CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: James Funk, Director
Subject: Approval of Contract Change
Order No. One to contract with Bond
Blacktop, Inc. for slurry sealing of various
streets, phase X per plan no. 10126.
Dept: Development Services
Date: April 11, 2001
File No. 1.7191
Synopsis of Previous Council Action:
MCC DATE: 04/16/01
07/10/00 Allocated $550,000 from Y:z-Cent Sales Tax (Fund 129) and $115,600 from Gas Tax
(Fund 126) for citywide pavement rehabilitation in the FY 2000/01 Capital Improvement
Program.
12/18/00 Adopted Resolution awarding contract to Bond Blacktop, Inc for slurry sealing of
various streets, Phase X in the amount of$419,190.50.
Recommended Motion:
That the Mayor and Common Council approve Contract Change Order No. One in the amount of
$52,190.00 to contract with Bond Blacktop, Inc. for slurry sealing of various streets, Phase X per
Plan No. 10126. ~f~
-J James Funk
Contact person:
Michael W. Grubbs, Field Engineer
Phone:
5179
Supporting data attached: Staff Report, Change Order #1
Ward:
5,7
FUNDING REQUIREMENTS: Amount:
$52,190.00
Source: (Acct. No.) 129-367-5504-7191 & 126-369-5504-7187
Acct. Description: Pavement Rehab. - Various Locations
Finance:
Council Notes:
Agenda Item No.
1!~/J.
fI/!~/b/
Staff Report
, .
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
Subiect:
Approval of Contract Change Order No. One to contract with Bond Blacktop, Inc. for slurry
sealing of various streets, phase X per Plan No. 10126.
Background:
On December 18,2001, the Mayor and Common Council awarded a contract to Bond Blacktop,
Inc. in the amount to $419,190.50 for slurry sealing of various streets, Phase X per Plan No.
10126. The bids ranged from $419,190.50 to $610,370.63 with the second lowest bidder at
$465,836.83.
During construction it became apparent that certain changes should be made to the original
contract to assure an efficient and fully functional project for the cost. The proposed changes are
described in the attached change order.
Due to the deteriorated condition of a number of the streets being slurried and the effects of
heavy rain during the preparation process, over-runs have occurred on Bid Item No.4 "Repair of
Street Cut" and Bid Item No. 6 "Patch Existing Pavement" in the amount of 25% over the
quantities of the bid items indicated in the contract. The total cost of the over-runs on these two
items will be $10,320.13.
Financial Impact:
The total cost of this change order including quantity adjustments is $62,510.13, which is less
than the contingency amount of $65,800.00 allocated by the Mayor and Common Council as part
of the contract award. Sufficient funds are available in Account No. 129-367-5504-7191 and
Account No. 126-369-5504-7187 to cover the cost of this change order plus the cost of overruns.
Recommendation:
That the Mayor and Common Council approve contract change order no. one in the amount of
$52,190.00 to contract with Bond Blacktop, Inc. for slurry sealing of various streets, Phase X per
Plan No. 10126.
DEVELOPMENT SERVICES DEPARTMENT
'"
300 North "D" Street. San Bernardino. CA 92418-0001
Planning & Bnilding 909.384.5057 . Fax: 909.384.5080
Public WorkslEngineering 909.384.5111 . Fax: 909.384.5155
www.ci.san-bernardino.ca.lis
CONTRACT CHANGE ORDER NO. ONE
FILE NO. 1.7191
DATE: APRIL 11, 2001
PROJECT: Pavement Rehabilitation by Slurry Seal Method at Various
Locations per Plan No. 10126
TO: Bond Blacktop, Inc.
P.O. Box 616
Union City, CA 94587
GENTLEMEN:
You are hereby compensated for performing the additional work as follows:
Item Description of Change Increase!
No. Decrease
Profile grinding of Parkside Drive from 30'" Street to 34'" Street and
1 Broadmoor Boulevard from 30'" Street to Parkdale Drive, including Posting of $18,250.00
"No Parking" signs, notification of residents, grinding up heaved asphalt
along gutter line, hauling & disposing of grindings & sweep street clean. __~......_n_.____________
Compensation for additional skin patching in excess of 125% of the original
2 contract quantity for Bid Item No.6 to complete Area "A". Agreed Lump $7,500.00
Sum at $7,500.00.
Furnish and install Chip Seal on Parks ide Drive from 30'" Street to 34'" Street,
Broadmoor Boulevard from 30'" Street to Parkdale Drive, and Marshall
3 Boulevard from Waterman Avenue to Parkside Drive, conforming to Caltrans $48,000.00
Standard Specification, Emulsion shall be PMCRS-2h, including posting of
"No Parking" signs, notification of residents & sweep street clean during the
process. Approx. 320,000 SF at $0.15 per SF 1
ADDITIONAL PAYMENT TO CONTRACTOR FOR CCO #1 $73,750.00
QUANTITY ADJUSTMENTS TO CONTRACT
Apply coat of slurry seal over Chip Seal (Cape Seal) for Parkside Drive from
30'" Street to 34'" Street, Broadmoor Boulevard from 30'" Street to Parkdale Included in
4 Drive, and Marshall Boulevard from Waterman Avenue to Parkside Drive, Quantity of
including Posting of "No Parking" signs, notification of residents & sweep Bid Item No.
street clean after application. Approx. 231 tons of Slurry per Bid Item No.2 2
at $70.00 per ton. 1
5 Delete Harrison Street from Lynwood Drive to 40'" Street. Deleted 143 tons ($10,010.00)
of Slurry per Bid Item No.2 at $70.00 per ton. 1
r
Contract Change Order No. One
Pavement Rehabilitation by Slurry Seal Method at Various Locations per Plan No. 10126
Page 2 of 4
6 Delete Parkdale Drive from Valencia Avenue to Waterman Avenue. Deleted ($5,040.00)
72 tons of Slurry per Bid Item No.2 at $70.00 per ton. '
7 Bid Item No.2: Estimated underrun for entire project. Estimated ($6,510.00)
Minus approx. 93 tons at $70.00 per ton.'
NET CHANGE ORDER COST $52,190.00
I Quantities are estimated. Actual tonnage of Slurry Seal for payment purposes will be determined by field
measurement.
JUSTIFICATION:
Item No.1: Based on complaints by residents Staff closely examined Parkside Drive and Broadmoor
Boulevard and found the pavement adjacent to the gutter and median curb to be excessively heaved.
The heaving has caused ponding problems which have caused accelerated deterioration of the
pavement. Staff determined that removal and replacement of the heaved pavements areas would be
costly and, instead, requested that the Contractor provide a proposal to "profile grind" the streets along
the edges of the gutters. The contractor submitted a proposal to profile grind Parkside Drive form 30th
Street to 34th Street and Broadmoor Boulevard from 30th Street to Parkdale Avenue for a distance of
approximately 4 feet from each gutter. The total amount of grinding will be approximately 9,000
square yards. The price proposed for this work of $9,250.00 ($1.03 per square yard) for Broadmoor
Boulevard and $9,000.00 for Parkside, which is consistent with the average unit price of $1.00 per
square yard received from bids for similar projects. See attached proposals from contractor.
Item No 2: During construction it became apparent in area" A" that significant additional skin patching
over the original bid quantity and greater than the 25 % overrun limit established by Section 3-2.2.1
"Contract Unit Prices" of the Standard Specifications would be required to properly prepare the streets
for placement of slurry sealing. The contractor proposed to perform the additional skin patching above
the 25% overrun limit for a lump sum price of $7,500.00. City staff reviewed the proposal based on
the estimated area of additional skin patching and concluded that the price of $7,500.00 represents a
unit price of approximately $0.75 per square foot which is less than the bid item price for skin patching
of $2.05 per square foot. Therefore, staff feels the price proposed by the Contractor is fair and
reasonable for this extra work.
Item No.3: After grinding it became apparent that the reach of Broadmoor Boulevard between 30th
Street and Parkdale Drive was not in satisfactory condition for slurry sealing. Many large cracks larger
than I" were noted and unraveling had occurred due to the grinding. The same problem was observed
on Marshall Boulevard between Waterman Avenue and Parkside Drive. The Contractor recommended
that these streets receive a "Cape" seal due to its deteriorated condition. A cape seal consists of
placement of a chip seal of 3/8" rock followed by a coating of slurry seal material to seal the rocks in
place. This rehabilitation method has been proven to fill the large cracks, restore the wearing surface
and provide 5 to 10 years of additional life of pavement. The Contractor proposed to furnish and install
the Chip seal for $0.15 per square foot and the slurry seal over the chip seal at the $70.00 per ton bid
price. See attached proposals from contractor.
Item No.4: This item is to provide for the slurry coat 'over the chip seal. Approximately 172 tons of
slurry seal material will be required to cover the chip seal. The application of the slurry coat is
necessary to hold the chips in place and to provide a smooth riding surface.
I n_______
Contract Change Order No. One
Pavement Rehabilitation by Slurry Seal Method at Various Locations per Plan No. 10126
Page 3 of 4
Item No 5: Staff reviewed Harrison Street from Lynwood to 40th Street and determined that the
character of the street, traffic speed and traffic volume did not make it a good candidate for slurry
sealing. Therefore it was deleted from the contract.
