HomeMy WebLinkAbout12-Development Services CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION Date: February 8, 2000 ORIGIlJAL 1. 7172 Subject: Authorization to execute Contract Change Order No.1 with Signal Maintenance Inc.-Installation of Traffic Signal at the Intersection of Tippecanoe Ave. and Laurelwood Ave. per Plan No. 10012. MCC Date: 02-22-2000 From: Michael E. Hays Dept: Development Services File: Synopsis of Previous Council Action: July 6, 1999 Allocated $145,000 from the Traffic Systems Fund as part of the FY 1999-2000 Budget to fund a traffic signal and median at Tippecanoe/Laurelwood. August 2, 1999 Approved installation of temporary delineators for a period of 6 months and approved installation of a traffic signal at the intersection of Tippecanoe Avenue and Laurelwood Drive. August 9,1999 Approved Plan No. 10012 for installation ofa traffic signal at the intersection of Tippecanoe Avenue and Laurelwood Drive, and authorized the Director of Development Services to advertise for bids. January 10, 2000 Resolution 2000-6 adopted awarding construction contract to Signal Maintenance Inc. in the amount of$81,260.00. Recommended Motion: That Contract Change Order No. One to the contract with Signal Maintenance Inc. be approved for additional conduit, pull boxes and additional concrete R & R, with credit for a change in conduit size, for a total Change Order amount of $5,855.00, increasing the contract total from $81,260.00 to $87,115.00. ~ Michael E. Hays Contact person: Michael Grubbs, Sr. Civil Engineer Phone: 5179 Supporting data attached: Staff Report, CCO #1 & Letter Ward: 3 FUNDING REQUIREMENTS: Amount: $5,855.00 Source: (Acct. No.) 250-370-5504-7172 Acct. Description: Tippecanoe/Laurelwood- Install Traffic Si~nal and Median Finance: d-~(J Council Notes: Agenda Item No. I/)..J CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION STAFF REPORT Subject: Authorization to execute Contract Change Order No. I with Signal Maintenance Inc.- Installation of Traffic Signal at the Intersection of Tippecanoe A venue and Laurelwood A venue per Plan No. 10012. Background: On January 10, 2000, the City entered a contract with Signal Maintenance Inc. for the Installation of Traffic Signal at the Intersection of Tippecanoe A venue and Laurelwood Avenue per Plan No. 10012. At the time of bidding, it was recognized that some changes may be needed to the design to insure consistency between the signal design and the planned realignment of Rosewood Drive to Laurelwood Drive in connection with a redevelopment project presently under study by the Economic Development Agency. The EDA project has progressed faster than expected, therefore, Staff has revised the signal plan to accommodate the realignment, as much as possible, within the existing right-of-way. The Contractor has provided a price for this revision (see attached letter), and we believe this to be a fair and reasonable price. Contract Change Order No. I consists of the following items: Descn tion of Chan e Item I: Additional conduit, ull boxes and additional concrete R & R. Item 2: Credit due to change in conduit size for conduit shown as 2" and now bein chan ed to 3" which will sim Ii installation of wirin . TOTAL COST Cost $6,350.00 (495.00) $5,855.00 A copy of Change Order No. I is attached which will increase the contract total from $81,260.00 to $87,115.00. Financial Impact: Sufficient funding for this Change Order is available from the $145,000.00 budgeted in Account No. 129-367-5504-7172 (Tippecanoe/Laurelwood-Install Traffic Signal and Median). Recoimnendation: Staff recommends approval of Contract Change Order No. 1. C I T V 0 F San Bernardino DEVELOPMENT SERVICES DEPARTMENT M I C MAE L E. MAY. DIRECTOR CONTRACT CHANGE ORDER NO.1 FILE NO. 1.7172 DATE: 02/08/2000 PROJECT: InstaIlation of a Traffic Signal at the Intersection of Tippecanoe Avenue and Laurelwood Drive per Plan No. 10012 TO: SIGNAL MAINTENANCE, INC. 2283 Via Burton Street Anaheim, CA 92806-1203 GENTLEMEN: You are hereby compensated for performing the additional work as follows: Description of Change Cost Item 1: Additional conduit, pull boxes and additional concrete R $6,350.00 &R Item 2: Credit due to change in conduit size for conduit shown $ (495.00) as 2" and now being changed to 3" which will simplify installation of wirinj.(. TOTAL COST $5,855.00 Total Cost Added to the Contract ................................... $ 5,855.00 Previous Contract Price ............................................... $ 81,260.00 Amended Cost Price ................................................... $ 87,115.00 Additional time to complete Contract due to Change Order o Workin!!: Davs 300 NORTH '0' STREET, SAN BERNARDINO, CALIF 92418-0001 (808) '....5357. FAX: 3'''-50'0 I PUB Lie W 0 R K. PAX: 3'4-5151 SIGNAL MAINTENANCE, INC. Contractor Accepted CITY OF SAN BERNARDINO DEVELOPMENT SERVICES Approved By: By MICHAEL HAYS, Director Title: Date: Date: . .-.....- II PEEK SIgnal .....inten8nCe 'neo ConslnlCtlon llepar1ment 2283 Via Burton St. Anaheim. California 92806 Telephone: (714) 563-4000 Faca,mile: (714) 563-3178 I :.... j s~ SIGNAL MAIfflHANC& INC. , UC.# 679111 TRAFFIC January 20, 2000 City of San Bernardino Department of Development Services Division of Public Works 300 North '0' Street San Bernardino, CA 92418-0001 RE: TRAFFIC SIGNAL INSTALLATION g TIPPECANOE AND LAURELWOOD REVISED PLANS Gentlemen: . The revised plans received with revisions on 1/4100 have been reviewed and the following determination and proposal are hereby submitted. The cost for the additional conduit, pull boxes and additional concrete R & R is Lump Sum $ 6,350.00. In addition to the above a credit of $ 495.00 is due for the Change in conduit size for conduit already shown as 2" and now being changed to 3". The total additional cost for the changes made is LUMP SUM S 5,855.00. If this is acceptable, please issue an appropriate Contract Change Order at your earliest convenience. Sincerely, PEEK TRAFFIC - SIGNAL MAINTENANCE, INC. 4~~~:'~" Martin Eichmann Construction Manager Peek i$ a Thermo Power compatly