HomeMy WebLinkAbout23-Development Services
., ORIGINAL
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
From: James Funk, Director
Subject:
Resolution awarding a contract to Bonadiman-
McCain, Inc. for Street Improvements per
Revision No. One of Drawing No. 11393 at
Chestnut Avenue from Station 14+21.53 to
Irvington Avenue, per Plan No. 11393 and
authorization for the Director of Finance to amend
the FY 05/06 Budget.
Dept: Development Services
Date: February 2, 2006
File Nos. 1.7156 - 05/06 Chestnut
MCC Date: February 21, 2006
Synopsis of Previous Council Action:
August 2005
The Mayor and Common Council approved FY 2005-06 CIP Budget.
Recommended Motion:
I. Authorize the Director of Finance to amend the FY 05/06 Budget by transferring $78,000 from Account No.
129-367-5504-7384 (SS04-67) "Bridge Repair Railing at Baseline Street and Warm Creek" to Account No.
129-367-5504-7669 "Chestnut Ave. between Washington Ave. and Irvington Ave."
2. Adopt Resolution.
-r~
Contact Person:
Mike Grubbs, Engineering ManagerlField Engineer
Phone:
5179
Supporting data attached:
Staff Report, Resolution, Vicinity Map
Ward:
5
FUNDING REQillREMENTS:
Amount: $ 78.000.00
Source: (Acct. No) 129-367-5504-7669
Acct. Description:
Y2-Cent Sales Tax
Finance:
Council Notes:
~otJb - Lfq
Agenda Item No.JJ
dJ JJ IIJID
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
Staff Report
Subject:
Resolution awarding a contract to Bonadiman-McCain, Inc. for Street Improvements per Revision No. One of
Drawing No. 11393 at Chestnut Avenue from Station 14+21.53 to Irvington Avenue, per Plan No. 11393 and
authorization for the Director of Finance to amend the FY 05/06 Budget.
Background:
On August 15, 2005, the Mayor and Common Council allocated funds, as part of the FY 2005/06 Capital
Improvement Program (CIP), for Street Safety Improvements at Various Locations (Annual), 2005/06, (SS-C).
The project consists of construction of curb-gutter, sidewalk, catch basin, CMP storm drain, and pavement
repair. The purpose of this project is to complete Chestnut Avenue between Washington Street and Irvington
Avenue. After completion of the curb, gutter and sidewalk at this location, GFR Homes has agreed to complete
the paving on this reach of Chestnut Avenue to provide an enhanced entrance to the area.
The plans and specifications for this project have been completed and the project was opened to public bidding
on January 10, 2006. The project was advertised locally in the San Bernardino County Sun Newspaper, F. W.
Dodge, High Desert Plan Room, Construction Bid Board, Reed Construction Data, Bid America, Construction
Bid Source, Bid Ocean and the City's web sites, and with the San Bernardino Area Chamber of Commerce.
Bids have been received and are listed below:
Name of Bidder City Amount of Basic Bid
BONADIMAN-McCAIN, INC. SAN BERNARDINO $ 59,514.00
Sim Engineering, Inc. Fallbrook $ 64,365.00
Hardv & Harper, Inc. Santa Ana $ 99,328.00
Fischer, Inc. San Bernardino $ 143,187.00
En2ineer's Estimate $ 50,742.00
Based on review of the sealed competitive bids received, staff has determined that Bonadiman-McCain, Inc. of
San Bernardino, CA, the apparent low bidder, has met the minimum requirements of the specifications and bid
guidelines; and, therefore, recommends that the Mayor and Common Council award the referenced contract to
Bonadiman-McCain, Inc.
The estimated project costs are as follows:
rox.15%)
TOTAL
$ 59,514.00
$ 8,927.10
$ 9,558.90
$ 78,000.00
If approved, this project is expected to begin construction in March of 2006 and be completed by May of 2006.
2
02/06/2006 11:04 AM
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
Staff Report (Continued)
Financial Impact:
Staff has identified Project SS04-67 "Bridge Repair Railing at Baseline Street and Warm Creek", Account No.
129-367-5504-7384, as a source of funds for this project. This project is under design but has been delayed due
to processing requirements for federal Highway Bridge Replacement and Rehabilitation (HBRR) funding.
Funding for SS04-67 will be restored in the FY 06/07 budget year.
Recommendation:
I. Authorize the Director of Finance to amend the FY 05/06 Budget by transferring $78,000 from Account No.
129-367-5504-7384 (SS04-67) "Bridge Repair Railing at Baseline Street and Warm Creek" to Account No.
129-367-5504-7669 "Chestnut Ave. between Washington Ave. and Irvington Ave."
2. Adopt Resolution.
3
02/06/2006 11 :04 AM
City of San Bernardino, California
Department of Public Works', Division of Engineering
Revision No. ONE of Drawing No. 11393
STREET IMPROVEMENTS
ON
CHESTNUT A VENUE
AT
STA.14+21.53 TOIRVINGTONAVE
/
q,-,
/ ~/
I ,-.,i:::...,.
"~$..."
o~
~
/
'\'~:.v
. ~;;~ ~...,
.:.'f' o~\~~_,
\.+ . ~ ',;-:
.'~i'>.""~'~,;:
:~..l
\
\
\
\
\
\
(! ~~ ~
"<!/",<'
\ MLH~ ~ <.oJ
~ ."----.-~- .....
'1,''-..'l:> $
~ -....<.....
<* ';""-
~
,,)-~ :s
~T1CML
p ~
'RR1N
"
~
,,/
~i.~
,~
..:r.."
g,l"
'-..~ w l'''''-,~/o
"', -~(':~Rs
.::..:'
"':
,:
~:
{:
RO ""wr
"
. "
/)
\
~
.
.~
---"-""",
VICINITY MAP
N.T.S.
ss-c 05/06
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLLTlON NO.
RESOLUTION OF THE lVlAYOR AND COMMON COUNCIL OF THE CITY OF SAN
BERNARDINO A WARDING A CONTRACT TO BONADIMAN-McCAIN, INC. FOR
STREET IMPROVEMENTS PER REVISION NO. ONE OF DRAWING NO. 11393 AT
CHESTNUT AVENUE FROM STATION 14+21.53 TO IRVINGTON AVENUE (SS-C
05/06), PER PLAN NO. 11393.
BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE
CITY OF SAN BERNARDINO AS FOLLOWS:
SECTION I. Bonadiman-McCain, Inc., 280 South Lena Road, San Bernardino, CA
92408, is the lowest responsible bidder for Street Improvements per Revision No. One of Drawing
NO.1 Ll93 at Chestnut Avenue fi'om Station 14+21.53 to lrvington Avenue (SS-C 05/06), per Plan No.
I LllJ3.
A contract is awarded accordingly to said bidder in a total amount of $ 59,5 14.00, with a
contingency amount of $ 9,558.90, but such award shall be effective only upon being fully
executed by both parties. All other bids, therefore, are hereby rejected. The Mayor is hereby
authorized and directed to execute said contract on behalf of the City; a copy of the contract is
on Ii Ie in the officc of the City Clerk and incorporated herein by reference as fully as though set
forth at length.
SECTION 2. This contract and any amendment or modifications thereto shall not take
effect or become operative until fully signed and executed by the parties and no party shall be
obligated hereunder until the time of such full execution. No oral agreements, amendments,
l11odliications or waivers are intended or authonzed and shall not be implied from any act or
course of conduct of any party.
SECTION 3. This resolution is rescinded if the parties to the contract fail to execute it
within sixty (60) days of passage of the resolution.
AID. J-3
~ I ~II Dro
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
BERNARDINO AWARDING A CONTRACT TO BONADIMAN-McCAIN, INC. FOR
STREET IMPROVEMENTS PER REVISION NO. ONE OF DRAWING NO. 11393 AT
CHESTNUT AVENUE FROM STATION 14+21.53 TO IRVINGTON AVENUE (SS-C
05/06), PER PLAN NO.1 1393.
I HEREBY CERTIFY that the foregoing Resolution was duly adopted by the Mayor and
Common Council of the City of San Bemardino at a
meeting thereof, held on the
day of
, 2006, by the following vote, to wit:
ABST AIN
ABSENT
Council Members:
AYES
NAYS
ESTRADA
LONGVILLE
MC GINNIS
DERRY
KELLEY
JOHNSON
MC CAMMACK
City Clerk
day of
,2006.
The foregoing resolution is hereby approved this
Judith Valles, Mayor
City of San Bernardino
Approved as to
form and legal content:
.' . . /
; ,
,. I
/.' j t.
James F. Penman,
City Attorney
** FOR OFFICE USE ONLY - NOT A PUBLIC DOCUMENT **
RESOLUTION AGENDA ITEM TRACKING FORM
M~"'g ""0 ''''''' Ad:"", ;( '){ lOb "om # ~ ~
Vote: Ayes --!tZ Nays Abstain
Change to motion to amend original documents D
Companion Resolutions
NulVVoid After: days /
Resolution # On Attachments: D
Note on Resolution of attachment stored separately: D
By:
PUBLISH D POST D RECORD W/COUNTY D
Date Sent to Mayor: U -" /)?; 0 b
Date of Mayor's Signature: ~).~, 010
Date of Clerk/CDC Signature: 'I'd> 1 ,CIv
Date Memo/Letter Sent for Signature:
1" Reminder Letter Sent:
Date Returned:
2'd Reminder Letter Sent:
Request for Council Action & Staff Report Attached:
Updated Prior Resolutions (Other Than Below):
Updated CITY Personnel Folders (6413, 6429, 6433, 10584, 10585, 12634):
Updated CDC Personnel Folders (5557):
Updated Traffic Folders (3985, 8234, 655, 92-389):
Copies Distributed to:
Animal Control D EDA
City Administrator ~/ Facilities
City Attorney Finance
Code Compliance D Fire Department
Development Services ~2~ Human Resources
Others:
~
D
D
a[){)~ - Lf9
Absent)} 1
Resolution #
Reso. Log Updated: ~
Seal Impressed: U
Reso. # on Staff Report d
Not Returned: D
Yes
Yes
/~
NO~y_
No ~y
No_ By_
NO~'
No By_
Yes
Yes
Yes
Information Services D
Parks & Recreation D
Police Department D
Public Services D
Water Department D
Ready to File:
Revised 12/18/03
CITY OF SAN BERNARDINO
Interoffice Memorandum
CITY CLERK'S OFFICE
Records and Information Management (RIM) Program
DATE:
February 28, 2006
TO:
Leslie Crawford, Engineering Assistant I
FROM:
Eileen Gomez, Senior Secretary
RE:
Transmitting Documents for Signature - Resolution 2006-49
At the Mayor and Common Council meeting of February 21, 2006, the City of San Bernardino
adopted Resolution No. 2006-49 - Resolution awarding a contract to Bonadiman-McCain, Inc.
for street improvements per Revision No. One of Drawing No. 11393 at Chestnut Avenue from
Station 14+21.53 to Irvington Avenue (SS-C 05/06), per Plan No. 11393.
Attached is a certified copy of the resolution, one (I) original bound contract and three (3)
duplicate original bound contracts. Please obtain signatures in the appropriate locations and
return the ORIGINAL bound contract to the City Clerk's Office as soon as possible, to my
attention. Please distribute the remaining bound contracts accordingly.
Please be advised that the resolution and contract will be null and void if not executed
within sixty (60) days, or by Thursday, April 20, 2006.
If you have any questions or need further assistance, please do not hesitate to contact me at ex!.
3206.
Thanks and have a great day!
Eileen Gomez
Senior Secretary
Signed:
Date:
'.
DEPARTMENT OF DEVELOPMENT SERVICES
DIVISION OF PUBLIC WORKS
DOCUMENT TRANSMITTAL SHEET
....,
<= ;0
=
"'" fT1
"'" 0
-0 fT1
:;;0 ::2
fT1
c>
t
0
-0 :::i
~ -<
i5? ("')
.-
CJl ~
~.
~>~
FROM: J. LESUE CRAWFORD, Division of Public Works
TO: QTYaERK'S OFFICE
DA TE : APRIL 11, 2006
FILE NQ: 1.7156-05/06-OiESTNUT
SUBJECT: "ORIGINAL" EXHIBIT "It:' CDNIRACTDOCUMENT - PLAN NO. 11393
CONTRA CT TITLE:
STREET IMPROVEMENTS
PER REVISION NO. ONE OF DRAWING NO. 11393
AT
CHESTNUT AVENUE
FROM STA. 14+21.53 TO IRVINGTON AVENUE
(SS-G 05/06)
RESOLUTION /ORDINANCE TITLE:
RESOLUTION NO. 2006-49
ITEM NO. 23
MCC MEETING DATE: 02/21/06
SUBMITTED TOGTYQERK:
J (I
lb~)l~PV\