Item No 6: After start of construction the San Bernardino Municipal Water Department (SBMWD)
advised us that they would be trenching in Parkdale Drive between Waterman Avenue and Valencia
Avenue to install a new water line. The time frame of their proposed work was such that they would
have to excavate through the recently placed slurry. Therefore, staff deleted this reach of Parkdale
Drive from the current slurry seal project. It is proposed to include the street in a future pavement
rehabilitation project.
Item No.7: Based on measured quantities of Slurry Seal used to date, staff is estimating total quantity
placed of 3,220 tons which is approximately 93 tons below the contract quantity of 3,313 tons. This
underrun will result in a reduction in contract amount of 93 tons x $70.00 per ton = $6,500.00
(approx.). This underrun combined with the other adjustment in Slurry Seal quantity does not exceed
25 % of the contract amount, therefore, no adjustment in unit price is required.
SUMMARY OF CONTRACT COSTS
The estimated revised contract cost is as follows:
Original Bid Amount ....................................................................... $419,190.50
Increase due to CCO#I - See Description of changes above........................ $ 52 190.00
Revised Contract Amount* .............................................................. $471,380.50
Percent change to total contract amount....................... .................... ............+ 12.5%
.Overruns/underruns on other bid items that are based on measured quantities are not reflected in this
amount.
Additional time to complete Contract due to Change Order ....... ...... .10 Workinl: Days
Contract Change Order No. One
Pavement Rehabilitation by Slurry Seal Method at Various Locations per Plan No. 10126
Page 4 of 4
BOND BLACKTOP, INC.
Accepted
By:
Title:
Date:
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES
Approval Recommended:
By:
James Funk
Dir. of Development Svcs.
Date:
Approved By City Council
MCC Agenda Item No.
Date Approved
. .
j, 7/f /
\-D'~~[gD\YJ~rw
to) MAR n ,i 2001
BLACKTOP, Inc.
COMPLETE ASPHALT MAINTENANCE
:.:il Y Of SAN BERNARDINO
OEVELOPMENT SERVICES
DEPARTMENT
March 6, 2001
City of San Bernardino
Development Services Department
300 North D St.
San Bernardino, CA. 92418-0001
Attn: Andy NavarTo
Re: Proposal for Cape Seal on Broadmoor
Dear Mr. NavarTo,
Per our conversations, please except the following proposal to construct a Cape Seal on
Broadmoor. The limits will remain as outlined in the specifications.
Post "No Parking" signs, NotifY residents, Grind up heaved asphalt along gutter line, haul
& dispose of grin dings & Sweep....................9,250.00
Furnish and install a 3/8 inch chip seal conforming to the State of Calif., Dept. of Trans.,
Standard Specification. Emulsion shall be PMCRS-2h........ ..0.J..91ler square foot (s;€G t-e'7 i e',t:.
d~ OF 4-/11101)
Furnish and install a Type II Slurry seal per existing contract..... ...70.00 per Ton
These prices are based on the City's estimate of258,980 sq. ft. Actual Quantities
m"'asur~d in th" field wi!! be bil!ed for the chip ::c2ol ',,;:n':,.
Thank you for the opportunity to quote this work. Should you need any further
information, please feel free to contact me.
Respectfully,
Ed &"'-
Ed Dillon
Bond Blacktop, Inc.
P.O. Box 616, Union City, CA 94587
Phone (510) 441-9981 Fax (510) 441-9982
Controct Lie. #746432
04/11/2001 14:49 FAX 510 441 9982
BOND BLACKTOP. Inc.
Ij!J 002/002
BOND
BLACKTOP, Inc.
co.......,. ASPHALT MAINTlNANCE
--- -~ ~ ------ - ------ --
April 11, 2001
City of San Bernardino
Development Services Department
300 North D SL
San Beinardino, CA. 92418-0001
Attn: Andy Navarro
Re: Proposal for Cape Seal on Vacious Streets
Dear Mr. Navarro,
Per our conversations, please except the following proposal to construct a Cape Seal on
various streets. The limits will be defined by the City prior to construction.
Post "No Parking" signs, Notify residents. Grind up heaved asphalt along gutter line, haul
& dispose of grin dings & Sweep....................9.oo0.00 .
Furnish and install a 3/8 inch chip seal conforming to the State of Calif., Dept. of Trans.,
Standard Specification. Emulsion shall be PMCRS-2h..........0.15 per square foot
Furnish and install a Type II Slurry seal per existing contract........70.00 per Ton
These prices are based on the City's estimate of320,000 sq. ft. Actual Quantities
measured in the field will be billed for the chip seal work.
Thank you for the opportunity to quote this work. Should you need any further
information, please feel free to contact me.
Respectfully,
&~
Ed Dillon
Bond Blacktop, Inc.
P.O. Box 616, Union City, CA 94587
Phone (510) 441-9981 Fax (510) 441-9982
Conlnlcl Lie. 11746432