CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES DEPARTMENT
INTEROFFICE MEMORANDUM
To:
Judith Valles, Mayor
From:
Michael E. Hays, Director of Development Services
Subject:
Highland Avenue Street Tree Project: Default of Colarossi Construction-
Request for Continuance from February 22, 2000 Council Meeting to
March 20, 2000.
Date:
February 10,2000
Copies:
Fred Wilson, City Administrator
File:
7.37-5040
The Mayor and Common Council originally heard this item on January 24, 2000, and the
backup was distributed at that time. At the request of Colarossi Construction, its attorney and
the attorney for the bonding company, the item was continued to February 22, 2000.
On January 14, 2000 and again on February 10, 2000, staff met with the attorneys for
Colarossi Construction and its bonding company. Negotiations are continuing and additional
time is necessary to coinpletely review new documentation )Jeing supplied by the contractor.
Upon completion of negotiations, staff will bring the item before the Mayor and Common
Council with a recommendation. We anticipate that the additional review and negotiations will
be completed by March 20, 2000. Therefore, we are requesting that the item be continued
until the regular meeting of the Mayor and Common Council on March 20, 2000.
'It 31
t2.J~JOD
"';::~.;.
,---,"
'-
\
,
\
I,
I
i
~
!
~ OF SAN BERNARD~O - REQUEST FOR COUNCIL ACI10N
From: Michael E. Hays
Subject: Declaration of Default by
Contractor and Cancellation of Contract-
Installation of Street Trees along Highland
Avenue from "E" Street to WatefIlliU1
Avenue (Colarossi Construction) per PIan
No. 9845.
MCC Date: 01-24-2000
Dept: Development Services
Date: January 18,2000 (G(Q) [P)W
File: 7.37-5040
Synopsis of Previous CoUDcil Action:
May 3, 1999 -- authorized the Director of Development Services to Advertise for Bids for the
Installation of Street Trees along Highland Avenue from "E" Street to Waterman Avenue.
August 2, 1999 - Resolution A warding Contract to Colarossi Construction for lnstaIIation of
Street Trees along Highland Avenue from "E" Street to Waterman Avenue in the amount of
$158,433.
Recommended Motion:
That the Mayor and Common Council declare Colarossi Construction in default and cancel the
Contract pursuant to Section 6-4 "Default by Contractor" of the Standard Specifications for
project "Installation of Streetscaping on Highland Avenue from "E" Street to Waterman
Avenue per Plan No. 9845".
-(af~
Contact person: Michael Grubbs, Sr. Civil Engineer
Phone:
5179
Supporting data atlacbed: Staff Report & Project Correspondence Ward: 2 & 7
FUNDING REQUIREMENTS:
Amount: None
Source: (Acct. No.)
Acct. Description:
Fmance:
;$ounci1 Notes:
~17'I^~
J/.J..V/' 0
.
g/7/06/
/#17
~ ;).3
:II 21
d./;)./OO
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Declaration of Default by Contractor and Cancellation of Contract-Installation of Street Trees
along Highland Avenue from "E" Street to Waterman Avenue (Colarossi Construction) per
Plan No. 9845.
BackgrowxI:
On August 2, 1999, the City entered into a Contract with Colarossi Construction for
Installation of Street Trees along Highland Avenue from "E" Street to Waterman Avenue for
the contract amount of $158,433.
,-------
The "Notice to Proceed" was given on August 27, 1999. Colarossi Construction began work
at the southeast comer of "E" Street and Highland Avenue and started trenching. east as
required by Bid Item No. 8 "Trenching, Backfil1ing and Restoration of Asphalt concrete
Pavement". On 9/1/99 the contractor encountered 9" to 10" thick asphalt concrete pavement.
On 9/7/99 the contractor encountered a 6" thick layer of concrete underneath the asphalt
concrete pavement. The extra thick asphalt concrete pavement and the subsurface concrete
was not shown on the plans and appeared to affect the entire reach of the project., therefore,
Colarossi Construction immediately stopped work and verbally requested a change order to
compensate them for the extra cost incurred due to "Changed Conditions" under Section 3-4 of
the Standard Specifications.
