CITY OF SAN BERNARDINO -
FQe No. 7.3716 & 7.3725 ...J
REQUEST FOR COUNCIL ACTION
From:
ROGER G. HARDGRAVE
REC'O.-ADMlMajQif. Approval of Plans & Authorization
to Advertise for Bids--Construction
Pu b 1 i c Works/Eng i neer i ngl981 SEP I 0 ,\:,~ :D' 430f Horseshoe Pitch i ng Pit &
Storage Building at Center for
Individuals with Disabilities,
per Plan No. 7279
r;f~
Dept:
Date:
8-26-87
Synopsis of Previous Council action:
June, 1985
June, 1986
Allocation of $10,000. for construction of a horse-
shoe pitching pit, approved in the 1985~86 CDBG
Program.
Allocation of $20,000, for construction of a 270-
sq. ft. storage room, approved in the 1986-87
CDBG Program.
Recommended motion:
That the plans for construction of a storage room and horseshoe
pitching pit at the Center for Individuals with Disabilities, in
accordance with Plan No. 7279, be approved; and the Director of
Public Works/City Engineer authorized to advertise for bids.
cc: Ray Schweitzer
Warren Knudson
Ken Henderson
Annie Ramos
FUNDING REQUIREMENTS:
Staff Report
Amount: $27,200
Ward:
5025
NIA
Contact parson:
Roqer G. Hardqrave
Phone:
Supportlnll date ettached:
Source: (ACCT.
( ACCT.
NO.) 121-544-57555 & 57557
DESCRIPTION) Construction of Storage
Finance: J~'ll=~
1", (J,J...,J ~
Building & Horseshoe Pitching Pit
Council Notal:
-
Agenda Item No.
~
I,
}S.Q161
CI,(; OF SAN BERNARDIQ) - REQUEO FOR COUNCIL ACTJN
STAFF REPORT
Plans for these improvements have been prepared by the
Engineering Division, and the project is ready to be advertised
for bids.
The project will consist of constructing a 234 sq. ft.
storage building and a horseshoe pitching pit. A 240 sq. ft.
storage building will be included as Additive Alternate "A".
This second storage building will be included in the contract
if sufficient funds are available.
Listed below is an estimate of the total project cost:
Construction Contract
Storage Bu il ding
Horseshoe Pit
$13,000
7,500
$ 20,500
Engineering & Inspection
W.O. #1343 (Storage Bldg.) $ 2,000
W.O. #1470 (Horseshoe .1,200
Pit)
3,200
Sub-Total $
Contingencies (15%)t
23,700
3,500
TOTAL ESTIMATED PROJECT COST $
27,200
An amount of $20,000 has been allocated, under Account
No. 121-544-57557, for the storage building, and $10,000, under
Account No. 121-544-57555, for the horseshoe pitching pit, for
a total amount available of $30,000.
A finding that this project is needed for health and
safety reasons will not be needed, since it is not located
within the City limits.
Environmental review was handled by the County, since ~
the project is within their jurisdiction.
We recommend that the plans be approved and authoriza-
tion granted to advertise for bids.
---
8-26-87
15-0264