HomeMy WebLinkAbout39-Public Works
o
o
1.215 IMPROVEMENT PROJECT
crrv COUNCIL BRIEFING
CITY OF SAN BERNARDINO
NOVEMBER 19, 1990
12:00 PM
/
J9
o
o
1.215 IMPROVEMENT PROJECT
CITY COUNCIL BRIEFING
Novelllber 19, 1990.12:00 PM
City of San Bernardino
AGENDA
PROJECT TEAM
BRIEF PROJECT HISTORY
GOALS AND OBJECTIVES
DESCRIPTION OF PREUMINARY ALTERNATIVES
ENGINEERING ISSUES AND CONCERNS
ENVIRONMENTAL ISSUES AND CONCERNS
MILESTONE SCHEDULE
QUESTIONS, DISCUSSIONS. AND COMMENTS
o
o
'-215 'MPROVEMENT PROJECT
pROJECT TEAM
Ken Steele
Bill Ojeda
Pat Connally
David Parra
CALTRANS
District Director
Deputy District Director
Contract Manager
Measures Environmental Branch
SAN BERNARDINO ASSOCIATION OF GOVERNMENTS
Wes McDaniel
Kerry Forsythe
Bob Wirts .
Executive Director ~
Deputy Executive Director
Staff Engineer
PARSONS BRINCKERHOFF QUADE & DOUGLAS, INC.
Don Capelle
Mike SpIegel
Belly Bowers
Project Manager
Engineering Manager
Environrnental Manager
MYRA L. FRANK & ASSOCIATES, INC.
I
I
I
I
I
I
I
Gary Patersen
Annette Mercer
Senior Environmental Planner
Environrnental Planner
o
o
1.215 IMPROVEMIENT PROJIECJ'
PROJIECJ' HISTORY
Backgr_nd
The existing north/south freeway assigned as Interstate 215 was planned and constructed in a
series of projects during the 1950's. Routing studies Included alternatives as much as two or three
miles to the west of the as constructed JocaIion. to a block or so east of the location. Two
north/south highways (Mt. Vernon Avenue and "E"Street) were uIIimateIy replaced with what Is now
Interstate 215, located about four blocks west of"E" Street on what was know as the "I" Street
alternate.
Historically, the City of San Bernardino near its central business district has been separated by the
transcontinental Santa Fe Railway mainline trackage, which parallelecl "r Street. During the late
1940's and the 1950's, heavy freight traffIC reached the point where the community was seeking any
solution to the separalicn problem between the eastern and western parts of the CIty. ThIs situation
played an extremely important role. In the selection of the "r Street alternate by the Department and
the California Hghway Commission. It was believed that adoption of the T Street alternate would
necessitate grade separalion of some local streets and the freeway In a WEri that would also require
separation structures across the transcontinental railway lines, particularly between Third Street and
Highland Avenue.
The adoption of the "r Street alignment required that freeway construction be immediately edjacent
to the railroad. This resulted In the construction of the left-hand off- and on-ramps for the
southbound lanes at both the BaselIne and 5th Street Interchanges. A secondary impact of the
selected alignment was the connection of ramp tarmlnaIs at lhasa local service interchanges to
nearby city streets In neu of direct connections to the major cross street. The result was ramp
terminals at 4th Street and 6th Street, Orange/1 0Ih and 13th Street. The 5th Street/Baseline local
service interchanges haWfbeen the object of social and political concern since about 1972.
o
o
'.215 'MPROVEMENT PROGRAM
CHRONOLOGY OF '.215
Interstate 215 has been know by several other route numbers during the past years including Route
43. Route 194. 1-15E and 1-215. The route was revised to Legislative Route 215 effective 1/1/83.
1956
1959
1970
1971
June 1971
August 1971
October 1971
May 2, 1972
1973
1988
April 1989
Freeway Agreement
The ConstructIon of Route 215 through San B8mardino was completed.
San Bernardino Was advised in a report by Economics Research Associates
that the western development 01 the CIty was being Impeded by the obsolete
design of the interchanges.
Senate Concurrent Resolution No. 82 requested the Department to conduct
a study on the feasibility and practicality of rebuilding a portion of the freeway
to modern design standards. The report was completed in January 1972
and concluded that it was possible and practical to rebuild portions of the
freeway.
CALTRANS meets with Inland Action, Inc., a local citizen group, to present
future Impr~ to Route 215 In the vicinity of 5th Street. The discussion
centered on access to the Central CIty Project and the west side area.
CALTRANS meets with CIty Councilmen concerning proposals.
CALTRANS meets with Inland Action. Inc. to present future improvements in
the vicinity of Baseline Street.
Project Report #&J75 approved for operationallmprovernents between
Inland Center Drive and Route &J. Eight lanes with a 22' median.
Reconstruction of the Route 10/215 Interchange.
1988 STlP (247c) Route 10 to Route 66
Subject to California Transportation Commission (CTC) Resolution #G-85-4
Public Information Meeting was held to discuss a study for operational
improvements. .
o
o
'-215 'MPROVEMENT PROJECT
PROJECT COALS AND OBJECTIVES
1. Improve Traffic Safety and Operational Characteristics
2. Improve Freeway Access And Freeway Capacity
3. Accommodate Local Planning Goals
4. . Reduce Barrier Effect Of 1-215 By Replacing The Left Entrance And Exit Ramps With
Improved Access
5. Minimize Environmental Impacts
6. Improve Freeway Aesthetics
7. Develop A Coordinated Infrastructure Plan With The AT&SF Railway
~~
ALTERNA11VE 1
ALTERNA11VE 2
ALTERNA11VE 3
o
o
'.215 'MPROVEMBNTPROGRAM
PRBUM'NARY AL'fERNATlVES AND OFl'lONS
ADD ONE LANE IN EACH DIRECTION WITH A UMITED FRONTAGE ROAD
SYSTEM
Frontage Road System with access control proposed from Orange Show
Road to Mill Street and from 4th Street to 16th Street. Eliminate a1llett-hand
entrance- and exit-remps. Replace aU hook ramps. Use of split diamond
type Interchange conIiguratior)s. Use of Auxiliary lanes to provide adequate
-weaving distanCes. Unrestricted right-of-way requirements.
ADD ONE LANE IN EACH DIRECTION WITH A UMITED FRONTAGE ROAD
SYSTEM
Basically the same as Alternative 1 with the following exceptions: Frontage
Road System north of 1 st StrllElt ls.the same as Alternative 1. Variation is in
Frontage Road System between Orange Show Road and Mill Street. Right-
of-~ requirements are minimized with the use of retaining walls.
ADD ONE LANE IN EACH DIRECTION WITH A CON11NUOUS FRONTAGE
ROAD SYSTEM
Fun length Frontage Road System proposed from Orange Show Road north
10 Baseline Street. Use of slip ramps for access to and from the Frontage
Road System and the Freeway.
OPTIONS FOR ALL ALTERNATIVES
HIGH OCCUPANCY VEHICLE (HOV) OPTION
Each a1temative has the option for lane additions be HOV lanes rather than
mixed flow lanes.
RAILWAY RElOCATION OPTION
Each alternative has the option to be designed with the AT&SF railway
relocated out of the area, and its right-of-way used for fr~lFrontage
Road System improvements.
o
o
'-215 'MPROveMENT PROJECT
ENC'NEEII'NG 'SSUES AND CONCERNS
1. Maintenance of traffic flow on the freeway during construction.
2. Replacement of bridge structures.
3. Conflicts between right-of-way needs and existing uses.
4. Impacts of alternative ramp patterns on local roads.
o
o
'-215 'MPROVEMENT' PRO.IECT
ENVlIIONMEN'rAL ,SSUES AND CONCERNS
1. Displacement Of Residents And Businesses
2. Noise
3.. Construction Impacts
4. Community Impacts
5. Accessibility
6. Safety
7. Consistency With Development Plans & Goals
8. Aesthetics
9. Historic Resources
10. Parklands
o
o
1.215 IMPROVEMENT PROGRAM
MIU:STONE SCHEDUU:
Consultant on Board
First Mlleatone.
Begin Permit Applications .
EstabrlSh Project Development Team
Project Category Determination
. Environmental Checklist
Publish Notice of Intent
Second M.....one.
