- REQUEST FO COUNCIL ACTION
CITY OF SAN BERNIQDINO
Date:
2-27-91
Approval of Change Order No. TWO
Construction of Storm Drain
in Redlands Blvd., Hunts Lane to
Waterman Avenue, per Plan No.
3: 48 8072 --CORNISH CONSTRUCTION CO.,
INC.
Fro~ ROGER G. HARDGRAVE REC'D.-ADg!N~u3~r
De~ Public Works/Engineering
t99{ MAR - 4 ~::1
Synopsis of Previous Council action:
June, 1989 -- Allocation of $357,600 in 1989/90 Storn Drain Con-
struction Fund Budget - Acct. No. 248-368-57835.
05-07-90 Negative Declaration adopted and finding 0= Gonsis-
tency with General Plan made.
08-20-90 Authorization granted to advertise for bids - Plan
and Specification No. 8072.
08-20-90 Authorization to transfer $94,400 from Account No.
248-368-57813, "Pershing Ave - 40th to 48th" to
Acct. No. 248-36B-57835 "Redlands Blvd. - Hunts
Lane to Waterman," gr'anted.
11-05-90 Resolution No. 90--442 adopted, awarding a contract
for the lmq bid price of $330,000.
01-07-91 Change Order No. One approved, increasing the con-
tract price by $19,500.00, to $349.500.00.
Recommended motion:
That Change Order No. Two to the contract with Cornish Construc-
O tion, for the construction of a storm drain in Redlands
Boulevard, from Hunts Lane to Waterman Avenue, in accordance with
Plan No. 8072, be approved, to increase the cost authorized for
Change Order No. One, for installation of 455 feet of 8-inch
sewer main, from $19,500.00 to $23,500.00 for an increase in the
contract price of $4,000.00, from $349,500.00 to $353,500.00
cc: Shauna Edwins
Andy Green
Supporting data attached:
Ward:
5025
3
Contact person:
Roqer G. Hardqrave
Staff Report,
CCO #2
Phone:
FUNDING REQUIREMENTS:
Amount: $4,000
Source: (Acct. No.! 248-368-57835
IAcct. Descriotion)
Storm Drain, Redlands Blvd.
~ \\ .
Finance: l,'~ Y) r'
Hunts Lane to Waterman Avenue
cOl Notes:
75-0262
Agenda Item No.
q
.'-t',
+I
at
J. ~ ~
J
J.
-....
III
CIT~ OF SAN BERNQDINO - REQUEST Fg. COUNCIL ACTION
o
STAFF REPORT
Change Order No. One was approved at the Council
meeting of 1-7-91, to authorize the construction of an B" sewer
main in Redlands Boulevard, from Hunts Lane to a point about
455 feet easterly. This change order was approved with a not
to exceed amount of $19,500.00.
During construction, numerous underground utility lines
were encountered in Hunts Lane, which had not been identified
by the responsible companies. Conflicts with these utility
lines delayed the Contractor up to 5 working days, which
resulted in additional costs in the amount of $4,000.00.
We have reviewed the Contractor's request for addi-
tional compensation, and feel that it is fair and reasonable.
The total estimated project cost, based upon the actual
low bid price, included an amount of $55,000 for contingencies,
which can be used to finance the additional cost of $4,000.00
for Change Order No.1.
We recommend that Change Order No. 2 be approved.
o
o 2-27-91
"'"""
.
-
_l..a
-
l _..
..L.
pn;;;ject:
from Hunts Lane to Waterman Avenue
o
IJQIooIE;.
o File No.4. 42-14
Plan No. 8072
o
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO. CALIFORNIA
CONTRACT CHANGE ORDER NO. TWO
-
(Change necessitated because of field conditions)
Cornish Construction Co.
TO: 9435 Bellegrave
Glen Avon, CA 92509
Gentlemen:
The cost for extra work done under authority of Contract Change
Order'No. One', for installation of 455 t L.F. of 8" sewer main,
is hereby increased from $19,500.00 to $23,500.00. .
o
Total extra work cost added to contract .............................$ 4,000.00
Previous Contract Price .........................~...................$ 353,500.00
Amended Cost Price ..................................................$ 357,500.00
Five Work-
Additional time to complete contract due to change ord~r ............ ing Days
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
ROGER G. ~O~~
Director of Public Works/City Engr.
By:
c3itle:
Accepted Date:
Approved Date: