CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: James Funk, Director
ORlGiNAl
Subject: Authorization to Submit Request
for Reimbursement to SANBAG for
Signing and Striping of Bicycle Lanes for
Phase I & Phase II of City Adopted Bicycle
Facilities Master Plan, per Plan No. 10229
and authorize the Director of Finance to
amend the FY 2002/03 budget.
Dept: Development Services
Date: May 30, 2003
File: 1.7116
MCC Date: 06/16/03
Synopsis of Previous Council Action:
10/15/01 Adopted Resolution No. 2001-320 awarding a contract in the amount of $40,889.39 to
JP Striping.
Recommended Motion:
1. Authorize the Director of Finance to execute the attached claim form marked Exhibit "C"
requesting reimbursement in the amount of $30,853.45 in accordance with Article 3, PUC
Section 99234a "Pedestrian and Bicycle Facilities" for Signing and Striping of Bicycle
Lanes for Phase I & Phase II of City Adopted Bicycle Facilities Master Plan, per Plan No.
10229.
2. Authorize the Director of Finance to amend the FY 2002/03 budget to transfer $26,623.18
in unallocated gas tax funds to Account No. 122-373-5504-7116 "Bikepath Valencia
A venue, Highland Ave to 40th St".
-~t:::-
Contact person: Michael Grubbs, Acting City Engineer
Phone' '1179
Supporting data attached: Staff Report & Report of Expenditures Ward(s)' 4 liT 7
FUNDING REQUIREMENTS: Amount: $26,623.18
Source: (Acct. No.) Unallocated Gas Tax
Acct. Description:
Finance:
I I
(PI l/p I/)'J.
. I U
Council Notes:
Agenda Item No. / (p
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Authorization to Submit Request for Reimbursement to SANBAG for Signing and Striping of
Bicycle Lanes for Phase I & Phase II of City Adopted Bicycle Facilities Master Plan, per Plan
No. 10229 and authorize the Director of Finance to amend the FY 2002/03 budget.
Background:
Staff successfully applied for Transportation Development Act (TDA) , Article 3 funding in
2000 allowing the City to proceed with a portion of the Bicycle Facilities Master Plan adopted
in 1994. This project extended the existing bicycle lanes from California State University San
Bernardino to Perris Hill Park along 40th Street, Mt View Avenue, Electric Avenue and
Valencia Avenue. This project added approximately 7 miles of bike lanes to previously
completed portions of Phases I and II of the master plan, including master planned bicycle lanes
along University Parkway, Kendall A venue and Northpark Boulevard.
A contract in the amount of $40,889.39 was awarded to JP Striping of Cherry Valley on
October 15, 2001. All construction work on this project has been completed and all claims
have been paid.
A report of expenditures is attached as Exhibit "A," indicating a total cost for the project of
$57,476.63, which included design, inspection and contract administration. However, due to
complaints by local residents, a portion of the work authorized by the grant was not completed.
Exhibit "B" indicates a comparison of the work authorized by the grant versus the actual work
done, which was on the master plan of bicycle lanes and is therefore eligible for reimbursement
under terms of the grant. The proportional cost of the work eligible for reimbursement from
SANBAG, at a reimbursement ratio of 88%, is $30,853.45. In order to obtain reimbursement
from SANBAG, the attached claim form marked Exhibit "C" must be executed by the Finance
Director and submitted to SANBAG. A minute action by the Mayor and Common Council is
required to authorize the Finance Director to execute the document.
Financial Impact:
Only $30,853.45 of the total project cost of $57,476.63 will be reimbursed under terms of the
grant from SANBAG leaving a shortfall of $26,623.18. Therefore, staff recommends that
$26,623.18 be transferred from unallocated gas tax funds to account no. 122-369-5504-7116
"Bikepath Valencia Avenue, Highland Ave to 40th St" to cover the un-reimbursed amount of the
total project cost.
2
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT (Continued)
Recommendation:
1 Authorize the Director of Finance to execute the attached claim form marked Exhibit "C"
requesting reimbursement in the amount of $30,853.45 in accordance with Article 3, PUC
Section 99234a "Pedestrian and Bicycle Facilities" for Signing and Striping of Bicycle
Lanes for Phase I & Phase II of City Adopted Bicycle Facilities Master Plan, per Plan No.
10229.
2 Authorize the Director of Finance to amend the FY 2002/03 budget to transfer $26,623.18 in
unallocated gas tax funds to Account No. 122-373-5504-7116 "Bikepath Valencia Avenue,
Highland Ave to 40th Sf'.