Written Notice of Initiation of Studies
TraffIC Analysis
Preliminary Geometric Drawings with Plan and Profile
for all Alternatives with Cost Estimates
Praliminary Typical x-Secticins
Preliminary Detour Drawings
Area of Potential Effect Map
Advanced Planning Studies (Structure Estimates)
Hold Initial Public Informational Meetings
Preliminary RI'N Requirements
Third Milestone.
Draft Archaeologic8l Survey Report
Draft Historic Architecture Survey Report
Draft Historic Property Survey Report
Scoping Report
Notice of Preparation
Cooperating ArJency Request
Hold Public Meeting
Fourth MDestone.
Prepare Stage II Work Program
Draft Natural EnIIironmental Survey Report
Draft Background SocIoeconomic Report
Draft I'Jr Quality Report
Draft Energy Analysis
Draft Visual Impact Assessment
Draft Noise Report
Draft Technical Studies Reports
Draft Biological Assessment
Request Biological Opinion
Draft Floodplain Evaluation Report
Draft Location Hydraulic Study
Draft Geotechnical Study .
Draft Section 4(f) Evaluation
Draft Water Quality Study
Draft Parking/Circulation Impact Report
Draft RI'N Relocation Impact Study
-
DUE DATE
Nov. 1989
Dee. 1989
Nov. 1990
Nov. 1990
M8r.1991
L
.
o
o
Fifth Milestone.
Final Environmental Studies and Reports
Draft Project Report
Inilial Draft Envlronmentallmpact Statement to Caltrans for Review
Effect Fanding for Historic Architectural Properties ,
Hold Pubfte Meeting
Sixth Milestone.
Project Report and DEIS
Seventh Milestone.
. Notice of Public HearIng
Circulate DEIS for Cormnent
Hold Public Meeting
Eighth Milestone.
, Public HearIng
Ninth Milestone.
Record of Public HearIng
Response to Comments on DEIS
Tenth Milestone.
Select Preferred Alternative
Eleventh Milestone.
Final EIS Completed
Project Approval Report Completed
Consultant Available for Consultation
Draft Record of Decisjon
Draft Findings'
Draft Notice of Determination
Twelfth Milestone.
Final EIS Available for A-95 Review, Public, etc.
Project Approval by State
Notice of Determination Filed
Project Approval by FHWA
-
-
June 1991
Aug. 1991
Nov. 1991
Dec. 1991
Feb. 1991
Mar. 1992
June 1992
Oct. 1992
-
o
o
'-215 'MPROVEMEN'I' PROJECT
CITY COUNC'L 8R'EFlNG
CITY OF SAN BERNARDINO
~
NOVEMBER 19, 1990
12:00 PM
o
o
1-215 IMPROVEMENT PROJECT
CITY COUNCIL BRIEFING
November 19, 1990 . 12:00 PM
City of San Bernardino
AGENDA
PROJECT TEAM
BRIEF PROJECT HISTORY
GOALS AND OBJECTNES
DESCRIPTION OF PREUMINARY ALTERNATNES
ENGINEERING ISSUES AND CONCERNS
ENVIRONMENTAL ISSUES AND CONCERNS
MILESTONE SCHEDULE
QUESTIONS. DISCUSSIONS, AND COMMENTS
o
o
'-215 'MPROVEMENT PROJECT
PROJECT TEAM
CALTRANS
Ken Steele
Bill Ojeda
Pat Connally
David Parra
District Director
Deputy District Director
Contract Manager
Measures Environmental Branch
SAN BERNARDINO ASSOCIATION OF GOVERNMENTS
Wes McDaniel
Kerry Forsythe
BobWirts
Executive Director
Deputy Executive Director
Staff Engineer
PARSONS BRINCKERHOFF QUADE & DOUGLAS, INC.
Don Capelle
Mike Spiegel
Betty Bowers
Project Manager
Engineering Manager
Environmental Manager
MYRA L FRANK & ASSOCIATES, INC.
Gary Petersen
Annette Marcer
Senior Environmental Planner
Environmental Planner
o
o
'.215 'MPROVEMENT PROJECT
PROJECT H'STORY
Background
The existing northIsouth freeway assigned as Interstate 215 was planned and constructed in a
series of projects during the 1950's. Routing studies included alternatives as much as two or three
miles to the wast of the as constructed location, to a block or so eest of the location. Two
northIsouth highways (MI. Vernon Avenue and 'f" Street) were ultimately replaced with what is now
Interstate 215, located about four blocks wast of 'f" Street on what was know as the 'I' Street
alternate.
