CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: Michael E. Hays, Acting
Director
Subject:
Approval of Plans and authorization to advertise for
bids - Installation of handicapped ramps in various
locations per Plan No. 9793.
Dept: Public Works/Engineering
File No. 7.37-107
a"~'G' ".~ '1
"1"'/ 'I. "i .
i I, ~n.::.
Date: April 6, 1998
MCC Date: April 20, 1998
Synopsis of Previous Council Action:
July 1997
Project accepted by Mayor and Common Council for Community Development Block Grant
Funding.
Recommended Motion:
That the Mayor and Common Council approve the plans for construction of handicapped ramps at various
locations in accordance with Plan No. 9793 and the Acting Director of Public Works be authorized to advertise
for bids.
~!..~,
Contact person: Gene R. Klatt
Phone: 384-5125
Supporting data attached: Staff Rt<port
Ward(s): All
FUNDING REQUIREMENTS: Amount: $25.000
Source: 97-233 (Acct# 001-301-5952-5037)
(Acct. Description) CDBG Handicapped Access/Curb Cuts various locations
F;~~
Council Notes:
1/:J..oj9f!
Agenda Item No. a
..
.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
SUBJECT:
Approval of Plans and authorization to advertise for bids - Installation of handicapped ramps in
various locations per Plan No. 9793.
BACKGROUND:
Installation of handicapped ramps along various streets has been programmed for the last several
years. The proposed ramps follow the adopted policy for installation in that they cover public
facilities, schools, retail areas, and places of public accommodation in a set order. The CDBG
application provided for $50,000 for construction. This is the first set of ramps and reflects
those that do not require additional right-of-way and/or relocation of major facilities. The
remaining locations for the priority list are being designed and will be ready in the near future.
However, they do require additional work for right-of-way and/or relocation of existing
improvements.
The Memorandum of Understanding was completed and approval given to begin design March
17, 1998. This portion of the project represents construction of approximately 40 ramps; plans
are now complete and we are ready to advertise for bids.
Listed below are the estimated construction costs based on the Engineer's Estimate of
construction:
Subtotal
$20,000
3.000
$23,000
Construction Contract
Engineering and Inspection
Contingencies (3.6 %)
$ 2.000
Total Fmimated Cost
$25,000
FINANCIAL IMPACT:
Funding for the installation of handicapped ramps at various locations is found in the Community
Development Block Grant Projects Fund under Account No. 97-233 in the amount of $50,000.
RECOMMENDATION:
Staff recommends approval of the plan and that the Acting Director of Public Works be
authorized to begin advertising for bids on the installation of handicapped ramps in various
locations.