In a meeting with the Contractor, City Staff acknowledged the "Changed Condition" and
authorized the Contractor to proceed under Section 3-4 of the Standard Specifications, which
requires the Agency to issue a change oroer to adjust the compensation for the affected work.
However, it was not possible to immediately process a change order before the City Council
because the locatioJ;l and amount of the unforeseen asphalt and concrete was highly variable
and the total cost of the change order could not be estimated. The Contractor and City Staff
agreed that Bid Item No. 8 "Trenching, Backfilling and Restoration of Asphalt Concrete
Pavement" would be deleted and the work covered would be completed on a "Time and
Materials" basis as provided by Section 3-3.2.2 "Basis for Establishing .Costs" of the Standard
Specifications. It was further agreed that Colarossi Construction would attempt to complete
300 linear feet per work day of trenching.
The Contractor resumed work on 9/8/99. An evaluation by City Staff of the progress of the
work was made on 9/22/99 and the rate of trenching was found to be only 188 linear feet per
day, substantially less than the performance goal of 300 linear feet per day. City Staff
suggested that Colarossi Construction investigate alternative methods of trenc.hing, such as a
"rock saw" trencher. Representatives of Colarossi Construction, rejected the suggestion and
insisted on conrinnil'1g the work by conventional methods. Each family member performed
various tasks, such as laborer, equipment operator, fIagger, truck driver, etc. CoIarossi
Construction refused- to bring in additional workers or hire subcontractors to speed up the
trenching operation.
On September 22, 1999, the City issued a "Stop Work Notice" to CoIarossi Construction. The
"Stop Work Notice" was to remain in effect until the Colarossi Construction: 1) Formally
requested a "Change in Condition" from the City in writing; and 2) that Colarossi
Construction submit a fair and reasonable request for additional performance time and cost
based on an economical alternative trenching methodology.
On October 19, 1999, a meeting was held with Colarossi Construction and their Attorney,
Blake A. Hudson. Henry Empeno, Deputy City Attorney, was in attendance on behalf of the
City together with Public Works Staff. It was agreed that CoIarossi Construction would
resume work on 11/1/99 with a goal of 300 linear feet per day of trenching. The Contractor
would further attempt to complete trenching in the street between "E" Street and Sierra Way
before 12/1/99 so that our Highland Avenue Pavement Rehabilitation Project, a separate
contract, could proceed. Additionally, City Staff agreed to seek approval to pay for materials
that had been delivered but not incorporated in the work. Further, City Staff agreed to
consider a claim by tIie Contractor for "lost time cost" due to the "Stop Work Notice".
,----
In the spirit of cooperation with the Contractor and to alIeviate unfair impacts to its material
supplier M & M Boys, Inc. the City processed Change Order No. 1 to delete the portion of
Section 6-1.06 PAYMENTS, which read as follows: "No partial payment will be made for
any materials which are furnished but not incorporated in the work.". The purpose of this
change order was to enable payment to the Contractor for materials delivered to the job, but
not yet incorporated into the work. This was a "no cost" change order and did not require
City Council approval.
-~-
The Contractor resumed work on 11/1/99 and worked continuously until 12/29/99, when the
Contractor without notice to the City, abandoned the Project. The Contractor failed to provide
"Time and Material" reports as required by SeCtion 3-3.3 "Daily Reports by Contractor" for
anytime during that period. Measurement by City Staff of the work completed during that time
period indicated that the Contractor averaged 67 linear feet per day of trenching, backfilling
and restoring asphalt concrete pavement. City Staff felt that the Contractor's lack of
manpower was the cause of the extremely low rate of progress.
On December 28, 1999, City Staff attempted to deliver two checks to Colarossi Construction.
One check was to CoIarossi Construction for work completed during the period 8/27/99
through 9/20/99. The other check was a joint check made payable to Colarossi Construction
and M & M Boys, Inc. and was intended to pay for grates and irrigation materials stored at M
& M Boys' yard in Corona, but not yet incorporated in the work. Larry COlarossi, Sr. refused
to accept either of the checks indicating that he felt that approximately $80,000 is owed to him
for work completed to date.