Historically, the City of San Bernardino neer its cantral business district has been separated by the
transcontinental Santa Fe Railway mainline trackage, which paralleled 'I' Street. During the late
1940's and the 1950's, heavy freight traffic reached the point where the community was seeking any
solution to the separation problem between the eastern and western parts of the City. This situation
played an extremely important role in the selection of the 'I' Street alternate by the Department and
the California Highway Commission. It was believed that adoption of the 'I' Street alternate would
necessitate grade separation of some IocaJ streets and the freeway in a WErt that would also require
separation structures across the transcontinental railway lines, particularly between Third Street and
Highland Avenue.
The adoption of the 'I' Street alignment required that freeway construction be immediately adjacant
to the railroad. This resulted in the construction of the left-hand off- and on-ramps for the
southbound lanes at both the Baseline and 5th Street Interchanges. A secondary impact of the
selected alignment was the connection of ramp terminals at these IocaJ service interchanges to
nearby city streets in lieu of direct connections to the major cross street. The result was ramp
terminals at 4th Street and 6th Street, Orange/10th and 13th Street. The 5th StreeVBaseline local
service interchanges have'been the object of social and political concam since about 1972.
o
o
'-215 'MPROVEMENT PROGRAM
CHRONOLOGY OF '-215
Interstate 215 has been know by several other route numbers during the past years including Route
43, Route 194, 1-15E and 1-215. The route was reviseclto Legislative Route 215 effective 1/1/83.
1973
Freeway Agreement
The Construction of Route 215 through San Bernardino was completed.
San Bernardino was advised in a report by Economics Research Associates
that the western development of the City was being impeded by the obsolete
design of the interchanges.
Senate Concurrent Resolution No. 82 requested the Department to conduct
a study on the feasibility and practicality of rebuilding a portion of the freeway
to modem design slanderds. The report was completed in January 1972
and concluded that it was possible and practical to rebuild portions of the
freeway.
GAL TRANS meets with Inland Action, Inc., a local citizen group, to present
future improvements to Route 215 in the vicinity of 5th Street. The discussion
centered on access to the Central City Project and the west side erea.
GAL TRANS meets with City Councilmen conceming proposals.
GAL TRANS meets with Inland Action, Inc. to present future improvements in
the vicinity of Baseline Street.
Project Report #3075 approved for operational improvements between
Inland Center Drive and Route 30. Eight lanes with a 22' median.
Reconstruction of the Route 10/215 Interchange.
1988 STlP (247c) Route 10 to Route 66
Subject to California Transportation Commission (CTC) Resolution #G-85-4
Public Information Meeting was held to discuss a study for operational
improvements.
1956
1959
1970
1971
June 1971
August 1971
October 1971
May 2,1972
1988
April 1989
]
o
o
'.215 'MPROVEMENT PROJECT
PROJECT GOALS AND OB.lECTlVES
1. Improve TraffIC Safety and Operational Characteristics
2. Improve Freeway Access And Freeway Capacity
3. Accommodate Local Planning Goals
4. Reduce Barrier Effect Of 1-215 By Replacing The Left Entrance And Exit Ramps With
Improved Access
5. Minimize Environmental Impacts
6. Improve Freeway Aesthetics
7. Develop A Coordinated Infrastructure Plan WIlh The A T&SF Railway
ALTERNATIVE 1
ALTERNATIVE 2
ALTERNATIVE 3
o
o
'.215 'MPROVEMENT PROGRAM
PREUM'NARY ALTERNATIVES AND OPJ'lONS
ADD ONE LANE IN EACH DIRECTION wmt A UMITED FRONTAGE ROAD
SYSTEM
Frontage Road System with access control proposed from Orange Show
Road to Mill Street and from 4th Street to 16th Street. Eliminate all left-hand
entrance- and exit-ramps. Replace all hook ramps. Use of split diamond
type Interchange configurations. Use of Auxiliary lanes to provide adequate
weaving distances. Unrestricted right-of-way requirements.
ADD ONE LANE IN EACH DIRECTION wmt A UMITED FRONTAGE ROAD
SYSTEM
Basically the same as A1temative 1 with the following exceptions: Frontage
Road System north of 1 st Street is the same as Alternative 1. Variation is in
Frontage Road System between Orange Show Road and Mill Street. Right-
of-~ requirements are minimized with the use of retaining walls.
