February 2, 1990
To: Shauna Clark, City Clerk
Re: SPECIAL MEETING
NOTICE IS HEREBY GIVEN that the Mayor of the City of San
Bernardino has called a Special Meeting of the Mayor and Common
Council/Community Development Commission for 11:00 a.m., Monday,
February 5, 1990, in the Council Chambers of City Hall, 300 North
"D" Street, San Bernardino, California.
The purpose for which this meeting has been called is to
consider recommendation of funding sources for street
improvements from bond proceeds and authorization to proceed with
work, with the following proposed motions:
1. Authorize the funding of the streets designated in
Exhibits 1 - 8 for paving with $790,683.00 from RDA Tax
Allocation Bonds and $763,229.00 from the City's share
of proceeds from the sale of the CMO's.
2. Authorize the Director of Public Services to take the
necessary action to pave the streets designated in
Exhibits 1 - 8 with City personnel and equipment.
3. Authorize the Director of Public Services to seek bids
for the cold planing of certain designated streets
listed within Exhibits 1 - 8 as deemed necessary.
SHAUNA CLARK
City Clerk
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --
STATE OF CALIFORNIA )
COUNTY OF SAN BERNARDINO ) SS
CITY OF SAN BERNARDINO )
I HEREBY CERTIFY that notice of this Special Council Meeting was
served by handing a copy of the above notice to:
on
1990,
at
Server:
Title:
I ,
CITY OF SAN BERti-HRDINO - REQUEST FOR COUNCIL ACTION
From: Marshall W. Julian
Subject: Recommendation of funding sources
for street improvements from
bond proceeds and authorization
to proceed with work
Dept: Administrative
Date: February 5, 1990
Synopsis of Previous Council action:
July 11, 1989
Mayor and Common Council approve Budget for FY 89-90,
which includes designated street improvements which
are federal-aided projects
December 7, 1989
Approved the use of bond proceeds and use of tax
increment funds for designated street paving and
street improvement projects included in FY 89-90
Budget.
Recommended motion:
1.
That the funding of the repair and improvement of the streets designated
in Exhibits 1-8 be approved from tax allocation bond proceeds and incre-
ment funds, in the amount of $790,683, and from the City's share of CMO
proceeds, in the amount of $763,229.
2.
That the Mayor and Common Council determine that the work required to re-
pair and improve the streets designated in Exhibits 1-8 can be performed
by City Forces and that the Director of Public Services be directed to
have such work performed.
~~~~
Contact person:
Marshall W. Julian
Phone:
5122
Supporting data attached:
Yes
Ward:
City-wide
FUNDING REQUIREMENTS:
Amount:
$l,811,512
RDA - $865,683
CMO - $945,829
Source: (Acct. No.)
(Acct. Description)
Finance:_(~W )j,..J./-
Council Notes:
SP2C/AL H1~Lr/p~
SII4.srJTIIT E
J
'CITY OF SAN BERN.. ~RDINO - REQUEST FuR COUNCIL ACTION
STAFF REPORT
RECOMMENDED MOTIONS: Continued
3. That the Director of Public Services be authorized to seek bids for the
cold-planing of such streets designated in Exhibits 1-8 as may be
necessary.
4. That the funding of the matching portion of the cost for the Federal Aid
street/signal projects designated in the memorandum from the Director of
Finance be approved from tax allocation bond proceeds, in the amount of
$75,000, and from the City's share of CMO proceeds, in the amount of
$182,600.
5. That staff be directed to take the necessary steps to transfer funds to
the appropriate accounts.
Attached (Exhibits 1 - 8) are the list of streets recommended to be
repaved by the Director of Public Services. The first list concerns
major arteries to be done. The next seven lists are those residential
streets to be resurfaced and they are listed by ward.
Staff has researched which streets can be funded with Redevelopment Funds
and which streets the City needs to use the bond proceeds from the
Collateralized Mortgage Obligations (CMO). In addition, we have designated
what Redevelopment Project Area they are within. Funds allocated
from the CMOs for street resurfacing total $763,229. The total funds
needed from Redevelopment Funds are $790,683.
In addition to the resurfacing funding, the Mayor and Common Council
approved on December 7, 1989, the use of bond proceeds for federal-aided
projects which requiring City matching funds. This amount totals $257,600
with $75,000 coming froM RDA Bond proceeds and the remaining $182,600
coming from the CMO proceeds.
The Mayor and Common Council and the Community Develo~ment COMmission need
to authorize these funding allocation and authorize the Director of
Public Services to proceed with the street resurfacing program attached.
7c:;,.n?';4
CITY OF SAN ~ERNARDINO
-
MEMORANDUM
To
W. R. Holcomb, Mayor
From Manue I P. Moreno, Jr.
