I CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
File No. 1. 7077
\
From:
ROGER G. HARDGRAVE
Subject:
Approval of Plans & Authorization
to Advertise for Bids - Modifi-
cation of Traffic Signals at DED
Street and Marshall Boulevard,
per Plan No. 9630
Dept:
Public Works
Date:
3-24-97
0,;1-
Synopsis of Previous Council action:
~DM,l.N., OF.lflC~:!
June, 1996 - Allocation of $60,000, in the Traffic Systems Fee Con-
struction 1996/97 Budget, approved.
,~[. Mt,,, 97 9: ,U
Recommended motion:
That the plans for nodification of the traffic signals at "E"
Street and Marshall Boulevard, in accordance with Plan No. 9630,
be approved; and the Director of Public Works/City Engineer be
authorized to advertise for bids.
cc: F. Wilson
a~~
Contact person: Roqer G. Hardqrave
Phone:
5025
Supporting data attached: Staff Report
Ward:
5 & 7
FUNDING REQUIREMENTS:
Amou~: $59,500 (Traffic Systens Fee Fund)
Source: (Acct. No.)
250-370-5504-7077
Acct, Descri tion
Upqrade Traffic Siqnals
Finance'
Council Notes:
75-0262
lJ!7)q7
Agenda Item No.-1D
.. ., ...
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Plans for the modification of traffic signals at "E"
Street and Marshall Boulevard have been completed, and the
project is ready to be advertised for bids. The project
consists, in general, of installing new signal poles with mast.
arms, street lighting, detection loops, audible pedestrian
signals (for the visually impaired), 2" ADA push buttons, and a
new electrical service.
Below is an estimate of the total project cost:
Construction Contract
Engineering & Inspection (W.O. #7077)
Edison Meter Fee
Sub-Total
Contingencies (15%)t
TOTAL ESTIMATED PROJECT COST
$ 47,000
4,500
500
$ 52,000
7,500
$ 59,500
All costs incurred for this project will be charged to
the $60,000 allocated under Account No. 250-370-5504-7077.
We recommend that the plans be approved and authorization
granted to advertise for bids.
3-24-97
75-0264