On December 29, 1999, the Contractor stopped work, without notice to the City, and moved
their equipment off the site. City Staff believed they had abandoned the project. A letter was
sent on 1/3/2000, by certified mail to Colarossi Construction, its bonding company and ~ts
Attorney, Blake A. Hudson advising them that the City considered them in default as defined
by Section 6-4 of the Standard Specifications. The Contractor was given five (5) days to
respond to the "Notice of Default" letter. The Contractor was advised that if it failed to
resume work and diligently pursue the work to completion, the City would declare the
Contractor in default, cancel the contract and exclude the Contractor from the project site
taking possession of all materials and equipment at the site.
On Wednesday, January 12, 2000, without notice to the City, the Contractor returned to the
job site and resumed work. City staff has monitored the work since the Contractor's return
and the Contractor's perforrnanre still falls far shon of the mutually agree upon goal of 300
linear feet per day. The average rate of progress since returning has been less than 100 linear
feet per day.
In addition to stopping work and moving off the site on December 29, 1999, Colarossi
Construction had reponedly directed its supplier, M & M Boys of Corona, to return to the
manufacturer approximately $44,000 worth of tree grates and irrigation material. This action
indicated to City Staff that Colarossi Construction was not acting in good faith and had no
intention of returning to complete the project.
In addition to the substandard performance indicated above, staff has been unable to obtain
from Colarossi Construction documents required by HUD for the City to obtain reimbursement
under the CDBG Grant. Except for the period 8/27/99 to 9/20/99, the Contractor has failed to
submit acceptable Certified Payroll Records for the payroll periods during which contract work
was completed. No Certified Payroll records have been submitted for work completed
between 11/1/199 and 12/29/99. Without acceptable Certified Payroll Records for all pay
periods worked after 9/20/99, Staff is unable to authorize any further payment to Colarossi
Construction.
City Staff had been in contact with Colarossi's bonding company and has attempted to have the
bonding company intervene and influence the Contractor to remedy the deficiencies in his
performance to no avail.
Consequently, on January 18, 2000, Staff mailed and delivered to C01arossi Construction a
notice to suspend work pursuant to Section 6-3 "Suspension of Work" of the Standard
Specifications pending resolution of the "Notice of Default" action before the Mayor and
Common Council on January 24, 2000. A copy of the letter and all other correspondence
between the City and Colarossi Construction or their representatives is attached.
, .
Therefore, Staff is recommending that the Mayor and Common Council declare Colarossi
Construction in default and Cancel the Contract pursuant to Section 6-4 "Default by
Contractor" of the Standard Specifications which provides that "The Contract may be canceled
by the Board without liability for damage, when in the Board's opinion the Contractor is not
complying in good faith, has become insolvent, or has assigned or subcontracted any part of
the Work without the Board's consent". Staff contends that the Contractor is not "complying
in good faith" as evidenced by the following actions and performance deficiencies: .
1. Abandoned the Work on 12/29/1999 without notice to the City and subsequently returned
to work, also without notice to City, on 1/12/2000, but only after receiving a written notice
from Staff regarding their abandonment.
2. Directed M & M Boys, Inc. to return approximately $44,000 in tree grates and irrigation
supplies which were intended to be included in the work, indicating a lack of commitment
to complete the Project even though the City attempted to deliver to them a joint check to
pay for the materials.
3. Made no effon to achieve the agreed upon perfonnance goal of 300 linear feet per day of
trenching, backfilling and restoration of pavement.
4. Have not submitted proper and complete documentation of Cenified Payroll Repons and
Time and Materials repons that are required for the City to pay Contractor and obtain
reimbursement from the Community Development Block Grant (CDBG) Fund.
Financial 'mpn:
There is no immediate financial impact due to the proposed action declaring the default and
canceling of the contract.
Recommendation:
That the Mayor and Common Council declare Colarossi Construction in default and cancel the
Contract pursuant to Section 6-4 "Default by Contractor" of the Standard Specifications for
project "Installation of Streetscaping on Highland Avenue from "E" Street to Waterman
Avenue per Plan No. 9845".