HomeMy WebLinkAbout15-Public Works
..
. ,.... '
- CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
File TIo. 1.7069 & 4.42-701R
1
From:
ROGER G. IlARDGRA VE Subject:
Approval of Plans & Authorization
to Advertise for Bids -- Improve-
ment of Coulston St., (North Side)
from Richardson St. to Curtis
St., per Plan No. 9576
Dept:
Public Works ORIGINAL
12--18-96
Date:
Synopsis of Previous Council action:
09--03-96
Allocation of $200,000, in 1996/97 1/2-Cent Sales Tax
Fund, approved.
- Transfer of $75,000, to finance the cost of installing
a storm drain in Richardson Street, frOM Davidson
Street to Coulston Street, approved.
Continued to 12-16-96.
Tabled
June, 1996
12=02-96
12-16-96
"l\D~1.N. OFit..i.Cr.;
19 D:::C 96 2.J 4"
Recommended motion:
That the plans for iMproving Coulston Street, (North Side) fron
Richardson Street to Curtis Street, in accordance with Plan tlo.
9576, be approved; and the Director of Public Works/City Engineer
be authorized to advertise for bids.
cc: F. Hilson
J. PenMan
{Az~
. Signature
Contact person:
Roqer G. lIardqrave
Phone:
'i07'i
Supporting data attached:
Staff Report
Ward:
1
FUNDING REOUIREMENTS:
Amount: $223,000 (1/2<:: Sales Tax & StorM Drain Funds)
Source: (Acct. No.) 129-367-5504--7069 &
($200,000)
Acct. Descri tion 1m rovement 0
Side) --Richardson St. to Curtis St. Finance'
Council Notes:
Ilmi1
75-0262
Agenda Item No.J5
- ---,
.
... ~. ..
, ..
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORl'
Plans for the improvement of Coulston Street (North
Side), from Richardson Street to Curtis Street, and installation
of a storm drain system in Richardson Street, from Davidson
Street to Coulston Street, have been prepared, and the project is
ready to be advertised for bids. The project consists, in
general, of installing curbs and gutters, widening the pavement
to provide 2 west-bound traffic lanes and sidewalk, driveway
approaches, street lights and a storm drain system.
Below is an estimate of the total project cost:
Construction Contract
Engineering & Inspection (W.O. #7038)
Sub-Total
Contingencies (15%)!
TOTAL ESTIMATED PROJECT COST
$ 176,700
17,700
$ 194,400
29,600
$ 223,000
Funds have been allocated in the 1/2<: Sales Tax 1996/97
Budget to finance the costs incurred for this project as set
forth below:
Account tTo.
129-367-5504-7069
AMount
$ -200,000
248-368-5504-7083
75,000
TOTAL AVAILABLE FUNDS
$ 275,000
We recomMend that the plans be approved and authorization
granted to advertise for bids.
12-18-96
75.0264