CITY OF SAN BERIORDINO
From:
ROGER G. HARDGRAVE
- REQUEST ())R COUNCIL ACTION
File No. 2.144
Approval of Contract Change Order
Subject: O. FOUR Assessment District
No. 987, Chestnut Avenue Storm
Drain, Zone 2, Plan No. 8163 -
Place Concrete and Rip-Rap
--RIVERSIDE CONSTROCTION
Dellt:
Public Works/Engineering
Date:
6-03-92
Synopsis of Previous Council ection:
02-06-89 -- Authorization granted to proceed with Assessment
District No. 987, Palm Avenue Box culvert and traffic
signals.
02-06-89 -- Authorization granted to proceed with Assessment
District No. 988, Chestnut Avenue Storm Drain and
Debris Basin.
03-20-89 Authorization granted to proceed with assessment
district for improvement of Palm Avenue.
04-03-89 Authorization granted to combine Assessment District
No. 988 and Palm Avenue Improvements into Assessment
District No. 987.
05-15-89 -- Resolution No. 89-44 adopted authorizing execution of
an agreement with GFB - Friedrich & Associates, Inc.
for assessment enqineerinq services. (Cont. on 'nn P~qpl
Recommended motion:
That Change Order No. FOUR to the contract with Riverside Con-
struction for the construction of a Storm Drain and Retention
Basin, located at Meechum Canyon, in accordance with Plan No. 8163
be approved, to authorize the Contractor to place concrete and
rip-rap at the water chute of the retention basin, for an increase
in the contract price of $19,895.00, from $2,556,356.22 to
$2,576,251. 22.
cc: Shauna Clark
~G
Signature
Contect person: Roger G. Hardgrave
Staff Report,
Supporting date attached: CCO 1I4
Phone:
502'i
Ward:
c;
FUNDING REQUIREMENTS:
Amount:$19.895.00 (Assessment Dist. No. 987)
Source: (Acct. No.)
251-663-53925
Acct. Oescri tion
Finance:
Council Notes:
75-0262
Agenda Item No
/3
o
o
File 2.144
SYNOPSIS OF PREVIOUS COUNCIL ACTION (Cont.)
05-15-89 -- Resolution No. 89-148 adopted authorizing execution of
an agreement with Stone and Youngberg for investment
banking services.
05-15-89 -- Resolution No. 89-150 adopted authorizing execution of
an agreement with CM Engineering Associates for
engineering design services for the Chestnut Avenue
Storm Drain.
05-18-89 -- Resolution No. 89-146 adopted setting a surcharge fee
of $ 0 . 09 per square foot for Chestnut Storm Drain
area.
05-07-90 -- Resolution No. 90-164 adopted authorizing execution of
a Common Use Agreement with County for Palm Avenue Box
Culvert at Cable Creek Channel.
05-07-90 -- Negative Declaration adopted for Palm Avenue improve-
ments, box culvert and traffic signals, Public Works
Project No. 90-08.
05-21-90 -- Resolution No. 90-188 adopted authorizing execution of
an Agreement with Orrick, Herrington and Sutcliffe for
bond counsel services, and rescinding Resolution No.
89-148.
06-05-90 Resolution No. 90-212 adopted adjusting Chestnut
Avenue drainage surcharge to $0.13 per sq. ft.
06-18-90 Negative Declaration adopted for Chestnut Avenue Storm
Drain and Debris Basin Public Works Project No. 90-07.
10-15-90 Resolution No. 90-416 adopted authorizing execution of
an agreement with Department of Fish & Game for
streambed alterations.
03-11-91 Resolutions No. 91-69 through 74 and 80 adopted
relating to establishment of Assessment District No.
987.
07-15-91 Resolution No. 91-335 adopted awarding a contract to
Riverside Construction, for the low bid price of
$2,469,567.69.
08-19-91 -- Resolution No. 91-376 adopted authorizing contractual
services of Lloyd Weverka as resident engineer.
6-03-92
CITY OF SAN BERtORDINO - REQUEST Q)R COUNCIL ACTION
STAFF REPORT
Construction of the retention basin at Meechum Canyon, as
part of the Chestnut Avenue Storm Drain System, will provide'
protection from possible flooding of the area.
The water chute at the top of the retention basin,
directly above the spillway, was constructed to provide the
retention basin with an overflow mechanism, preventing the walls
of the retention basin from being breached.
Concrete and rip-rap were originally included in the
plans, in order to control erosion and prevent potential damage
~n case of an overflow from the basin. However, these items were
deleted in a cost saving measure. The Contractor has stated that
he will not assume responsibility for any damage to the spillway,
if the concrete and rip-rap are not constructed.
The project is nearing completion, and there are suffi-
cient contingency funds to finance this extra work. Installation
of the concrete and rip-rap will reduce the City's exposure for
maintenance costs in the future.
The Contractor has quoted a price of $19,895.00 for con--
structing the concrete and rip-rap protection at the water chute.
We have reviewed the quoted price, and feel that it is fair and
reasonable for the work involved.
There is a current balance of $335,711.81 in contingency
funds, that will be used to finance the cost for this extra work.
We recommend that the Contractor be authorized to perform
these items of extra work.
6-03-92
75-0264
o
o
C I T Y
o F
SAN
BERNARDINO
DEPARTMDI'1' OF PUBLIC WOUB
ENGINEERING DIVISION
Project: Chestnut Avenue storm Drain
File No.:
Plan No.:
Date:
2.144
8163
5/26/92
CONTRACT CHANGE ORDER NO. FOUR
TO: Riverside Construction Company
111 Main street, P.O. Box 1146
Riverside, CA 92502
Gent18ll8D:
You are hereby authorized and directed to place concrete and rip-
rap, 1.5 feet thick, at the water chute of the Retention Basin,
located at Meechum Canyon, at the aqreed price of $19,895.00.
Total Extra Work Cost added to Contract .........$ 2.55'.35'.22
Previou8 Contract Price .........................$
19.815.00
aaended Coat Price ............................... 2.57&.251.22
Additional ti.e to complete Contract due to Chanqe Order -0-
CONTRACTOR
CITY OF SU BERJlARDIIIO
Accepted
By:
Reco_ended
By:
Title:
ROGER G. HARDGRAVE DATE
Director of Pulllic Works/City Enqr
Date: