885
Acct. Descri tion
Installati
/
Sewer Main -
Redlands Boulevard
Finance:
Council Notes:
-,c; n"<':"
Anpnrl~ Itpm Nn
5~/
CITY OF SAN BER~DINO
~
- REQUEST ~R COUNCIL ACTION
STAFF REPORT
Plans for the installation of a sewer main in Redlands
Boulevard have been prepared by the Consulting Engineer, and the
project is ready to be advertised for bids. The project
consists, in general of removing the 457 feet of 8-inch sewer
main, and installing 18-inch sewer main between Hunts Lane and
Club Way.
Below is an estimate of the total project cost:
Construction Contract
Consultant's Design Fee
Construction Engineering (W.O. #1964)
Sub"Total
Contingencies (15%)t
TOTAL ESTIMATED PROJECT COST
$ 90,270
18,830
17,170
$ 126,270
18,730
$ 145,000
An amount of
No. 245-365-57885,
project.
$200,000 has been allocated, under Account
to finance the costs incurred for this
We recommend that the plans be approved and authorization
granted to advertise for bids.
URGENCY CLAUSE:
The pavement rehabilitation proj ect on Redlands Boulevard has
been deferred until this sewer project is ready to go to bid. It
is necessary to secure approval to advertise as soon as possible
in order to allow the rehabilitation of the pavement to be com-
pleted prior to the rainy season.
9-02-92