Director of Publ ic ServicE
Date January 12, 1990
Subject
Resurfac i ng
Approved
Date
Attached please find a I ist of Residential
scheduled for" resurfacing in March 1990.
require resurfacing and Cold Planing.
and Major Arteries that are
Some of these streets will
Please cal I me if yo~ have any questions on this matter.
. 'f1!1 a.l4V....l ,P aY\ ~ I
Manuel P. Moreno, Jr.
Director of Publ ic Services
cc: Marshal I Jul ian. City Administrator
James Robbins, Deputy City Administrator
Phi I Arviso, Executive Assistant to Counci I
AI I Counci I Members
Craig Graves, Treasurer
Andrew G~een, Director of Finance
Roger Hardgrave, Director of-Publ ic Works
Larry Reed, Director of Planning and Sui Iding and Safety
Anwar Wagdy, Traffic Engineer
Traffic Signal Department
MPM:dlw
~ ,." ;~-;.;~-::.:::,
" ... . '-:..1 - - --
.. .... ,
--.: ~.-."
.,~,
MAJOR ARTERIES - ALL WARDS
Northpark Blvd: Electric to "H" St
Perris Hi I I Rd: Pacific north to Flood Cntrl
"H" St: 6th St to 9th St
Arden: Highland to Pacific
5th St: Sterl ing east to City Limits
6th St: Sterl ing east to City Limits
Harrison: 35th St to 40th St
Court St: "0" St to "E" St
3rd St: "I" St to 2nd St
5th St: Victoria west to City Limits
MT Vernon: 21st St to Cajon
Pacific: Central to Orange
Pacific: Arden to Flood Control
Pepper: Spruce to 6th St
Arrowhead: Mi I I to 3rd St
University Blvd: 215 Fwy to Cot lege
Mi II St: "Ell St to Waterman
Gi Ibert: Waterman to 207' e/o Cedar
"DII St: Rialto to 2nd St
Rialto: "I" St to Mt Vernon
Rialto: Arrowhead to "E" St
40th St: Waterman to Sierra Wy
4th St: Waterman to Sierra Wy
"E" St: Mi I I to Orange Show Rd
"I" St: Rialto to 3rd St
Or-ange Show Rd:
Redlands Blvd: Hunts Ln to Waterman
6th St: "H" St to "G" St
LOCATION
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
'15.
'16.
--, 7.
'18.
.19.
.20.
.21.
.22.
.23.
'24.
'25.
.:6.
*27.
.28.
* Wi I I require Header Cut or Ful I Width Cut
TONNAGE
1,690
660
650
775
480
360
730
170
1,135
435
300
420
750
250
2,385
2,125
2,650
1,280
315
1,235
410
710
575
2,120
385
590
1,200
300
25,085
"Exhibit I"
RDA-UPT
RDA-CC
RDA-UPT
RDA-NW
RDA-CC
RDA-STC
RDA-CC
RDA-CC
RDA-UPT
RDA-CC
RDA-CC
RDA-CC
RDA-UPT
RDA-CC
RDA-SV
RDA-CCN
PROJECT COST
$ 53,053.00
20,824.00
20,523.00
24,407.00
15,180.00
.11,363.00
23,039.00
5,374.00
35,860.00
13,763.00
9,466.00
13,264.00
23,637.00
7,898.00
90,174.00
73, 165.00
97,521.00
49,315.00
12,042.00
45,715.00
13,981.00
23,934.00
19,657.00
69,660.00
12,645.00
19,732.00
39,989.00
11 ,300.00
$856,481.00
WARD 1
LOCATION TONNAGE PROJECT COST
1. Redick: Arrowhead to Pershing 65 RDA-CC $ 2,062.00
2. Pershing: Cluster to Hi Ida 220 RDA-CC 6,987.00
3. Garner: 7th St to Vine 40 1,258.00
4. Perris: 6th St to 9th St 390 12,353.00
*5. Vine: Mt. Vernon to Davidson 270 11,037.00
6. Doo I i tt Ie: Mi II to Dead-end 310 9,753.00
7. Mt. View: Rialto to 2nd St 240 RDA-CC 7,583.00
8. 7th St: Arrowhead to "E" St 410 RDA-CCN 13,000.00
9. 8th St: Arrowhead to "E" St 410 RDA-CCN 13,000.00
10. 7th St: Waterman to Sierra Way 560 RDA-CC 17,703.00
*11. Ciescent: 7th St to 6th St 120 RDA-CCN 4,980.00
3,035 $99,716.00
* Wi I I require Header Cut or Ful I Width Cut
"Exhibit 2"
WARD 2
I_OCA T I ON TONNAGE PROJECT COST
*1. 10th St: "0" St to "G" St 760 RDA-UPT $26,465.00
2. 16th St: '....aterman to Dead-end 385 12,165.00
3. 17th St: Waterman to Cu I de Sac 250 7,938.00
4. 13th St: "0" St to Arrowhead 145 RDA-UPT 4,576.00
