CITY OF SAN BERNA8DINO
- REQUEST Fca COUNCIL ACTION
Files: 1.307/1.308/1.309
Contract Change Order No. TWO -
Subject: Installation of Guard Rail on
Little Mountain Dr., Rancho Ave.
and Waterman Avenue, per Plan
No. 8262 -- PALADIN CONSTRUCTION,
INC.
From: ROGER G. HARDGRAVE
Dept~ Public Works
Date: 1-06-93
AD;.!lN. Ofio'lC~
Synopsis of Previous Council action:
June, 1990 Allocation of $217,000 approved in 1990/91 Street
7 ,),,,i 95 9: 04 Construction Fund Budget.
OB-03-92 Plans approved and authorization granted to advertise
for bids, and the transfer of $10,200 approved.
10-05-92 Resolution No. 92-393 adopted awarding a contract to
Paladin Construction, Inc. for the low bid price of
$180,295.50.
Recommended motion:
That Change Order No. TWO to the contract with Paladin Construction,
Inc., for the installation of Guardrail on Little Mountain Drive,
Rancho Avenue, and ~;D.tcrman Avenue, in accordance with Plan No.
8262, be approvp.d, t~ authorize the Contractor to provide a Railroad
Protective r,iahility Insurance Policy, at an increase in the
contract nr~cc of $6,900.00; from $172,543.50 to $179,443.50.
cc:
Shauna Clark
Barbara Pachon
(JJ,~
r-
Contact person:
Roqer G. Hardqrave
Phone:
5025
Supporting data attached:
Staff Report, CCO #2
Ward:
3 & 5
FUNDING REQUIREMENTS:
Amount: $6.900.00 (Street Construction Fund)
Source: (Acct. No.1 242-362-57309
Acct. Descri tion Installation
Mountain Dr.. Rancho Ave. & Waterman Ave. Finance:
Council Notes:
75-0262
Agenda Item No.
7
CITY OF SAN BERNA.INO - REQUEST Foe COUNCIL ACTION
STAFF REPORT
Caltrans is requiring the Contractor to provide a Railroad
Protective Insurance Policy while performing the removal of the
existing concrete rail and the installation of the new Type 26
concrete barrier on Waterman Avenue, at the Southern Pacific
Railroad overpass south of Redlands Boulevard.
The Contractor will purchase the insurance policy and be
reimbursed for the costs incurred.
Contract Change Order No. One deleted a portion of the
temporary "K" Rail, and decreased the contract price by
$7,752.00. There is a total of $38,456.50 in contingencies
available to finance the additional costs of the Railroad
Protecti ve Insurance Policy. Cal trans will participate in the
financing of 90% of these additional costs, from Federal-Aid High
Hazard Elimination Funds.
We recommend that Contract Change Order No. 2 be approved.
1-06-93
75.0264
r---
.
.
COIITRACT CHUGB ORDBR NO. 2
ROAD Guardrail-Waterman Avenue
FBD NO. HES 3069(036)
TO: Paladin Construction Inc.
REV NO.
Bridge
SUPPLe NO.
SHBBT 1
COIITRACT NO.
OF 1
8262
You are hereby directed to make the herein described changes from the plans and
specifications or do the following described work not included in the plans and
specifications on this contract. NOTE: This change order is not effective until
aDDroved bv the state Hiahwav Enaineer
Description of work to be done, estimate of quantities, and prices to be paid.
Segregate between additional work at contract price, agreed price and force
account. Unless otherwise stated, rates for rental of equipment cover only such
time as eauiDment is actuallv used and no allowance will be made for idle time.
The last percentage shown is not accumulated increase of decrease from the
original quantity in the Engineers Estimate.
BXTRA WOU ATAGREBD PRICB:
Provide a Railroad Protective Insurance Policy for work to be performed on the
Waterman Avenue OVerpass, south of Redlands Blvd., at the agreed price of
$6,900.00.
BSTIMATBD COST DBCREASB S
By reason of this order the
34 working days
Submitted by:
INCREASB S 6.900.00
time of completion will be adjusted as follows:
Resident Bngineer,
Date:
Approval Recommended:
Date:
Approved:
city Bngineer
Date:
We the undersigned contractor, have given careful consideration to the change
proposed and hereby agree, if this proposal is approved, that we will provide all
equipment, furnish all material, except as may otherwise be noted above, and
perform all services necessary for the work above specified, and will accept as
full Davment therefor the Drices shown above.
Accepted Date:
Contractor:
By:
Title:
If the contractor does not siqn acceptance of this order, his attention is
directed to the requirements of the specifications as to proceeding with the work
and filing a written protest within the time therein specified.