CITY OF SAN BERNA(J)INO - REQUa;~! f~.lC:!?~NCIL ACTION
:rom: ROGER G. HARDGRAVE
Authorization to Advertise for
Subject: Bids Relocation of Sewer in
"D" Street, from 7th Street to
9th Street, per Plan No. 8587
)ept: Public Works/Engineering
)ate: 10-10-91
iynopsis of Previous Council action:
June, 1991
Sewer Line Construction Fund Budget for 1991/92
Fiscal Year approved.
09-16-91
--Approval of transfer of $78,000, from Sewer Line
Construction Fund, Installation of Sewer in Cajon
to "on Street Sewer Replacement, from 7th to 9th St.
!'lecommended motion:
That the plans for replacement of sewer line in "0" Street, from
7th Street to 9th Street, in accordance with Plan No. 8587, be
approved; and the Director of Public Works/City Engineer be
authorized to advertise for bids.
cc: Shauna Clark
Andy Green
Manuel Moreno
Contact person:
Gene R. Klatt
Phone:
5125
Supporting data attached: Staff Report
Ward:
1
FUNDING REQUIREMENTS:
Amount: $78.000 (Sewer Line. Construction Fund)
Source: (Acct. No.) 245-365-57886
in "0"
St.. from 7th to 9th St.
Finance:
of Sewer Main
LL\~ D~.
(Acct. DescriPtion) Replacement
Council Notes:
75-0262
Agenda Item No
II
~"'
CITY OF SAN BERNACbINO - REQUEST FcQ COUNCIL ACTION
STAFF REPORT
Plans, specifications, and estimates have been prepared
for this project and it is now ready to bid.
The project calls for the replacement of the existing
sewer line in "0" Street, from 7th Street to 9th Street, due to
continued calls for service and the deteriorated condition of the
line.
Below is the total estimated project cost:
Construction Contract
Engineering & Inspection (W.O.
$
52,000.00
16,000.00
Sub-Total
$
$
$
10,000.00
68,000.00
Contingencies (15%)t
TOTAL ESTIMATED PROJECT COST
78,000.00
A total amount of $7~000.00 has been allocated, in
Account No. 245-365-57886, to fund this construction.
We recommend that the plans be approved and authorization
granted to advertise for bids.
10-10-91