CITY OF SAN BER~DINO - REQUE~~eQ~ 1~~UNCIL ACTION
From:
Subject:
Approval of Contract Cnange Order
No. 8 - Pavement Rehabilitation
on Waterman Avenue, from Mill to
5th Street, per Plan No. 8038 -
E. L. YEAGER CONSTRUCTION
ROGER G. HARDGRAVE
Date:
7-15-92
Public Works/Engineering
Dept:
Synopsis of Previous Council action:
June, 1988 Allocation of $100,000 in 1988/89 Street Construction
Fund Budget approved.
Resolution No. 89-197 adopted authorizing execution
of agreement with ASL Consulting Engineers for
design.
Supplemental allocation of $60,000 approved.
Supplemental allocation of $1,498,000 approved.
Plans approved and authorization granted to advertise
for bids.
Resolution No. 91-128 adopted authorizing execution
of Program Supplement No. 65.
Resolution No. 91-126 adopted authorizing execution
of an Agreement with the County. (Cont. on 2nd Page)
06-19-89
June, 1989
June, 1990
02-18-91
04-15-91
04-15-91
Recommended motion:
That Change Order No. EIGHT to the contract with E. L. Yeager
Construction Company, Inc., for the pavement rehabilitation on
Waterman Avenue, from Mill to Fifth Street, in accordance with Plan
No. 8038, be approved; to authorize the Contractor to regrade and
repave the existing parking lot at the Marine-Navy Reserve Center
to match new improvements on Waterman Avenue, at an increase in the
contract price of $5,379.53; from $1,180,820.79 to $1,186 32.
cc: Shauna Clark
Contact person:
Phone:
5025
Supporting data attached:
FUNDING REQUIREMENTS:
Roqer G. Hardqrave
Staff Report,
Contract Chanqe Order. *8
1
Ward:
Amount: $5.379.53 (Street Construction Fund)
Source: (Acct, No.)
242-362-57667
Acct, Descri tion Waterman Avenue
from Mill Street to 5th Street
Council Notes:
75-0262
7
Agenda Item No,
ClTY.OF SAN BERNCjlDINO - REQUEST 'CfI COUNCIL ACTION
STAFF REPORT
The project plans direct the installation of new curb,
gutter and driveway approaches in front of the Marine-Navy
Reserve Center located on Waterman Avenue, south of 4th Street.
After the new curb, gutter, and driveway approaches were
installed, the existing parking lot was found to be considerably
lower than the new improvements and, therefore, was unusable. In
order to provide vehicular access to the property, it was
necessary to remove and replace the pavement for the existing
parking lot, at a grade to match the newly placed curb, gutter,
and driveway approaches.
The reconstruction of the Marine-Navy Reserve Center
parking lot was necessary in order to provide adequate and safe
access. Caltrans personnel has expressed the opinion that this
work wil1 be eligible for financing 86% of the cost, with
Federal-Aid Urban Funds.
The Contractor has quoted a net price of $5,379.53 to
reconstruct and pave the parking lot.
The project has a balance of $148,340.21 in contingency
funds, which can be used to finance the cost of this extra work.
We recommend that this change order be approved.
SYNOPSIS OF PREVIOUS COUNCIL ACTION Continued
07-15-91
Resolution No. 91-325 adopted awarding a contract to
E. L. Yeager.
Resolution No. 91-391 adopted authorizing execution
of Program Supplement No. 66.
Contract Change Order No. 7 approved, widening the
Northeast corner of 5th/Waterman Avenue for a total
price of $18,288.82, increasing the contract from
$1,162,531.97 to $1,180,820.79.
09-03-92
06-01-92
7-15-92
'5.0264
,
o
.:)
COIlTRACT CHAJlGB ORDBR BO. 8 REV BO.
ROAD Waterman Avenue-Mill to 5th
FBD BO.
TO: E. L. Yeager
You are hereby directed to make the herein described changes from the plans and
specifications or do the following described work not included in the plans and
specifications on this contract. NOTE: This change order is not effective until
aooroved bv the state Hiahwav Enaineer
Description of work to be done, estimate of quantities, and prices to be paid.
Segregate between additional work at contract price, agreed price and force
account. Unless otherwise stated, rates for rental of equipment cover only such
time as eauioment is actual Iv used and no allowance will be made for idle time.
The last percentage shown is not accumulated increase of decrease from the
original quantity in the Engineers Estimate.
EXTRA WORK AT FORCB ACCOUBT:
SUPPL. BO.
SHEBT 1 OF 1
CONTRACT BO. 8038
Remove and replace an existing parking
Center at 284 North Waterman Avenue,
improvements on Waterman Avenue.
lot, located at the Marine-Navy Reserve
to match the newly constructed street
BSTIMATBD COST DBCREASB S
By reason of this order the
working days
IBCREASB S 5.379.53
time of completion will be adjusted as follows:
Submitted J:)y:
Resident Bngineer,
Date:
~pproval Recommended:
Date:
\pproved:
city Bngineer
Date:
ie the undersigned contractor, have given careful consideration to the change
)roposed and hereby agree, if this proposal is approved, that we will provide all
iquipment, furnish all material, except as may otherwise be noted above, and
lerform all services necessary for the work above specified, and will accept as
:ull oavment therefor the orices shown above.
,ccepted Date: Contractor:
ly: Title:
:f the contractor does not sign acceptance of this order, his attention is
lirected to the requirements of the specifications as to proceeding with the work
,nd filing a written protest within the time therein specified.