CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTQ81 G J N A l
From:
James Funk, Director
Subject:
Authorization for the Director of Development
Services to execute Contract Change Order No.
Three to contract with David T. Wasden, Inc.
for 9th Street Storm Drain Improvements from
Waterman Avenue to East Twin Creek
Channel per Plan No. 10676 and authorization
for the Director of Finance to amend the FY
2005/06 Budget.
Dept:
Development Services
Date:
August 2, 2005
File No.
4.7429
MCC Date:
August 15,2005
Synopsis of Previous Council Action:
09/15/03 Allocated $375,000 for 9th Street Storm Drain, Waterman Avenue to Warm Creek (SD04-12) in
the FY 2003/04 Capital Improvement Program (CIP) budget.
11/03/03 Adopted resolution awarding contract to David T. Wasden, Inc. for 9th Street Storm Drain
Improvements from Waterman Avenue to East Twin Creek Channel per Plan No. 10676.
09/07/04 Carried over 9th Street Storm Drain, Waterman Avenue to Warm Creek (SD04-12) in the FY
2004/05 Capital Improvement Program (CIP) budget.
10/04/04 Authorized the Director of Development Services to execute Contract Change Order No. One to
the contract with David T. Wasden Construction in the amount of$10,894.66.
11/15/04 Authorized the Director of Development Services to execute Contract Change Order No. Two to
contract with David T. Wasden, Inc. for 9th Street Storm Drain Improvements from Waterman
Avenue to East Twin Creek Channel per Plan No. 10676 and to accept from San Bernardino
Valley Municipal Water District reimbursement to the City for $82,974.00; and authorize the
Director of Finance to amend the Fiscal Year 2004/2005 budget to increase the project
expenditures in Account No. 248-368-5504-7429 by $82,974.00 and a corresponding increase to
revenues in the amount of $82,974.00 in Account No. 248-000-4651-0000
Recommended Motions:
I. Authorize the Director of Finance to amend the Fiscal Year 2005/2006 budget by transferring $40,000
from Account No. 248-368-5504-7316 "SD04-08 State Street Storm Drain" to Account No. 248-368-
5504-7429 "9th Street Storm Drain from Waterman Avenue to East Twin Creek (SD04-12)".
2. Authorize the Director of Development Services to execute Contract Change Order No. Three to contract
with David T. Wasden, Inc. for 9th Street Storm Drain Improvements from Waterman Avenue to East
Twin Creek Channel, per Plan No. 10676 for $12,806.01.. ~ ~ ~
~esFunk
Contact
Person:
Phone:
Mike Grubbs, Engineering Mgr./Field Engineer
5179
Supporting data attached: Staff Report & CCO #3 Ward:
FUNDING REQUIREMENTS: Amount: $40,000
Source: (Acct. Nos.):
248-368-5504-7429
9th Street Storm Drain Improvements from
Acct. Description: Waterman Avenue to East Twin Cr k
Channel
Agenda Item No.
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subiect:
Authorization for the Director of Development Services to execute Contract Change Order No. Three
to contract with David T. Wasden, Inc. for 9th Street Storm Drain Improvements from Waterman
Avenue to East Twin Creek Channel, per Plan No. 10676 and authorization for the Director of Finance
to amend the FY 2005/06 Budget.
Backe:round:
On November 3, 2003, the Mayor and Common Council awarded a contract in the amount of $273,040
to David T. Wasden, Inc. for 9th Street Storm Drain Improvements from Waterman Avenue to East
Twin Creek Channel.
Change Order No.1 was approved on October 4, 2004, in the amount of $10,894.66. This work
consisted of potholing along the alignment of the storm drain to determine locations of the existing
utilities. The change order also included removal of extra thick asphalt pavement which varied in
thickness varied from 7" to 12" thick, and additional traffic control that was necessary for crews
performing video inspection and cleaning of the sewer lines.
Change Order No.2 was approved on November 5, 2004, in the amount of $165,948. This large
change order primarily resulted from conflicts with Bubalo Construction, a contractor installing a large
water line in 9th Street for the San Bernardino Valley Municipal Water District. San Bernardino Valley
Municipal Water District acknowledged that its contractor's work had delayed the work of our
contractor and agreed to contribute $82,974 of the cost of Change Order No.2. San Bernardino Valley
Municipal Water District has been invoiced for the above amount.
Change Order No.3, in the total amount of$12,806.01, consists of the following changes:
1. During construction, an unidentified utility was discovered. The contractor was forced to remove,
disassemble, and then reassemble his trench shield to move past the utility. This process resulted
in delays to the project.
2. At the intersection of Bobbett Street and 9th Street, a conflict with a water main and valve cluster
was encountered. It was necessary to remove an existing concrete pad from beneath the valve
cluster to provide for clearance between the water valves and the new storm drain.
3. It was also discovered that there was inadequate clearance between the new storm drain and three
utilities. To ensure protection of the utilities, it was necessary to install concrete collars at the
crossings with the utilities.
4. The contractor elected to use a pavement grinder to remove the asphalt within the trench. Conflicts
with the operations of Bubalo Construction prevented David T. Wasden, Inc. from completing the
pavement removal in one operation. David T. Wasden, Inc. was required to move its equipment in
for a second time after Bubalo Construction completed work in the area. This resulted in a claim
by our contractor for additional compensation.
2
08/11/20053:47 PM
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
STAFF REPORT (Continued)
5. The project required an existing catch basin in 9th Street near Waterman Avenue to be connected
into the new storm drain. The existing catch basin was incorrectly constructed with a reverse slope
in the bottom. It was necessary for our contractor to modify the bottom of the existing catch basin
in order to achieve positive drainage from the catch basin into the new storm drain.
6. During construction, a sewer line was uncovered and determined to be leaking. It was necessary
for the contractor to repair the sewer prior to backfilling of the trench.
7. It was necessary to pour a concrete collar around an existing sewer main to provide adequate
support for the new storm drain.
8. The plans and specifications call for our contractor to base pave the trench to serve as a temporary
driving surface until the storm drain work was completed. After completion of all work, the plans
called for final asphalt pavement to be installed to produce a smooth, finished riding surface. Due
to scheduling conflicts between the storm drain project and the water main being installed by
Bubalo Construction, our contractor was unable to place the final cap and he indicated that he
would pull off the job until Bubalo Construction cleared the work area. David T. Wasden, Inc. also
indicated that additional mobilization charges would apply when he returned to place the final cap.
Rather than incur these additional charges, staff chose to eliminate the final asphalt concrete cap
from the project. The final asphalt concrete cap will be installed by City forces or by a separate
contract.
Staff is recommending that $40,000 to cover the cost of this change order and shortfall of
approximately $24,286 in the account be transferred from Account No. 248-368-5504-7316 "SD04-
08 State Street Storm Drain". The City is currently paying SAN BAG for its share of the cost of
State Street Storm Drain, which is currently under construction. Sufficient funds are available for
this transfer from the FY 2005/06 carryover in Account No. 248-368-5504-7316 and sufficient
funding will remain to meet all obligations for construction of the State Street Storm Drain.
The work involved in this project has been completed. Upon approval of this change order, the
project will be closed out.
Financial Impact:
The cost of this change order is $12,806.01. In addition to that cost, there is a shortfall of
approximately $24,286 in the account, which resulted from increased staff costs and inspection
requirements. Further, it is anticipated that approximately $3,000 in staff charges remain to be
made to the account. Therefore, staff is recommending that a total of $40,000 be transferred from
Account No. 248-368-5504-7316 "SD04-08 State Street Storm Drain" to Account No. 248-368-
5504-7429 "9th Street Storm Drain from Waterman Avenue to East Twin Creek (SD04-12)" III
order to cover the cost of this change order and the shortfall in the account.
3
08/08/2005 1 :06 PM
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
STAFF REPORT (Continued)
Recommendation:
1. Authorize the Director of Finance to amend the Fiscal Year 2005/2006 budget by transferring
$40,000 from Account No. 248-368-5504-7316 "SD04-08 State Street Storm Drain" to Account
No. 248-368-5504-7429 "9th Street Storm Drain from Waterman Avenue to East Twin Creek".
2. Authorize the Director of Development Services to execute Contract Change Order No. Three to
contract with David T. Wasden, Inc. for 9th Street Storm Drain Improvements from Waterman
Avenue to East Twin Creek Channel, per Plan No. 10676 for $12,806.01.
4
08/0812005 I :03 PM
DEVELOPMENT SERVICES DEPARTMENT
300 North "D" Street. San Bernardino. CA 92418-0001
Planning & Building 909.384.5057. Fax: 909.384.5080
Public Works/Engineering 909.384.5111 . Fax: 909.384.5155
www.sbcity.org
SM
CONTRACT CHANGE ORDER NO. THREE
FILE NO.4. 7429
W.O. # 7429
DATE: AUGUST 15, 2005
PROJECT:
9TH STREET STORM DRAIN IMPROVEMENTS FROM WATERMAN
AVENUE TO EAST TWIN CREEK CHANNEL PER PLAN NO. 10676.
TO:
DAVID T. WASDEN
1240 San Cristobal Drive
Riverside, CA 92506
GENTLEMEN:
You are hereby compensated for performing the additional work as follows:
ITEM NO: DESCRIPTION OF CHANGE COST
3-1 Delay Time awaiting disposition of Unidentified Utility $ 698.51
3-2 Remove concrete base around Water Values $ 1,938.56
3-3 Install 3 Concrete Collars $ 7,500.00
3-4 Move-in Cost for Trench Grinder $ 599.94
3-5 Repair Catch Basin $ 456.85
3-6 Repair Sewer Main $ 2,760.41
3-7 Pour Concrete Collar on Sewer Main $ 2,500.00
3-8 Credit to the City for deletion of A.C. Cap $ (3,648.26)
Total Cost $ 12,806.01
S:\]ublic Works\RFCA's\2005 Al1\08-15-05\CCO No.3 - David T. Wasden\CCO#3-9th Street Storm Drain.doc
Change Order No. Three
Storm Drain Improvements Project - 9'h Street Storm Drain from Waterman Ave. to East Twin Creek Channel.
JUSTIFICATION:
3-1
3-2
3-3
3-4
3-5
3-6
3-7
3-8
Delay Time for Unidentified Utility
At station 33 + 60 a 24-inch corrugated storm drainpipe was encountered (pipe not
identified on plans). It was necessary to disassemble the trench and reassemble to be
able to b ass the storm drain i e.
Remove Debris Around Water Values
Existing water main and gate values had an excessive amount of concrete poured around
them. It was necessary to remove and dispose of the concrete debris to provide ample
s ace to install ro osed storm drain under the waterline and ate value.
Install 3 Concrete Collars
It was necessary to pour and concrete collars around existing utilities to protect these
utilities to protect these utilities from damage, as there wasn't ample clearance from the
existing utilit to the ro osed storm drain.
Move-in Cost for Trench Grinder
It was necessary to have the trench ground in 2 stages to facilitate Bubalo Construction's
work. This re uired a second move-in of the avement rinder.
Repair Catch Basin
The existing catch basin, which was tied into the new storm drain, had reverse fall. It
was necessar to our a false bottom to correct the now.
Repair Sewer Main
During construction, a sewer mainline was uncovered and determined to be leaking.
The contractor was directed to re air the mainline.
Pour Concrete Collar on Sewer Main
To support an existing sewer main, a concrete collar was poured between the storm
drain and the sewer main.
Credit for AC Cap
Due to logistics and schedule between the City's project and Bubalo Construction
ro'ect, the as halt ca on the trench was eliminated from this ro'ect.
Overall contract cost increase of 10% due to additional increases in fuel, transportation and union labor
costs.
SUMMARY OF CONTRACT COSTS:
The estimated revised contract cost is as follows:
$
$
$
$
$
273,040.00
10,894.66
165,948.00
12,806.01
462,688.67
Original contract amount..........................................................................
Contract Change Order No. One ................................................................
Contract Change Order No. Two ................................................................
Contract Change Order No. Three ...............................................................
Revised Construction Contract Cost............................................................
Additional time to complete contract due to this change order..............................
20 days
The cost of CCO #3 in the amount of $12,806.01 represents 4.7% or the original contract amount.
2
Change Order No. Three
Storm Drain Improvements Project - 9th Street Storm Drain from Waterman Ave. to East Twin Creek Channel.
C.C.O. #1, C.C.O. #2 and c.C.O. #3 in the total amount of $189,648.67 represents 69.5 % of the
original contract amount. The contractor has agreed to accept change orders for this extra work in lieu
of a supplemental agreement.
DAVID T. WASDEN, INC.
CONTRACTOR
Accepted
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES
Approved
By:
By:
JAMES FUNK
Director of Development Services
Title:
Date:
Date:
APPROVAL BY CITY COUNCIL
Item No.
Approval Date: August 15,2005
3