5. 16th St: "E" St to Arrowhead 365 RDA-UPT 11,609.00
6. 01 ive: Waterman to Mt View 510 16,181.00
7. 16th St: "H" St to "G" St 145 4,583.00
*8. 13th St: Sierra Way to Mt View 150 5,882.00
*9. Berkley: Sase line to 13th St 155 6,071.00
10. Stoddard: 16th St to 15th St 125 RDA-UPT 3,902.00
2,990 $99,372.00
* Wi II require Header Cut or Fu II Width Cut
"Exhibit 3"
WARD 3
LOCATION TONNAGE PROJECT COST
1. Lugo: Central to Dead-end 280 $ 8,840.00
2. Eureka: Mi II to Esperanza 130 4, 123.00
3. Etiwanda: Meridian to Pepper 295 9,302.00
*4. Blood Bank Rd: "E" St to Entrance 230 9,132.00
5. Steele Rd: Wier Rd to Industrial Rd 210 RDA-SV 6,631.00
6. Commercial Rd: Waterman to Steele Rd 305 RDA-SV 9,650.00
7. Adell: Inland Center to "H" St 145 RDA-CC 4,576.00
8. College: Cl"escent to "HI! St 120 RDA-CC 3,813.00
9. Huff: "H" St to "G" St 235 RDA-CC 7,435.00
10. Crescent: Mi II to Co I lege 245 RDA-CC 7,728.00
11. Sierra Wy: Central to Dead-end 510 RDA-CC 16,087.00
12. Benedict: Arrowhead to Sierra Wy 195 RDA-CC 6,184.00
13. Hi I I crest: Arrowhead to Sierra Wy 195 RDA-CC 6,184.00
3,095 $99,685.00
* Wi II require Header Cut or Ful I Width Cut
"Exhibit 4"
WARD 4
LOCATION TONNAGE PROJECT COST
*1. Mt View: Electric to 40th St 455 $17,676.00
2. Dumbarton: Marsha I I to Cui de Sac 100 3,161.00
3. Eureka: Mountain to Conejo 165 5,229.00
4. C I i fton: Central to Orange 250 7,981.00
5. Vi Ila Court: C I i fton to Cu I de Sac 105 3,315.00
6. Pepper Court: C I i fton to Cu I de Sac 105 3,315.00
7. 01 ive Tree Court: C I i fton to Cu I de Sac 105 3,315.00
8. Li II ian Court: C I i fton to Cu I de Sac 105 3,315.00
9. Orange: Central to Fisher 170 5,381.00
*10. Sepulveda: 40th St to Sierra Way 605 22,973.00
11. Pershing: 48th St to 50th St T80 5,679.00
12. Sierra Road: 49th St to 54th St 300 9,497.00
13. 50th St: Leroy to SepGI veda 145 4,].77.00
14. 52nd St: Leroy to Sepulveda 140 4,421.00
2,930 $99,835.00
* Wi I I require Header Cut or Ful I Width Cut
"Exhibit 5"
WARD 5
LOCATION TONNAGE PROJECT COST
1. "F" St: 34th St to Dead-end 350 $11,052.00
2. Acacia: Sequoia to 48th St 235 7,440.00
3. "E" St: Sequoia to 48th St 235 7,440.00
4. Electric: Northpark to Bartlett 180 5,681.00
5. Marsha II Blvd: Miramonte to Little Mtn 380 RDA-STC 12,015.00
6. Turri II: 28th St to Col ima 215 6,787.00
7. Oakwood: Miramonte to Turr ill 90 2,866.00
8. 29th St: Miramonte to Turr ill 90 2,866.00
9. Garner: Col ima to Oakwood 95 3,010.00
10. Crescent: 30th St to Marsha I I 220 6,977.00
11. Stoddard: Sequoia to 49th St 170 5,381.00
12. "0" St: Sequoia to 49th St 170 5,381.00
13. Mirada: "I" St to Lincoln 90 2,857.00
14.. Mayfield: 44th St to 48th St 315 9,955.00
15. Electric: 44th St to 48th St 295 9,302.00
3,130 $99,010.00
"Exhibit 6"
WARD 6
LOCATION TONNAGE PROJECT COST
1. Herrington: 13th St to 14th St 130 $ 4,121.00
2. Garner: 17th St to Cui de Sac 40 1,295.00
3. Ramona: Basel ine to 11th St 125 RDA-NW 3,969.00
4. Herrington: Basel ine to 11th St 125 RDA-NW 3,972.00
5. 15th St: "J" St to Massachusetts 260 8,244.00
*6. 10th St: Mt. Vernon to Western 485 18,912.00
7. Concord: Cabrera to Cui de Sac 175 5,574.00
8. Wi I son: Base line to 11 th St 125 RDA-NW 3,972.00
9. Hancock: Basel ine to 11th St 120 RDA-NW 3,814.00
10. 11th St: Medical Center to Madison 190 RDA-NW 5,982.00
11. Colorado: Ca I i forn i a to Evans 550 17,382.00
12. Magno I i a : "~,, St to "J" St 110 3,462.00
13. Hanford: Colorado to State 30 952.00
14. 27th st: Cal ifornia to Gardena 470 14,867.00
15. Pico: 14th St to 15th St 110 3,471.00
3,045 $99,989.00
* Wi I I require Header Cut of Ful I Length Cut
~
"Exhibit 7"
WARD 7
LOCATION
1. Blythe: Byron to Amanda
2. Kenwood: 39th St to Avery
3. 17th St: Arden to Gutherie
4. Dumbarton: 18th St to Cui de Sac
5. 18th St: Dumbarton to Guthrie
6. Newcomb: 17th St to Cui de Sac
7. Mc Kinley: 17th St to Cui de Sac
8. Hudson: 17th St to Cui de Sac
9. 39th St: Valencia to Kenwood
10. Cedar Avenue: Lynwood to Holly Vista
11. Lawrence: Lynwood to Holly Vista
12. Casa Lorna: Lynwood to Holly Vista
13. Harrison: Lynwood to Hot Iy Vista
14. Newport Avenue: Lynwood to Holly Vista
15. Alameda Avenue: Lynwood to Holly Vista
16. Holly Vista: Cedar Avenue to Golden Avenue
17. Broadmoor: Sonora to Ralston
18. 8roadmoor: 39th St to Avery
19. 39th St: Parkside to Broadmoor
20. Avery: Parkside to Broadmoor
21. Ralston: Broadmoor to Parkside
TONNAGE
PROJECT COST
175
75
295
155
235
105
105
105
215
120
120
135
155
140
155
390
85
85
100
100
100
$ 5,579.00
2,359.00
9,347.00
4,883.00
7,485.00
3,317.00
3,317.00
3,317.00
6,782.00
3,816.00
3,816.00
4,262.00
4,-923.00
4 , 421 .00
4,924.00
12,365.00
2,708.00
2,708.00
3,165.00
3,165.00
3,165.00
3,150
$99,824.00
City of San Bernardino
INTEROFFICE MEMORANDUM
9001-1705
TO:
CRAIG GRAVES, CITY TREASURER
FROM:
ANDREW M. GREEN, DIRECTOR OF FINANCE
SUBJECT: FUNDING FOR CITY MATCH- REQUIRED FOR STREET
CONSTRUCTION FUND PROJECTS IN 1989/90 BUDGET
DATE:
JANUARY 18, 1990
COPIES:
-------------------------------------------------------------
As you requested at the January 17 meeting I have determined
the funding source breakdown of the matching funds required
in the 1989/90 Street Construction Fund budget.
It has been determined that $257,600 of matching funds will
be required to complete certain street construction projects
in the 1989/90 budget.
The following is a listing of
Construction Fund projects. I
which require a city match and
all budgeted 1989/90 street
have identified those projects
potential funding sources.
PROJECT
ESTIMATED
PROJECT COST
MATCHING FUNDS
REQUIREMENT
PROPOSED
FUNDING SOURCE
FOR MATCH
1. Fairfax Box
Culvert at Del Rosa
Channel
$ 400,000
2. Lynwood Box
Culvert at Sand Creek
575,500
3. Little League Dr.
Box Culvert
550,000
$110,000
CMO
4. victoria - Highland
to
315,000
5. Signals - Kendal
and University
*150,000
75,000
RDA
(state College)
INTEROFFICE MEMORANDUM: 9001-1705
FUNDING FOR CITY MATCH REQUIRED FOR STREET CONSTRUCTION FUND
PROJECTS IN 1989/90 BUDGET
January 18, 1990
Page 2
PROJECT
ESTIMATED
PROJECT COST
MATCHING FUNDS
REQUIRtMENT
PROPOSED
FUNDING SOURCE
FOR MATCH
6. Signals - Highland/ 90,000 12,600 CMO (Mutual
Valencia - Golden Benefit ?? uptown)
7. Signals - Highland 100,000 50,000 CMO
and Palm
8. South "E" Str Lft 45,000
Turn Lane - Mill & Inland
Center Drive
9. Waterman - Mill To 60,000 10,000 CMO (Mutual
5th street Benefit ?? Central
City)
$2,285,500
$257,600
*1989/90 Budget only reflects city match
Analysis indicates that approximately $75,000 of the total
required match of $257,600 could be funded through RDA Tax
Allocation Bond proceeds due to the direct benefit to RDA
project areas. The remaining match of $182,600 would have to
be funded with Collateralized Mortgage obligation (CMO)
proceeds.
If a mutual benefit findings could be made for projects
numbers 6 and 9, $160,000 would need to be funded by CMO's.
Let me know if you need any further information.
~jj~
Andrew Green
Director Of Finance
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: Marshall W. Julian
Subject: Recommendation of funding sources
for street improvements from
bond proceeds and authorization
to proceed with work
Oept: Administrative
Date: January 22, 1990
Synopsis of Previous Council action:
July 11, 1989 - Mayor and Common Council approve budget for FY 89-90,
which includes designated streets improvements which
are federal-aided projects
December 7, 1989 - Approved the use of bond proceeds and use of tax
increment funds for designated street paving and
street improvement projects included in FY 89-90
budget
./ ,i I . "Ii
Recommended motion: Mayor and Common Council and Community Development Commission
1. Authorize the funding of the streets designated in Exhibits 1 - 8 for
paving with $790,683.00 from RDA Tax Allocation Bonds and
$763,229.00 from the City's share of proceeds from the sale of
the CMO's
2. Authorize the Director of Public Services to take the necessary action
to pave the streets designated in Exhibits 1 - 8 with City Personnel
and Equipment.
3.
Authorize the Director of Public Services to seek bids for the
cold planing of certain designated streets listed within Exhibits 1 - 8
as deemed necessary.
Signature
Contact penon:
Marshall W. Julian
Phone:
5122
Supporting data attached:
Yes
Ward: City-Wide
FUNDING REQUIREMENTS:
Amount: $1.811.512
Source: (ACCT. NO.)
(ACCT. DESCRIPTION)
RDA - $865,683
CMO - $945,829
Finance:
Council Notel:
CITY OF SAN BERN'"ARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
RECOMMENDED MONTION: (cont.)
MAYOR AND COMMON COUNCIL and COMMUNITY DEVELOPMENT COMMISSION
4. Authorize funding for federal-aided projects listed in the approved
FY 89-90 (also listed in attached memorandum from Mr. Green) budget
with $75,000 from RDA Tax Allocation Bond proceeds and $182,600
from the City's CMO proceeds.
5. Authorize staff to take the necessary steps to transfer the
approved funding
Attached (Exhibits 1 - 8) are the list of streets recommended to be
repaved by the Director of Public Services. The first list concerns
major arteries to be done. The next seven lists are those residential
streets to be resurfaced and they are listed by ward.
Staff has researched which streets can be funded with Redevelopment Funds
and which streets the City needs to use the bond proceeds from the
Collateralized Mortgage Obligations (CMO). In addition, we have designated
what Redevelopment Project Area they are within. Funds allocated
from the CMOs for street resurfacing total $763,229. The total funds
needed from Redevelopment Funds are $790,683.
In addition to the resurfacing funding, the Mayor and Common Council
approved on December 7, 1989, the use of bond proceeds for federal-aided
projects which requiring City matching funds. This amount totals $257,600
with $75,000 coming frOM RDA Bond proceeds and the remaining $182,600
coming from the CMO proceeds.
The Mayor and Common Council and the Community Development COMmission need
to authorize these funding allocation and authorize the Director of
Public Services to proceed with the street resurfacing program attached.
CITY OF SAN BERNARDINO
-
MEMORANDUM
To
W. R. Holcomb, Mayor
From Manue I P. Moreno, Jr.
Director of Publ ic ServicE
Date January 12, 1990
Subject
Resurfac i ng
Approved
Date
Attached please find a I ist of Residential
schedu I ed for resurf ac i ng in March 1990.
require resurfacing and Cold Planing.
and Major Arteries that are
Some of these streets wi I I
Please cal I me if yo~ have any questions on this matter.
.'f1!1 a.l4V~{,P aY\ ~ I
Manuel P. Moreno, Jr.
Director of Publ ic Services
cc: Marshal I Jul ian, City Administrator
James Robbins, Deputy City Administrator
Phi I Arviso, Executive Assistant to Counci I
AI I Counci I Members
Craig Graves, Treasurer
Andrew Green, Director of Fi~ance
Roger Hardgrave, Director of Publ ic Works
Larry Reed, Director of Planning and Sui Iding and Safety
Anwar Wagdy, Traffic Engineer
Traffic Signal Department
MPM:dlw
.- --. .... ~,-
(' ~. '-..;::- -
~,. ;:qr;-.;:.. ~ "
,I". .1_ .::~ __' _
.. --,
~~;r'
MAJOR ARTERIES - ALL WARDS
LOCATION TONNAGE PROJECT COST
1. Northpark Blvd: Electric to "H" St 1,690 $ 53,053.00
2. Perr isH i I I Rd: Pacific north to Flood Cntrl 660 20,824.00
3. "H" St: 6th St to 9th St 650 RDA-UPT 20,523.00
4. Arden: Highland to Pacific 775 24,407.00
5. 5th St: Ster ling east to City Limits 480 15,180.00
6. 6th St: Ster ling east to City Limits 360 .11,363.00
7. Harrison: 35th St to 40th St 730 23,039.00
8. Court St: "0" St to "E" St 170 RDA-CC 5,374.00
9. 3rd St: "I" St to 2nd St 1,135 RDA-UPT 35,860.00
10. 5th St: Victoria west to City Limits 435 13,763.00
11. Mt Vernon: 21st St to Cajon 300 RDA-NW 9,466.00
12. Pacific: Central to Orange 420 13,264.00
13. Pacific: Arden to Flood Control 750 23,637.00
14. Pepper: Spruce to 6th St 250 7,898.00
'15. Arrowhead: Mill to 3rd St 2,385 RDA-CC 90,174.00
-
'16. University Blvd: 215 Fwy to Co I lege 2,125 RDA-STC 73,165.00
'17. Mi II St: "E" St to Waterman 2,650 RDA-CC 97,521.00
'18. G i I bert: Waterman to 207' e/o Cedar 1,280 49,315.00
'19. "0" St: Rialto to 2nd St 315 RDA-CC 12,042.00
'20. Rialto: "I" St to Mt Vernon 1,235 RDA-UPT 45,715.00
, 21. Rialto: Arrowhead to "E" St 410 RDA-CC 13,981.00
'22. 40th St: Waterman to Sierra Wy 710 23,934.00
~23 . 4th St: Waterman to Sierra Wy 575 RDA-CC 19,657.00
'24. "E" St: Mi II to Orange Show Rd 2,120 RDA-CC 69,660.00
'25. "I" St: Rialto to 3rd St 385 RDA-UPT 12,645.00
'~6. Orange Show Rd: 590 RDA-CC 19,732.00
.::'7. Redlands Blvd: Hunts Ln to Waterman 1,200 RDA-SV 39,989.00
.28. 6th St: "H" St to "G" St 300 RDA-CCN 11,300.00
25,085 $856,481.00
"Exhibit 1"
. Wi II require Header Cut or Ful I Width Cut
WARD 1
LOCATION TONNAGE PROJECT COST
1. Redick: Arrowhead to Pershing 65 RDA-CC $ 2,062.00
2. Pershing: Cluster to Hi I da 220 RDA-CC 6,987.00
3. Garner: 7th St to Vine 40 1,258.00
4. Perris: 6th St to 9th St 390 12,353.00
*5. Vine: Mt. Vernon to Davidson 270 11,037.00
6. Doo I i tt Ie: Mi II to Dead-end 310 9,753.00
7. Mt. View: Rialto to 2nd St 240 RDA-CC 7,583.00
8. 7th St: Arrowhead to "E" St 410 RDA-CCN 13,000.00
9. 8th St: Arrowhead to "E" St 410 RDA-CCN 13,000.00
10. 7th St: Waterman to Sierra Way 560 RDA-CC 17,703.00
* 11. Crescent: 7th St to 6th St 120 RDA-CCN 4,980.00
3,035 $99,716.00
* Wi I I require Header Cut or Ful I Width Cut
--
"Exhibit 2"
WARD 2
I..OCATION TONNAGE PROJECT COST
*1. 10th St: "0" St to "G" St 760 RDA-UPT $26,465.00
2. 16th St: Waterman to Dead-end 385 12,165.00
3. 17th St: Waterman to Cu I de Sac 250 7,938.00
4. 13th St: "0" St to Arrowhead 145 RDA-UPT 4,576.00
5. 16th St: "E" St to Arrowhead 365 RDA-UPT 11,609.00
6. 01 ive: Waterman to Mt View 510 16,181.00
7. 16th St: "H" St to "G" St 145 4,583.00
*8. 13th St: Sierra Way to Mt View 150 5,882.00
*9. Berkley: Base line to 13th St 155 6,071.00
10. Stoddard: 16th St to 15th St 125 RDA-UPT 3,902.00
2,990 $99,372.00
* Wi II require Header Cut or Fu II Width Cut
"Exhibit 3"
WARD 3
LOCATION TONNAGE PROJECT COST
1. Lugo: Central to Dead-end 280 $ 8,840.00
2. Eureka: Mi II to Esperanza 130 4,123.00
3. Etiwanda: Meridian to Pepper 295 9,302.00
*4. Blood Bank Rd: "E" St to Entrance 230 9,132.00
5. Steele Rd: Wier Rd to Industrial Rd 210 RDA-SV 6,631.00
6. Commercial Rd: Waterman to Steele Rd 305 RDA-SV 9,650.00
7. Adell: Inland Center to flH" St 145 RDA-CC 4,576.00
8. College: Crescent to "Hll St 120 RDA-CC 3,813.00
9. Huff: "H" St to fiG" St 235 RDA-CC 7,435.00
10. Crescent: Mi II to Co I lege 245 RDA-CC 7,728.00
11. Sierra Wy: Central to Dead-end 510 RDA-CC 16,087.00
12. Benedict: Arrowhead to Sierra Wy 195 RDA-CC 6,184.00
13. Hi Ilcrest: Arrowhead to Sierra Wy 195 RDA-CC 6,184.00
3,095 $99,685.00
* Wi II require Header Cut or Ful I Width Cut
"Exhibit 4"
WARD 4
LOCATION TONNAGE PROJECT COST
*1. Mt View: Electric to 40th St 455 $17,676.00
2. Dumbarton: Marsha I I to Cui de Sac 100 3,161.00
3. Eureka: Mountain to Conejo 165 5,229.00
4. C I i fton : Central to Orange 250 7,981.00
5. V i I I a Court: C I i fton to Cu I de Sac 105 3,315.00
6. Pepper Court: C I i fton to Cu I de Sac 105 3,315.00
7. 01 ive Tree Court: C I i fton to Cu I de Sac 105 3,315.00
8. Li II ian Court: CI i fton to Cu I de Sac 105 3,315.00
9. Orange: Central to Fisher 170 5,381.00
*10. Sepulveda: 40th St to Sierra Way 605 22,973.00
11, Pershing: 48th St to 50th St 180 5,679.00
12. Sierra Road: 49th St to 54th St 300 9,497.00
13. 50th St: Leroy to Sep1J.lveda 145 4,].77 .00
14. 52nd St: Leroy to Sepulveda 140 4,421.00
2,930 $99,835.00
*
Wi I I require Header Cut or Ful I Width Cut
"Exhibit 5"
WARD 5
LOCATION TONNAGE PROJECT COST
1. "F" St: 34th St to Dead-end 350 $11,052.00
2. Acacia: Sequoia to 48th St 235 7,440.00
3. "E" St: Sequoia to 48th St 235 7,440.00
4. Electric: Northpark to Bartlett 180 5,681.00
5. Marsha I I Blvd: Miramonte to Little Mtn 380 RDA-STC 12,015.00
6. Turri II: 28th St to Co lima 215 6,787.00
7. Oakwood: Miramonte to Turr ill 90 2,866.00
8. 29th St: Miramonte to Turr ill 90 2,866.00
9. Garner: Col ima to Oakwood 95 3,010.00
10. Crescent: 30th St to Marsha I I 220 6,977.00
11. Stoddard: Sequoia to 49th St 170 5,381.00
12. "0" St: Sequoia to 49th St 170 5 , 381 .00
13. Mirada: "I" St to Lincoln 90 2,857.00
14... Mayfield: 44th St to 48th St 315 9,95~.OO
15. Electric: 44th St to 48th St 295 9,302.00
3,130 $99,010.00
"Exhibit 6"
WARD 6
LOCATION TONNAGE PROJECT COST
1. Herrington: 13th St to 14th St 130 $ 4,121.00
2. Garner: 17th St to Cui de Sac 40 1,295.00
3. Ramona: Base line to 11th St 125 RDA-NW 3,969.00
4. Herrington: Base line to 11th St 125 RDA-NW 3,972.00
5. 15th St: "J" St to Massachusetts 260 8,244.00
*6. 10th St: Mt. Vernon to Western 485 18,912.00
7. Concord: Cabrera to Cu I de Sac 175 5,574.00
8. Wi I son: Base line to 11th St 125 RDA-NW 3,972.00
9. Hancock: Base line to 11th St 120 RDA-NW 3,814.00
10. 11th St: Medical Center to Madison 190 RDA-NW 5,982.00
11. Colorado: Ca I i forn i a to Evans 550 17,382.00
12. Magnol ia: "~,, St to "J" St 110 3,462.00
13. Hanford: Colorado to State 30 952.00
14. 27th St: Cal ifornia to Gardena 470 14,867.00
15. Pico: 14th St to 15th St 110 3,471.00
3,045 $99,989.00
*
Wi I I require Header Cut of Ful I Length Cut
<:....-
"Exhibit 7"
WARD 7
LOCATION