ADD ONE LANE IN EACH DIRECTION WITH A CONTINUOUS FRONTAGE
ROAD SYSTEM
Full length Frontage Road System proposed from Orange Show Road north
to Baseline Street. Use of slip ramps for access to and from the Frontage
Road System and the Freeway.
OP110NS FOR ALL ALTERNATIVES
HIGH OCCUPANCY VEHICLE (HOV) OPTION
Each a1temative has the option for lane additions be HOV lanes rather than
mixed now lanes.
RAILWAY RELOCATION OPTION
Each alternative has the option to be designed with the A T&SF railway
relocated out of the area, and its right-of-way used for fr~lFrontage
Road System improvements.
o
o
1-215 IMPROVEMENT PROJECT
ENGINEERING ISSUES AND CONCERNS
1. Maintenance of traffic flow on the freeway during construction.
2. Replacement of bridge structures.
3. Conflicts between right-of-way needs and existing uses.
4. Impacts of alternative ramp patterns on local roads.
o
o
'.215 'MPROVEMENT PROJECT
ENVIRONMENTAl. 'SSUES AND CONCERNS
1. Displacement Of Residents And Businesses
2. Noise
3. Construction Impacts
4. Community Impacts
5. Accessibility
6. Safety
7. Consistency With Development Plans & Goals
8. Aesthetics
9. Historic Resources
10. Parklands
j
o
o
'-215 'MPROVEMENT PROGRAM
M'LESTONE SCHEDULE
DUE DATE
First Milestone.
Begin Permit Applications
Establish Project Development Team
Project CatllQOlY Determination
. Environmental Checklist
Publish Notice of Intent
Second Milestone.
Written Notice of Initiation of Studies
TraffIc Analysis
Pralimina/Y Geometric Drawings with Plan and Profile
for all Alternatives with Cost Estimates
Prefimina/Y Typical X-Sections
Preliminary Detour Drawings
Area of Potential Effect Map
Advanced Planning Studies (Structure Estimates)
Hold Initial Public Informational Meetings
Preliminary ANI Requirements
Third Milestone.
Draft Archaeological Survey Report
Draft Historic Architecture Survey Report
Draft Historic Property Survey Report
Scoping Report
Notice of Preparation
Cooperating Agenr:J1 Request
Hold Public Meeting
Fourth Milestone.
Prepare Stage II Work Program
Draft Natural Environmental Survey Report
Draft Background Socioeconomic Report
Draft />Jr Quality Report
Draft Energy Analysis
Draft VISUal Impact Assessment
Draft Noise Report
Draft Technical Studies Reports
Draft Biological Assessment
Request Biological Opinion
Draft Floodplain Evaluation Report
Draft Location Hydraulic Study
Draft Geotechnical Study
Draft Section 4(f) Evaluation
Draft Water Quality Study
Draft Parking/Circulation Impact Report
Draft ANI Relocation Impact Study
Nov. 1989
Dec. 1989
ConsuRant on Board
Nov. 1990
Nov. 1990
Mar. 1991
. .
o
o
Fifth MI..sto_.
Final Environmental Studies and Reports
Draft Project Report
Initial Draft Environmental Impact Statement to Caltrans for Review
Effect Finding for Historic Architectural Properties
Hold Public Meeting
Sixth Milestone.
Project Report and DEIS
Seventh Milestone;
. Notice of Public Hearing
Circulate DEIS for Comment
Hold Public Meeting
Eighth Milestone:
. Public Hearing
Ninth Milestone.
Record of Public Hearing
Response to Comments on DEIS
Tenth Milestone.
Select Preferred Alternative
June 1991
Aug. 1991
Nov. 1991
Dec. 1991
Feb. 1991
Mar. 1992
Eleventh Mil_tone:
Final EIS CornpIeted
Project Approval Report CornpIeted
Consultant Avai/able for Consultation
Draft Record of Decisjon
Draft Findings
Draft Notice of Determination
June 1992
Twelfth Mllesto_.
Final EIS Available for A-95 Review. Public, etc.
Project Approval by State
Notice of Determination Filed
Project Approval by FHWA
oct. 1992