CITY OF SAN BERtORDINO - REQU~~eTN~~l~::>>UNCIL ACTION
From: ROGER G. HARDGRAVE
Approval of Plans & Authorization
Subject: to Advertise for Bids - Phase I
of Improvement of Buckboard Park,
per Plan No. 7662
Dept: Public Works
Date: 12-17-91
Synopsis of Previous Council action:
June, 1986 - Allocation of $10,000 in 1985-86 Park Construction
Fee Budget, for development of concept plan for Buckboard
Park, approved.
June, 1986 Application of Supplemental funds in the amount of
$15,000, for development of concept and design plans
for Buckboard Park, approved in 1986-87 Park Construc-
tion Fee Budget.
10-05-87 Resolution No. 87-366 adopted authorizing the execution
of an agreement with Kammeyer & Associates for professional
design.
June, 1988 Allocation of $250,000 in 1900-89 ?a~: Construction
Fee Budget, approved.
(Continued on 2nd Page)
Recommended motion:
That the plans for Phase I
accordance with Plan No.
Public Works/City Engineer
of the improvement of Buckboard Park,
7662 be approved; and the Director
be authorized to advertise for bids.
in
of
cc: Shauna Clark
Andy Green
Annie Ramos
Contact person:
Roqer G. Hardqrave
Phone:
<;O?<;
Supporting data attached: Staff Report
Ward:
<;
FUNDING REQUIREMENTS:
Amount:$699,OOO (Park Constru.ction Fee Fund)
Source: (Acct. No.) 243-363-57518
Acct. Oescri tion Phase I lm
Park
Finance:
- uckboard
Council Notes:
_ 75-0262
Agenda Item No.
~
-
-
c
o
12-17-91
File
No.
6.1468
SYNOPSIS OF PREVIOUS COUNCIL ACTION Cont:
June, 1989 Allocation of $200,000 in 1989-90 Park Construction
Fee Budget approved.
12-18-89 - Finding made that scope and concept has been changed,
and payment of an additional $1,020 to Kammeyer &
Associates approved.
June, 1990 Allocation of $110,000, in 1990-91 Park Construction
Fee Budget, approved.
June, 1991 - Allocation of $200,000 in 1991-92 Park Construction
Fee Budget approved.
CITY OF SAN BERQRDINO - REQUEST O>>R COUNCIL ACTION
STAFF REPORT
Plans for Phase I of the improvement of Buckboard Park
have been completed by the Consulting Landscape Architect and
Engineering Division, and the project is ready to be advertised
for bids. The project consists, in general, of clearing and
grubbing, perimeter fencing, irrigation system, hydro spraying
turf, security lights and street improvements along Kendall
Drive.
Below is an estimate of the total project cost:
Construction Contract --
Phase I - Park Improvements
Street Improvements
$408,786
106,715
$ 515,501
Engineering & Inspection -
Consultant Design Fees
Phase I- Park Imps (W.O.#1780)
Street Imps (W.O. #1823)
25,960
25,000
10,400
$
61,360
54,361
Water Meter Fees (1!" & 3")
Sewer Plant Capacity Fee
Electrical Service Fee
Sub-Total $
3,100
1,000
635,322
63,678
$ 699,000
Contingencies (10%)t
TOTAL ESTIMATED PROJECT COST
Park Construction Fees have been allocated, under Account
No. 243-363-5718, in the following amounts:
1985 - 86 $ 10,000
1986 - 87 15,000
1988 - 89 250,000
1989 - 90 200,000
1990 - 91 110,000
1991 - 92 200,000
Total Allocated Funds - $ 785,000
We recommend that the plans be approved and authorization
granted to advertise for bids.
12-17-91
75.0264