REQUEST FOR COMMISSION/COUNCIL ACTION
From:
Roger G. Hardgrave, Dir.
of Public Works/City Engr.
Subject: Approval of Contract
Change Order No. 3 -
Improvements to Swim-
ming Pool at Boys &
Girls Club, per Plan
No. 8891 --
NADAR, INC.
Date:
August 10, 1993
Synopsis of Previous Commission/Council/Committee Action:
12-21-92 - Requests for CDBG financial assistance, in the amount
of $2,268,520, as submitted by the Community Develop-
ment Citizens Advisory Committee, approved.
02-15-93 - Plans approved and authorization granted to advertise
for bids.
04-05-93 - Awarded contract to Nadar, Inc., for low bid price of
$148,300.00.
Recommended Motion:
e
That Contract Change Order No. 3 to the contract with Nadar, Inc.
for the improvements to swimming pool at Boys & Girls Club, in
accordance ith Plan No. 8890, be approved; to reinstate Bid Item
No. 1 and Additive Alternates 1 and 2 to the contract, at the
original bid prices, at an increase in the contract price of
$99,400; from $150,100.00 to $249,500.00.
cc: K. Henderson
Timothy
Contact Person: Roqer G. Hardqrave
Phone:
5025
Project Area: N/A
Supporting Data Attached:
Ward(s): 1, 3 & 6
Staff Report,
Contract Chanqe Order No.3
FUNDING REQUIREMENTS:
Amount: $ 99,400
Source: CDBG
Budget Authority: Acct. 8063004
Commission/Council Notes:
e
Agenda Item No.:
yt
,
-
.
.
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
e
Approval of Chanqe Order No. 3
Improvements to SWimminq Pool at
Boys and Girls Club
The installation of a diving board and pool fencing were
initially removed from the Bid package for the renovation of the
swimming pool at the Boys & Girls Club due to the lack of
available funding. In the 1993/94 funding cycle, these improve-
ments are funded in Acco~nt 8063004.
Contract Change Order No.1, made at contract award, deleted Bid
Item No.1, and Alternate Bid Items 1 and 2 from the contract
wi th Nadar, Inc. The Contractor has agreed to construct these
improvements at the original bid prices, and it is proposed that
Contract Change Order No. 3 reinstate the items into the contract
with the low bidder, Nadar, Inc.
Below is an estimate of the additional work, based on the actual
low bid price.
Bid Item No. 1 Boys & Girls Club Pool $ 59,700.00
e Alternate No. 1 Diving Board 6,000.00
Alternate No. 2 Perimeter Fencing 33,700.00
Contract Sub-Total $ 99,400.00
Contract Admin. & Inspection
(Portion of w.o. jlO1408) 4,000.00
Sub-Total $ 103,400.00
Contingencies (4%) $ 4,700.00
Total Estimated Additional Cost $ 108,100.00
Funds have been allocated in CDBG Account No. 8063004 in an
amount of $108,100.00 as a part of the 1993/94 grant applications
to fund this planned work.
We recommend that Contract Change Order No. 3 be approved.
e 8-10-93
y!
e
e
e
.
.
.
CITY OP SAN BBRNARDINO
DBPARTHEKT OP PUBLIC WORKS
BNGINEBRING DIVISION
project: THE RENOVATION OF VARIOUS SWIMMING POOLS
pile No.: 7.37-82
Plan No.: 8891
Date: 8/5/93
COKTRACT CHANGB ORDBR NO. THUB
TO: NADAR, INC.
P.O. BOX 94235
Pasadena, CA. 91109
Gentlemen:
You are hereby authorized and directed to perform the followinq
work:
Reinstate Bid It_ No.1 ( BOYS AND GIRLS CLUB POOL), and Additive
Alternate No. 1 (BOYS AND GIRLS CLUB POOL DIVING BOARD) and
Additive Alternate No.2 (BOYS AND GIRLS CLUB POOL FENCING) to the
contract, at the oriqinal bid prices, for a total cost of
$99,400.00.
Total Bxtra Work Cost added to Contract .........$
99.400.00
150.100.00
249.500.00
Previous Contract Price .........................$
Amended Cost Price ...............................
Addi tional time to complete Contract due to ChllJl.qe Order -O-WorkinCl
Davs
COKTRACTOR
CITY OP SU BBRNARDINO
Accepted
Recollllllended
By:
By:
ROGBR G. HARDGRAVB DATB
Director of l'UJ:)lic Works/City Bnqr
Title:
Date:
~