CITY OF SAN BERNARDINO REOUEST FOR COUNCIL ACTION
From: Valerie C. Ross, Director
Authorization for the Director of
Development Services to Execute
Contract Change Order No. One to the
contract with Grand Pacific Contractors,
Inc. for Installation of Reinforced
Concrete Box Culvert at 2128 Orange
Street (SD04-16), per Plan No. 11568.
Subject:
Dept: Development Services
Date: November 14,2006
File No. 4.7573
MCC Date: December 18, 2006
Synopsis of Previous Council Action:
08/07/2005 The Mayor and Common Council approved FY 2005-06 CIP Budget.
06/05/2006 Adopted Resolution awarding contract in the amount of $45,300.00 to Grand Pacific
Contractors, Inc., for Installation of Reinforced Concrete Box Culvert at 2128
Orange Street (SD04-16), per Plan No. 11568.
Recommended Motion:
Authorize the Director of Development Services to execute Change Order No. One in the amount
of $33,424 to contract with Grand Pacific Contractors, Inc. for Installation of Reinforced Concrete
Box Culvert at 2128 Orange Street (SD04-16), per Plan No. 11568.
~ (), fJfY
Valerie C. Ross
Contact Person:
Mike Grubbs, Engineering Mgr/Field Engineer
5179
Phone:
Supporting data attached:
StaffReoort & CCO No. One
4
Ward:
FUNDING REQUIREMENTS:
$33.424.00
Amount:
Source: (Acct. Nos) 248-368-5504-7573
Acct.
Description: Storm Drain Construction Fund
Finance:
Council Notes:
I/J.) IS/DID
Agenda Item No. J I
_,~_..,..",","'_,,~", "~'i'!fI'~,,~;s,
P-l
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
STAFF REPORT
e Subject:
Authorization for the Director of Development Services to Execute Contract Change Order No.
One to the contract with Grand Pacific Contractors, Inc. for Installation of Reinforced Concrete
Box Culvert at 2128 Orange Street (SD04-l6), per Plan No. 11568
Background:
On August 7, 2005, the Mayor and Common Council allocated funds, as part of the FY 2005/06
Capital Improvement Program (CIP), for Orange Street failed rock-lined channel reconstruction
(SD04-l6).
On June 5, 2006, the Mayor and Common Council adopted resolution awarding contract in the
amount of $45,300 to Grand Pacific Contractors, Inc. for Installation of Reinforced Concrete
Box Culvert at 2128 Orange Street (SD04-l6), per Plan No. 11568.
This project replaced a portion of a rock-lined ditch with a reinforced concrete box culvert with
new side walls to transition back to the existing channel walls. The rock-lined channel was
designed to be repaired at one location due to damage from tree roots.
e
During construction, it was necessary for the contractor to remove an additional tree and three
stumps in order to continue work. A wrought iron fence had to be added along each side ofthe
channel crossing for safety reasons.
The existing rock-lined channel was found by the contractor to be filled with mud and silt, which
made assessment of the damage to the channel impossible. After removal of the mud and silt, the
contractor found additional channel damage that needed to be repaired. As a result, 45 linear feet
of the drainage holes were added to facilitate drainage of the adjacent properties. A credit for bid
Item No.5 "Replace Channel Wall" was taken because the item was made unnecessary by the
decision to reconstruct the entire channel along the property frontage.
Because of the mud and silt buildup in the channel it was impossible to accurately assess damage
to the channel during the design phase of the project. After removal of the mud and silt by the
construction contractor, it became apparent that extensive additional work was necessary in order
to have a safe, functional channel.
Change Order No. One, in the amount of $33,424.00, consists of the following changes:
e
Item No.1-I: Increased clearing and grubbing.
Item No. 1-2: Installation of 106 linear feet of wrought iron fence, which was not in the
original contract.
Item No. 1-3: Removal and replacement of 45 linear feet of channel; which was too badly
deteriorated to join to the new channel.
Item No. 1-4: Core-drill drain holes for improved drainage from adjacent property.
Item No. 1-5: Credit for Bid Item No.5 the need for which was negated by Change Order
Item No. 1-3.
2
1210712006 10:45 AM
".~--~.,._~,~.".""''''','''
e
e
e
--._},:O"'''~
CITY OF SAN BERNARDINO REOUEST FOR COUNCIL ACTION
STAFF REPORT - Continued
Financial Impact:
The FY 2006-07 CIP budget included $89,000 in Acct. No. 248-368-5504-7573 for this project,
which will be adequate funds to cover the cost of this change order and all other costs for this
project. At this time, it is anticipated that all $89,000 of budgeted funds will be used for this
project.
The estimated project costs are as follows:
Ori inal Contract Amount
Contract Change Order No. One
Revised Construction Cost
TOTAL
$ 45,300.00
$ 33,424.00
$ 78,724.00
Recommendation:
Authorize the Director of Development Services to execute Change Order No. One in the
amount of$33,424 to contract with Grand Pacific Contractors, Inc. for Installation of Reinforced
Concrete Box Culvert at 2128 Orange Street (SD04-I6), per Plan No. 11568.
3
12/07/2006 U4 AM
__,,___,,',,.'<If'''.'.' l'"
e
e
e
~l
DEVELOPMENT SERVICES DEPARTMENT
300 North "0" Street. San Bernardino. CA 92418-0001
Planning & Building 909.384.5057 . Fax: 909.384.5080
Public WorkslEngineering 909.384.5111 . Fax: 909.384.5155
www.sbcity.org
..
CONTRACT CHANGE ORDER NO. ONE
FILE NO.
W.O. NO. 7573
DATE: DECEMBER 18, 2006
4.7573
PROJECT: INSTALLATION OF REINFORCED CONCRETE BOX CULVERT
AT 2128 ORANGE STREET (SD04-16).
TO: GRAND PACIFIC CONTRACTORS, INC.
11405 GEYSER DRIVE
MIRA LOMA, CA 91752
GENTLEMEN:
You are hereby compensated for performing the additional work as follows:
ITEM NO: DESCRIPTION OF CHANGE COST
1-1 Additional Clearing and Grubbing $ 1.000.00
1-2 Install 106 linear feet of Wrought Iron Fence @ $85/pe,r linear feet $ 9,010.00
1-3 Remove & Replace 45 linear feet of Channel $ 28,000.00
1-4 Core Drill Drain Holes $ 414.00
1-5 Credit for Bid Item NO.5 $ (5,000.00)
,
! TOTAL COST CCO #1 $ 33,424.00
JUSTIFICATION:
Additional Clearin!! and Grubbin!!
Item No. 1-1 During construction, removal of an additional tree and 3 stumps' was necessary to
allow for construction of the channel.
In5talll06 L.F. of Wrou!!ht Iron Fence tal $85/per L.F.
I Item No. 1-2 After the new channel as constructed, a wrought iron railing was installed along each
side of the crossing to mitil!ate a safetv concern. '
Remove & Replace 45 L.F. of Channel
Item No. 1-3 I The original channel downstream from the new installed box culvert was severely
deteriorated and did not drain properly. It was necessary to reconstruct 45 LF of
,
i channel.
e
e
e
Change Order No. One
Installation of Reinforced Concrete Box Culvert at 2128 Orange 8treet (8004-16).
Core Drill Drain Holes
Item No. 1-4 The top of the newly constructed channel blocked on-site drainage, which created a
water ponding situation. Therefore, the contractor was directed to core (4) 3-inch holes
in the channel wall for drainage.
Credit for Bid Item No 5
Item No. 1-5 Bid Item No. 5 was to replace a portion of the existing channel wall. With the
reconstruction of the entire channel, this item was no lon~er necessarv.
SUMMARY OF CONTRACT COSTS
The estimated revised contract cost is as follows:
Original Bid Amount. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... ...................$
Contract Change Order No. One............................. ....................$
Revised Construction Contract cost. . . . . . . . . . . . . . . . . . . . . . . . .. ....................$
45,300.00
33.424.00
78,724.00
This change order represents 73.78% of the original contract amount.
Section 3-2.1 of the Standard Specifications states that an increase in the total contract amount of more
than 25% must be accomplished by written Supplemental Agreement between the Contractor and
Agency, unless both parties agree to proceed with the change by Change Order.
The signatures hereon indicate concurrence that accomplishing this change by change order is acceptable
to both parties.
GRAND PACIFIC CONTRACTORS, INC.
CONTRACTOR
Accepted
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES
Approved
By:
By:
VALERIE C. ROSS
Director of Development Services
Title:
Date:
Date:
Approved by Mayor and Common Council
Date:
December 18, 2006
Item No.
2