CITY; OF SAN BER~DINO - REQUF~~TNoQ~t~6~UNCIL ACTION
Date:
7-23-92
Approval of Contract Change Order
Subject: No. ONE - Construction of Park
& Street Improvements - Buckboard
Park, per Plans No. 7539 & 7662
---VALLEY CREST LANDSCAPE, INC.
From: ,ROGER G. HARDGRAVE
Dept:
Public Works
Synopsis of Previous Council action:
June, 1986 - Allocation of $10,000 in 1985-86 Park Construction Fee
Budget, for development of concept plan for Buckboard
Park, approved.
June, 1986 Application of Supplemental funds in the amount of
$15,000, for development of concept and design plans
for Buckboard Park, approved in 1986-87 Park Construc-
tion Fee Budget.
10-05-87 Resolution No. 87-366 adopted authorizing the
execution of an agreement with Kammeyer & Associates
for professional design.
June, 1988 Allocation of $250,000 in 1988-89 Park Construction
Fee Budget, approved. (Cont. on 2nd Page)
Recommended motion:
That Change Order No. ONE to the contract with Valley Crest
Landscape, Inc. for construction of Park & Street Improvements for
Buckboard Park, in accordance with Plans Nos. 7539 and 7662, be
approved; to authorize the Contractor to furnish and install 92
additional trees, and install 21,412 sq. ft. of sidewalk at an
increase in the contract price of $44,103.44; from $390,015.26 to
$434,118.70.
cc: Shauna Clark
Annie Ramos
Contact person:
Roger G. Hardgrave
Phone:
Supporting data attached: Staff Report, CCO ill
Ward:
5025
5
FUNDING REQUIREMENTS:
Amount:$44.103.44 /Park Construction Fee Fund)
Source: (Acct. No'! 243-363-57518
Acct. Oescri tion oard Park
Council Notes:
75-0262
Agenda Item No.
10
.--..
o
~e No. 6.14-68
'SYNOPSIS OF PREVIOUS COUNCIL ACTION
Cant:
June, 1989 Allocation of $200,000 in 1989-90 Park Construction
Fee Budget approved.
12-18-89 - Finding made that scope and concept has been changed,
and payment of an additional $1,020 to Kammeyer &
Associates approved.
June, 1990 Allocation of $110,000, in 1990-91 Park Construction
Fee Budget, approved.
June, 1991 - Allocation of $200,000 in 1991-92 Park Construction
Fee Budget approved.
01-06-92 - Plans approved and authorization granted to advertise
for bids.
06-01-92 - Resolution No. 92-182 adopted awarding a contract to
Valley Crest Landscape for the low bid price.
7-23-92
'__'I--
CITY -OF SAN BERNO'DINO - REQUEST ~ COUNCIL ACTION
STAFF REPORT
The plans and specifications for the contract presently
under construction by Valley Crest Landscape, Inc. are for basic
park improvements, such as grading, security lighting, lawn,
irrigation system, street improvements, and a portion of the
trees.
Funds are available to finance the inclusion of some
amenities in the contract, in particular, those that could not be
easily installed in the future after the basic improvements are
installed. Items that could be installed along with the basic
improvements in a more cost effective manner are the balance (92)
of trees shown on the concept plan, and the sidewalk through the
park.
The Contractor has agreed to furnish and install the
additional 92 trees at the unit bid price of $55.80. A price
quote of $1.B2 per square foot has been provided for the 21,412
sq. ft. of sidewalk. We feel that this is a fair and reasonable
price, since sidewalk regularly costs more than $2.00 per square
foot.
The low bid was $125,488.74 (24.3%) under the Engineer's
Estimate. These funds could be used to finance the estimated
cost of $44,103.44 for Change Order No. One.
The Department of Parks and Recreation is in favor of
installing the additional trees and sidewalk at this time.
7-23-92
15-0264
-"
-
~
-
-- . --
c
o
CITY 01' SAN BBRNARDINO
DEPARTMBNT 01' PUBLIC WORKS
ENGINEERING DIVISION
projeot:BUCKBOARD PARK
I'ile No.:
Plan No.:
Date:
6.14-68
7539/7662
7/22/92
CONTRACT CHANGE ORDER NO. ONE
TO: VALLEY CREST LANDSCAPE
1920 South Yale Street
Santa Ana, CA 92704
Gentl_en:
You are hereby authorized and directed to perform the following
work:
1). Plant an additional 92 Trees, to be installed according to
plans and specification, as directed by the Resident Engineer, at
the original contract price of $55.80 each, for a total cost of
$5,133.60.
2). Install approximately 21,412 Square Feet of Sidewalk, per plans
and specifications, at the direction of the Resident Engineer, at
a cost of $1.82 per Square Foot, for a total cost of $38,969.84.
Total Eztra Work Cost added tOiContraot .........$
44.103.44
Previous Contract Price .........................$
390.015.26
Amended Cost Price ..............................$
434,118.70
Additional time to oomplete Contract due to Change Order 20 Workina
Davs
CONTRACTOR
CITY 01' SAN BERNARDINO
Acoepted
By:
Recommended
By:
Title:
ROGER G. HARDGRAVE DATE
Director of Public Works/Ci ty Enqr
Date: