DEVELOPMENT DEPARTMENT OF THE
CITY OF SAN BERNARDINO
REQUEST FOR COMMISSION/COUNCIL ACTION
From:
Roger G. Hardgrave, Dir.
of Public Works/City Engr.
Subject: Report of Bids and
Approval of Proposal
by Empire & Associ-
ates -San Bernardino
City, C.Y.S.A. Soccer
Complex
Date:
1-30-97
----------------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
07-22-96 Project approved in concept and staff directed to bring
project back on 8-5-96.
08-05-96 - Determination made that proposed financing plan was
acceptable, staff directed to contact prospective lenders,
and that a competitive bidding process, supervised by
Director of Public Works, be used.
08-19-96 - Joint Development Agreement approved, as amended; and staff
directed to proceed with financing, as proposed.
---------------------------------------------------------------------
Recommended Motion:
1.
That the report of bids, for construction of the San Bernardino City -
C.Y.S.A. Soccer COIJplex, be accepted and filed; that the bidding
process under the oversight of the City Engin~er be ratified as con-
- forming to City policies; and that the proposal by Enpire & Associates,
dated 1-21-97, to aSSUMe the contract, at the price of $2,787,950.00
for the Basic Bid and $85,650.00 for thn Additive Alternates, be
approved.
and
2. ~hat the City Engineer be authorized to enter into such additional
imp1enentation agreement with EMpire & Associates as deemed necessa.ry
by the City Engineer. a
Roger G. ~.W./C.E.
-----------------------------------------------------------------------
Contact Person: Roger G. Hardgrave
Phone:
5025
Project Area: N/A
Ward(s) :
7
Supporting Data Attached:
Staff Report
Funds/Bond Proceeds
Source: Line of
Credit
be determined
Park
Amount: $ 2,873,600
FOlIDING REQUIREMENTS:
Budget Authority: To
------------------------------------------------------------------------
Commission/Council Notes:
Agenda Item tlo. :gS:J..
0<#)7
I
.e.
.
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Page 1 of 2
Report of Bids and
Approval of Proposal
C.Y.S.A. Soccer Complex
Bids for construction of the San Bernardino City C. Y . S. A.
Soccer Complex were opened by Empire A/G Recreation, LLC on
Friday, 1--03-97, in the office of HAPCO, at 680 South vlaterman
Avenue. A representative of the City's Departr.lent of Public
Works was present. It should be noted that although the .Toint
Development Agreement provided for a Public \vorks bid, a process
similar to that used for bidding construction of New pine Avenue
was deemed more ~ppropriate. Also, relocation of the Community
Gardens was performed under separate contract aVlarded by the
City.
A total of two bids were
$2,703,454.65 and $2,862,782.00.
widening of Arden Avenue. Below is
received, in the amounts of
These amounts include the
a tabulation of those bids:
L.D. Anderson, Terra-Cal
Inc. Construction, Inc.
. Total Basic Bid - $ 2,703,454 $ 2,862,782
Additive Alternates -
1. PCC Parking lot 185,335 210,608
2. Fertilizer Injector 43,500 10,000
3. Turf grids 219,552 240,135
4. Soccer Goals 22,500 25,500
Section 2 (G) of the Joint Development Agreement states that
Empire shall have the right to match the lowest responsible bid.
Empire has advised us, by proposal dated 1-21-97, that they will
exercise their right to match the lowest responsible bid. Below
is a breakdown of the proposal by Empire of the contract price.
Total Basic Bid -
Soccer Complex
Wideni.ng Arden Avenue
$ 2,440,450
172,500
$ 2,612,950
.
The price by Empire for the Basic Bid of $2,612,950 is 3.3% under
the lowest responsible bid of $2,703,454.
1-30-97
tS-(
.. '. ..:
.
.
.
Page 2 of 2
Staff Report
C.Y.S.A. Soccer Complex
The Construction Cost Budget, attached as Exhibit "G" to the
Joint Development Agreement, lists an ap.!ount of $2,796,339 for
the contract cost, including the $88,000 for the relocation of
the gardens. It also included an amount of $176,039 for
contingencies. At the Council meeting of 10-21-96, action was
taken to allocate $172,500 for the wideninq of Arden Avenue.
Available funds for this project are: -
Soccer Complex - (JDA Agreement)
Contingencies (6.5%)
$ 2,620,300*
176,039
$ 2,796,339
Sub-Total
Widen Arden Avenue
(Account No. 129-367-5504-7064)
TOTAL FUNDS AVAILABLE
172,500
$ 2,968,839
*Does not include the $88,000 for relocation of the
COmP.Iunty Gardens.
The proposal from Empire
Alternates will be included
the desired facility -
states that the following Additive
in the contract, in order to achieve
Additive Alternates -
2. Fertilizer Injector
3. Turf Grids
4. Soccer Goals
Plan Check Correction
Total Additve Alternates
$
10,000
225,000
22,500
3,150
260,650
$
Inclusion of these Additive Alternates will increase Empire' s
total contract price fron $2,612,950 to $2,873,600. The ap.!ount
for contingencies will be reduced frop.! $176,039 to $90,390, in
order to provide sufficient funds to finance the total contract
price. Thus a contingency of $90,390 remains for developmnt of
the Soccer Complex.
We recoP.lrnend that the report of bids be accepted and filed, and
that the proposal by Empire & Associates be approved.
1-30-97
f7- }
I
~
SUBSTITUTE MOTIONS
RS-l. APPROVAL OF PROPOSAL BY EMPIRE & ASSOCIATES - SAN
BERNARDINO CITY, C.Y.S.A. SOCCER COMPLEX
(Mayor and Common Council)
(Community Dvelopment Commission)
OTION A: hat the report of bids, for construction of the San Bernadino City-
C.Y.SA Soccer Complex, be accepted and filed; that the bidding process
under the ovesight of the City Engineer be ratified as conforming to City
policies; and that the proposal by Empire & Associates, dated 1-21-97, to
assume the contract, at the price of $2,873,600 for the Base Bid and
Additives and Arden Avenue improvements be approved.
OTION B. That the City Engineer be authorized to enter into such additional
implementation agreement with Empire & Associates as deemed necessary
by the City Engineer, providing for a contingency amount not to exceed
$95,239 for any Soccer Complex change orders.
substitute.eda
edc 2/3/97
.....
,
...
Soccer Fields
wi Arden
Additives
Total
IDA Dollar Amounts
$2,884,339.50
(88.000.00)
$2,796,339.50
176.039.50
$2,620,320.00
ptnpk.,da
cdc 2/3/97
Bid Comoarisons
L.D. Anderson
$2,703,454
Terr-Cal
$2,862,782
285.552
$2,989,006
275.635
$3,138,417
Bid Reauired Under JDA
Bid Required
Community Gardens
Adjusted Bid Required
6.5% Contingency
Additives
Base Bid
Base & Additives
ITEM RS-l & 2
Empire
$2,612,950
260.650
$2,873,600
Actual Bid Dollar Amounts
$2.796.339.50
95,239.00
260,650.00
2.440.450.00
$2,796,339.00