Authorization for the Director of Development
Services to execute Contract Change Order
No. One to the Contract with Olivas Valdez,
Inc., for Street Widening Improvements on
Palm Avenue at BNSF Railroad Grade
Crossing North of Cajon Boulevard (SS 04-
04) per Plan No. 11354.
May 1, 2006
Synopsis of Previous Council Action:
The Mayor and Common Council approved FY 2005-06 CIP Budget.
The Mayor and Common Council authorized the Director of Finance to amend the FY 05/06 Budget
by transferring $157,100.00 from Account No. 129-367-5504-7245 [State Street Construction - Phase
IB & 3 (SS04-09)] to Account No. 129-367-5504-7231, for Street Widening Improvements on Palm
Avenue at BNSF Railroad Grade Crossing north of Cajon Boulevard (S04-04), per Plan No. 11354;
and adopted the Resolution for the Contract with Olivas Valdez, Inc.
Aug 2005
Nov 5, 2005
Recommended Motion:
Authorize the Director of Development Services to execute Change Order No. One in the amount of
$20,668.00 to contract with Olivas Valdez, Inc. for Street Widening Improvements on Palm Avenue at
BNSF Railroad Grade Crossing north of Cajon Boulevard (SS 04-04) per Plan No. 11352.
J es Funk, Development Services Director
5179
Contact Person:
Michael Grubbs, Engineering Manager/Field Engineer Phone:
Ward:
6
Supporting data attached:
Staff Report & CCO No. One
FUNDING REQUIREMENTS:
Amount: $20.668.00
Source: (Ace!. No) 129-367-5504-7231
Acct.
Description: Yz-Cent Sales Tax Fund
Finance:
Council Notes:
5j1/1Jh-
Agenda Item No. /5
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
Staff Report
Subiect:
Authorization for the Director of Development Services to execute Contract Change Order No. One to the
Contract with Olivas Valdez, Inc., for Street Widening Improvements on Palm Avenue at BNSF Railroad Grade
Crossing North of Cajon Boulevard (SS 04-04) per Plan No. 11354.
Backeround:
In 2002, the City entered into Agreement No. 53-R946 with BNSF and the State Department of Transportation
(Caltrans) to widen Palm Avenue in the vicinity of the BNFS tracks to compliment the relocation of the crossing
gates and the installation of a third Transcontinental track. The original agreement called for the project to be
completed by December 31, 2003 or funding for the project would be revoked. The deadline was extended once
by Caltrans to December 31, 2004. The deadline was further extended to December 31, 2005, only due to the
City Engineer's commitment to have the project complete by December 31, 2005. The work was substantial1y
completed in January 2006, and Caltrans recently agreed to an additional extension of time necessary to
complete the work and bill the project.
Funding for this project was allocated as part of the FY 2005/06 Capital Improvement Program (CIP) for Street
Widening Improvements on Palm Avenue at BNSF Railroad Grade Crossing North of Cajon Boulevard (SS 04-
04) per Plan No. 11354.
A contract for the work was awarded to Olivas Valdez, Inc. in the amount of $248,265.00 for Street Widening
Improvements on Palm Avenue at BNSF Railroad Grade Crossing north of Cajon Boulevard (SS 04-04) per
Plan No. I135i
Contract Change Order No. One, in the amount ofS20,668.00, consists of the fol1owing changes:
\.
Installation of K-rails in order to conform to the requirement of BNSF traffic control to create a
positive barrier between the work and traffic while construction of road and crossing gates was
proceeding. During construction BNSF required K-rails to be placed across Palm Avenue to
create a positive barrier for vehicle traffic. This was a safety provision during the construction
phase when the railroad crossing gates were removed.
Placement of additional crushed aggregate base which was not specified in the original contract.
This additional crushed aggregate base was necessary to create a safe transition from the
existing pavement to the widened lanes.
'J
Financial Impact:
The estimated project costs are as fol1ows:
I TOTAL
, Orillinal Contract 1 S248.265.00
Contract Change Order No. One S 20,688.00
Revised Construction Cost $268,933.00
Adequate funding for these projects is available in the FY 2005/2006 CIP, SS04-04. "Palm Avenue BNSF
Grade Crossing" Account No. 129-367-5504-723 \.
Recommendation:
Authorize the Director of Development Services to execute Contract Change Order No. One to the Contract
with Olivas Valdez, Inc., for Street Widening Improvements on Palm Avenue at BNSF Railroad Grade Crossing
);orth of Cajon Boulevard (SS 04-04) per Plan No. 11354.
2
04/17/20062: 14 PM
DEVELOPMENT SERVICES DEPARTMENT
SM
300 North "0" Street. San Bernardino' CA 92418-0001
Planning & Building 909.384.5057 . Fax: 909.384.5080
Public WorkslEngineering 909.384.5111 . Fax: 909.384.5155
www.sbcity.org
CONTRACT CHANGE ORDER NO. ONE
FILE NOS. 1.7231
W.O. NO. 7231
DATE: MAY 1,2006
PROJECT: STREET WIDENING IMPROVEMENTS ON PALM AVENUE AT BNSF
RR CROSSING PER PLAN NO. 11354
TO: OLIVAS VALDEZ, INC.
840 N. CHARTER DRIVE
COVINA, CA 91724
GENTLEMEN:
You are hereby compensated for performing the additional work as follows:
ITEM NO: DESCRIPTION OF CHANGE COST
I 1-1 $ 10,539.00
Install K-Rail
1-2 Additional Crushed Aggregate Base $ 10,129.00
I TOTAL COST CCO #1 $ 20,668.00
JUSTIFICATION:
Install K-Rail
Item 1-1 During construction BNSF requires K-Rails to be placed across Palm Avenue to create a
No. positive barrier for vehicle traffic. This was a safety provision during the construction
ohase when the railroad crossing gates were removed.
I I Additional Crushed Ae:e:ree:ate Base
i Item I
i 1-2 I It was necessary to put additional crushed aggregate base to create a safe transition from
I No. the existing pavement to the widened lanes.
Sl'MMARY OF CONTRACT COSTS
The estimated revised contract cost is as follows:
Original Bid Amount. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$
Contract Change Order No. One. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $
Revised ConstructiolJ. Contract cost. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$
248,265.00
20,668.00
268,933.00
Change Order No. One to Contract for Street Widening Improvements on Palm A venue at BNSF RR
Crossing per Plan No. 11354.
Additional time to complete Contract due to this Change Order. . . . . . . . . . . . ~ Working
Days
This change order represents 8.33% of the original contract amount.
OLIV AS VALDEZ, INC.
CONTRACTOR
Accepted
By:
Title:
Date:
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES
Approved
By:
JAMES FUNK
Director of Development Services
Date:
Approved by Mayor and Common Council
Date: May 1.2006
Item No.
")