CITY OF SAN BERNARDINO REOUEST FOR COUNCIL ACTION
e From: Valerie C. Ross, Director Subject:
Dept: Development Services
Date: March 26, 2007
File Nos. 4.7462
MCC Date:
Authorization for the Director of Development
Services to execute Contract Change Order
No. One to the contract with Powell
Engineering Construction for Drainage
Improvements and Pavement Rehabilitation
on Bailey Court (SD04-14), per Project Plan
No. 11248.
Synopsis of Previous Council Action:
April 16, 2007
Council approved FY 2004-05 CIP Budget - Storm Drain.
Adopted Resolution awarding contract in the amount of $91,000 to Powell Engineering
Construction for Drainage Improvements and Pavement Rehabilitation on Bailey Court
(SD04-14), per Project Plan No. 11248.
09-07-2004
06-06-2005
Recommended Motion:
Authorize the Director of Development Services to execute Change Order No. One in the amount of
$22,840.32 to a contract with Powell Engineering Construction for Drainage Improvement and
Pavement Rehabilitation on Bailey Court (SD04-14), per Project Plan No. 11248.
Ydtt~ {/, frHv
Valerie C. Ross
e
Contact Person:
Mark Lancaster,
Deputy Director/City Engineer
Phone:
3305
Supporting data attached:
Staff Report & CCO No. I
Ward:
5
FUNDING REQUIREMENTS:
Amount: $23.000
Source: (Acct. No.) 248-368-5504-7462
Acct.
Description: Storm Drain Improvement Projects
Finance:
COUNCIL NOTES
e
Agenda Item NO.~
lfJ /lI/07
e
e
e
CITY OF SAN BERNARDINO REOUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Authorization for the Director of Development Services to execute Contract Change Order No. One 10
the contract with Powell Engineering Construction for Drainage Improvements and Pavement
Rehabilitation on Bailey Court (SD04-14), per Project Plan No. 11248.
Background:
On September 7, 2005, the Mayor and Common Council allocated $150,000 in the Storm Drain
Construction Fund for Drainage Improvements and Pavement Rehabilitation on Bailey Court (SD04-
14), as part of the FY 2004/05 Capital Improvement Program (CIP). On June 6, 2005, the Mayor and
Common Council awarded a contract to Powell Engineering Construction for this project.
During construction, the contractor encountered water and sewer lines that were not shown on the
plans. The contractor was directed to pothole the water and sewer lines and verify elevation of said
utilities. It was determined that these utilities were in conflict with the proposed storm drain facility.
Therefore, the contractor was required to stand by until a revised design of the storm drain was
completed.
Change Order No. One, in the amount of $22,840.32, consists of the following changes:
Item No. I-I Compensation for placing additional 160.14 tons of asphalt concrete pavement at bid
price of $87 .40/per ton.
Item No. 1-2 Compensation for contractor's cost standing by while awaiting relocation of
unrecorded utilities.
The contractor just recently provided the documentation to support the change order. This action will
complete the project.
Financial Impact:
Adequate funding is available in Acct. No. 248-368-5504-7462 for this change order.
The estimated project costs are as follows:
.
TOTAL
$ 70,174.78
$ 22,840.32
$ 93015.10
Orillinal Contract Amount
Contract Chanlle Order No. One
Revised Construction Cost
This change order represents an increase of32.5% in the contract amount.
Recommendation:
Authorize the Director of Development Services to execute Change Order No. One in the amount of
$22,840.32 to a contract with Powell Engineering Construction for Drainage Improvements and
Pavement Rehabilitation on Bailey Court (SD04-14), per Project Plan No. 11248.
2
03127120073:03 PM
e
e
e
DEVELOPMENT SERVICES DEPARTMENT
300 North ''0'' Street. San Bernardino' CA 92418-0001
Planning & Building 909.384.5057 . Fax: 909.384.5080
Public WorkslEngineering 909.384.5111 . Fax: 909.384.5155
www.sbcity.org
w
CONTRACT CHANGE ORDER NO. ONE
FILE NOS. 4.7462
W.O. NOS. 7462
DATE: APRIL 16,2007
PROJECT: BAILEY COURT DRAINAGE IMPROVEMENTS (SD04-14), PER PLAN
NO. 11248.
TO: POWELL ENGINEERING CONSTRUCTION
974 N. MORGAN STREET
ORANGE, CA 92867-7554
GENTLEMEN:
You are hereby compensated for performing the additional work as follows:
ITEM NO:
DESCRIPTION OF CHANGE
Compensation for placing additional 160.14 tons of asphalt concrete
avement at Bid Price 0[$87.40/ er ton
Compensation for contractor's cost standing by while awaiting
relocation of unrecorded utilities.
COST
$ 13,996.31
I-I
1-2
$ 8,844.00
TOTAL COST CCO #1 $ 22,840.32
JUSTIFICATION:
Item
No.
Comnensation for olacin!! additional 160.14 tons of asohalt concrete oavement at
Bid Price of 587.40/oer ton
I-I It was necessary to pave an additional 160.14 tons of asphalt concrete, as the area
shown on the plans to be paved require more A.C. tonnage than was provided for in the
ro' ect bid.
ComDensation for contrador's cost standinl! bv while awaitinl! relocation of
unrecorded utilities .
During construction, the contractor encountered water and sewer lines that were not
shown on the plans. The contractor was directed to pothole the water and sewer lines
1-2 and verify elevation of said utilities. It was determined that these utilities were in
conflict with the proposed storm drain facility. Therefore, the contractor was required
to stand by until a revised design of the storm drain was completed. The contractor was
required to pothole and standby awaiting a revised storm drain design to downsize the
storm drain i e from 18 inches to 12 inches to clear the unrecorded utilities.
Item
No.
e
e
e
CHANGE ORDER NO. ONE ~ POWELL ENGINEERING CONSTRUCTION.
BAILEY COURT DRAINAGE IMPROVEMENTS (SOO4-14), PER PLAN NO. 11248.
SUMMARY OF CONTRACT COSTS
The estimated revised contract cost is as follows:
Original Bid Amount................................... ........................$ 70,174.78
Contract Change Order No. One. . . . . . . . . . . . . . . . . . . . . . . . . . . . . ....................$ 22.840.32
Revised Construction Contract cost. . . . . . . . . . . . . . . . . . . . . . . . .. ....................$ 93,015.10
Additional time to complete Contract due to this Change Order ................................. 10 Working Days
This change order represents 32% of the original contract amount.
POWELL ENGINEERING CONSTRUCTION
CONTRACTOR
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES
Accepted
Approved
By:
By:
Title:
VALERIE C. ROSS
Director of Development Services
Date:
Date:
Approved by Mayor and Common Council
Date:
April 16, 2007
Item No.
2