1. Blythe: Byron to Amanda
2. Kenwood: 39th St to Avery
3. 17th St: Arden to GUiherie
4. Dumbarton: 18th St to Cui de Sac
5. 18th St: Dumbarton to Guthrie
6. Newcomb: 17th St to Cui de Sac
7. Mc Kinley: 17th St to Cui de Sac
8. Hudson: 17th St to Cui de Sac
9. 39th St: Valencia to Kenwood
10. Cedar Avenue: Lynwood to Holly Vista
11. Lawrence: Lynwood to Holly Vista
12. Casa Lorna: Lynwood to Holly Vista
13. Harrison: Lynwood to Holly Vista
14. Newport Avenue: Lynwood to Holly Vista
15. Alameda Avenue: Lynwood to Holly Vista
16. Holly Vista: Cedar Avenue to Golden Avenue
17. Broadmoor: Sonora to Ralston
18. Broadmoor: 39th St to Avery
19. 39th St: Parkside to Broadmoor
20. Avery: Parks ide to Broadmoor
21. Ralston: Broadmoor to Parkside
TONNAGE
PROJECT COST
175
75
295
155
235
105
105
105
215
120
120
135
155
140
155
390
85
85
100
100
100
$ 5,579.00
2,359.00
9,347.00
4,883.00
7,485.00
3,317.00
3,317.00
3 , 317 .00
6,782.00
3,816.00
3,816.00
4,262.00
4,-923.00
4,421.00
4,924.00
12,365.00
2,708.00
2,708.00
3,165.00
3,165.00
3,165.00
3,150
$99,824.00
city of San Bernardino
INTEROFFICE MEMORANDUM
9001-1705
TO:
CRAIG GRAVES, CITY TREASURER
FROM:
ANDREW M. GREEN, DIRECTOR OF FINANCE
SUBJECT: FUNDING FOR CITY MATCH REQUIRED FOR STREET
CONSTRUCTION FUND PROJECTS IN 1989/90 BUDGET
DATE:
JANUARY 18, 1990
COPIES:
-------------------------------------------------------------
As you requested at the January 17 meeting I have determined
the funding source breakdown of the matching funds required
in the 1989/90 Street Construction Fund budget.
It has been determined that $257,600 of matching funds will
be required to complete certain street construction projects
in the 1989/90 budget.
The following is a listing of
Construction Fund projects. I
which require a city match and
all budgeted 1989/90 Street
have identified those projects
potential funding sources.
PROJECT
ESTIMATED
PROJECT COST
MATCHING FUNDS
REQUIREMENT
PROPOSED
FUNDING SOURCE
FOR MATCH
1. Fairfax Box $
Culvert at Del Rosa
Channel
2. Lynwood Box
Culvert at Sand Creek
400,000
575,500
3. Little League Dr.
Box Culvert
550,000
$110,000
CMO
4. victoria - Highland
to
315,000
5. Signals - Kendal
and University
*150,000
75,000
RDA
(State College)
--~ ......,.
INTEROFFICE MEMORANDUM: 9001-1705
FUNDING FOR CITY MATCH REQUIRED FOR STREET CONSTRUCTION FUND
PROJECTS IN 1989/90 BUDGET
January 18, 1990
Page 2
PROJECT
ESTIMATED
PROJECT COST
MATCHING FUNDS
REQUIREMENT
PROPOSED
FUNDING SOURCE
FOR MATCH
6. Signals - Highland/ 90,000 12,600 CMO (Mutual
Valencia - Golden Benefit ?? uptown)
7. Signals - Highland 100,000 50,000 CMO
and Palm
8. South "E" Str Lft 45,000
Turn Lane - Mill & Inland
Center Drive
9. Waterman - Mill To 60,000 10,000 CMO (Mutual
5th Street Benefit ?? Central
City)
$2,285,500
$257,600
*1989/90 Budget only reflects city match
Analysis indicates that approximately $75,000 of the total
required match of $257,600 could be funded through RDA Tax
Allocation Bond proceeds due to the direct benefit to RDA
project areas. The remaining match of $182,600 would have to
be funded with Collateralized Mortgage Obligation (CMO)
proceeds.
If a mutual benefit findings could be made for projects
numbers 6 and 9, $160,000 would need to be funded by CMO's.
Let me know if you need any further information.
~n~
Andrew Green
Director Of Finance