3
CITY OF SAN BERNARDINO
BIKEPATH - VALENCIA HIGHLAND
PROJECT 7116
122-373-5016/5504-7116
(126-369-5504-7116 - NO CHARGES)
PROJECT MUST BE COMPLETED BY 6/30102
Fund DeDt Obiect Account Title FYE 00 FYE01 FYE 02 Total
122 373 5016 Force Account Labor 1,363.11 5,594.11 935.98 7,893.20
122 373 5026 PERS Retirement 0.00 0.00 391.30 391.30
122 373 5027 Health & Life Insurance 0.00 0.00 603.88 603.88
122 373 5028 Unemployment Insurance 0.00 0.00 16.47 16.47
122 373 5029 Medicare 0.00 0.00 65.36 65.36
122 373 5504 Construction 0.00 50.00 47,446.94 47,496.94
1,363.11 5,644.11 49,459.93 56,467.15
126 369 5504 Construction 0.00 887.50 121.98 1,009.48
1,363.11 6,531.61 49,581.91 57,476.63
EXHIBIT "A"
06/13/2002
Bikepath Valencia 7116.xls
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES DEPARTMENT
INTEROFFICE MEMORANDUM
TO: James Funk, Director of Development Services
FROM: Anthony Lugo, Engineering Assistant III
SUBJECT: Valencia Avenue Bike lane Striping from 21st Street to 40tb Street per
Plan No. 10229 - Division of Costs.
DATE: May 30, 2003
COPIES: Mike Grubbs, Acting City Engineer
The grant application which was approved for the subject contract included installation of
Class II bike lanes on four city street segments as follows:
1. Valencia Avenue from Highland Avenue to 40th Street.
2. 40th Street form Electric A venue to Valencia Avenue
3. 40th Street from Kendall Drive to Acre Lane
4. Mt. View Avenue & Electric Avenue from Highland Avenue to
Northpark Boulevard
TOTAL APPLIED FOR
2.1 miles
0.9 mile
0.8 mile
2.8 miles
6.6 miles
During construction it was necessary to revise the scope of the project due to citizen
complaints. The revised locations, where master plan bike lane striping was completed
which is eligible for reimbursement under the grant, are as follows:
I. Mt. View Avenue from Highland to Northpark Blvd.
2. Valencia Avenue from 30th Street to 40th Street
TOTAL ELIGIBLE FOR REIMBURSEMENT
2.68 miles
1.3 3 miles
4.01 miles
The total mileage of bike lane striping eligible for reimbursement is 4.01 miles which is
61 % of the mileage as approved in the original grant. Therefore the proportional amount
of the cost eligible for consideration of reimbursement under the grant is 61 % of
$57,476.63 which equals $35,060.74.
If you have any questions regarding this matter, please contact me at (909) 384-5084.
~~
Antho ug
Engineering ssistant III
EXHIBIT "B"
San Bernardino Associated Governments
Local Transportation Fund - Article 3
Bicycle and Pedestrian Facilities
Financial Reporting Form
Claimant: City of San Bernardino
Date: 05/30/03
Certification: I certify that the information on this Project Information Form is true and accurate
to the best of my knowledge.
Signed:
1. Project Name: 40th StreetlValencia Bikeway Project
Budget 0/0 Actual %
Total Project Expenditure S 131,000 $35,060.74
IDA Article 3 (SB 821) $ 115,000 88% $30,853.45
Local (Match) $ 16,000 12% $ 4,207.29
2. Project Name:
Budget % Actual %
Total Project Expenditure
IDA Article 3 (SB 821)
Local (Match)
3. Project Name:
Budget 010 Actual %
Total Project Expenditure
IDA Article 3 (SB 821)
Local (Match)
4. Project Name:
Budget 0/0 Actual %
Total Project Expenditure
IDA Article 3 (SB 821)
Local (Match)
LTF Art 3 Claim CityofSB 03.dol
EXHIBIT "C"
San Bernardino Associated Governments
Local Transportation Fund - Article 3
Bicycle and Pedestrian Facilities .
Claim Form
Fiscal Year: 2001-2002
Date: 05/30/03
Claimant: City of San Bernardino
300 North "D" Street
San Bernardino, CA 92418
Attention: Barbara Pachon
Title: Finance Director
Amount:
$30,853.45
Purpose:
o Article 3, PUC Section 99234a Pedestrian and Bicycle Facilities
Authorizing Signature:
(Claimant's Chief Administrator or
Financial Officer
(Signature)
Barbara Pachon, Finance Director
(Type Name & Title)
Condition of Approval:
Approval of this claim and payment by the County Auditor to this claimant are
subject to monies being available, and to the provision that such monies will be used
only in accordance with the allocation instruction.
LTF ArtJ Cloim CityofSB OJ.dOI
EXHIBIT "c"
Medina Sa
From:
Sent:
To:
Cc:
Subject:
Pachon_Ba
Monday, June 16, 2003 12:30 PM
Clark_Ra
Wilson_Fr; Medina_Sa
Counicl Agenda Today - Items #15 & #16
Importance:
High
I was just looking over the items on today's agenda and the following items need to have their
motions corrected:
Item # 15. Motion #1 should be chanCled to:
Authorize the Finance Director to amend the FY 2002-2003 Budget to transfer $129,500 from
Account No. 126-369-5504-7306 "Slurry Seal at Various Locations" to Account No. 126-369-5504-
7246 "Acquire Right of Way and realignment Laurelwood Drive," and
The above new #1 motion changes the second account number to the correct one.
Item # 16. Motion #2 should be chanCled to:
Authorize the Director of Finance to amend the FY 2002-2003 budget to transfe~~in
unallocated Gas Tax Funds to Account No. 126-369-55~ 16 "Bikepath Vale~ue,
Highland Ave. to 40th Street". .
The above new #2 motion changes the dollar amount and the account number.