Resolution awarding contract to Dye and
Browning Construction, Inc. for the
installation of curb and gutter, sidewalk and
asphalt concrete paving at Richardson Street
from Hardt Street to 400 feet North (SS04-
13) per Plan No. 10663 and authorize the
Director of Finance to amend the FY 03/04
CIP Budget.
Dept:
Development Services
Date:
January 27,2004
FileNo.
1.7156-03-02
ORiGiNAL
MCC Date: February 17,2004
Synopsis of Previous Council Action:
09/15/03 Allocated a total of $356,600.00 (SS 04-13) Street and Safety Improvements at Various Locations
Recommended Motion:
I. Adopt Resolution; and
2. Authorize the Director of Finance to amend the FY
03/04 eIP Budget and transfer $52,000 from Acc!. No.
129-367-5504-7156 (Street & Safety Improvements at
Various Locations) to Acct. No. 129-367-5504-7448
(Richardson St. - Hardt to 400 feet north).
~~
Contact Person: Robert Sepulveda, Engineering Associate
Phone:
5167
Supporting data attached: Staff Report, Map & Resolution Ward:
3
FUNDING REQUIREMENTS: Amount: $52,000.00
Source: (Ace!. No)
129-367-5504-7448
Acct. Description: Street and Safety Improvements at Various
Locations (SS 04-13)
.....u, ~cj/~~
Council Notes:
'VFN"\~04rSO
Gl~
Agenda Item No. ~
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Resolution awarding contract to Dye and Browning Construction for the installation of curb and gutter,
sidewalk and asphalt concrete paving at Richardson Street from Hardt Street to 400 feet North (SS04-
13) per Plan No. 10663 and authorize the Director of Finance to amend the FY 03/04 CIP Budget.
Backl!;round:
This project is a result of the School of the Month Program. Richardson Elementary School has
requested improvements of curb, gutter and sidewalk in front of the school. In the design stages we
found a right-of-way issue. The School District has dedicated the needed right-of-way for the new
curb, gutter and sidewalk. The Traffic Section found that the crosswalk in front of the school had no
handicap ramp and requested that one be installed. With the available monies in our Street and Safety
Project Fund (SS04-13), we have included all items needed in this project.
Plans and Specifications, for Installation of Curb, Gutter, Sidewalk and Asphalt Paving at Richardson
Street from Hardt Street to 400' North (SS04-13), have been approved. Bids have been received and
the construction project is ready to be awarded.
This project was advertised locally in the San Bernardino County Sun Newspaper, F. W. Dodge
Company, Reed Construction Data, Bid America Electronic online Plan Room, Construction Data
(Hot Sheet), Construction Bid Source, the City's web site, and with the San Bernardino Area
Chamber of Commerce. The following companies responded:
Name of Bidder City Amount of Basic Bid
Dye and Browning Construction, Inc. Rancho Cucamonl!;a $35,690.60
Wheeler Paving Riverside $42,000.12
Hardv & Harper Santa Ana $43,464.00
Sol Construction, Inc. Riverside $45,433.00
Holland Lowe Construction, Inc. San Bernardino $45,986.00
International Pavinl!; Solutions San Bernardino $47,080.50
Enlrlneer's Estimate $48,748.00
The estimated project costs are as follows:
Item Cost Estimated Cost
Construction Cost $35,690.60
Continl!;encies $ 9,000.00
Inspection and Contract Administration $ 7,309.40
Total $52,000.00
2
CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
STAFF REPORT - Continued
If the project is awarded, it is anticipated that construction can start in March of 2004, and be
completed by April of 2004.
Financial Impact:
Because this project is going to cost over $25,000, Finance recommends that a separate project be set
up. Sufficient funds are available to transfer out of Acct. No. 129-367-5504-7156 (Street & Safety
Improvements at Various Locations) to Acct. No. 129-367-5504-7448 (Richardson Street - Hardt
Street to 400 feet north).
Recommendation:
1. Adopt Resolution; and
2. Authorize the Director of Finance to amend the FY 03/04 CIP Budget and transfer $52,000 from
Acct. No. 129-367-5504-7156 (Street & Safety Improvements at Various Locations) to Acct. No.
129-367-5504-7448 (Richardson St. - Hardt to 400 feet north).
3
r
r----------------------------------------------------------------------------------------------------------------,
I I
J I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
City of San Bernardino, California
Development Services Dept./ Public Works Division
PROJECT
LOCATION
~
_.,'C,
1Jl(
'[~ ,COOlEY ~j
If.")!
~ro/'l
~~I'
8. ,
1:- ~ =-
- ..
}!.
"!
" RR
IiAAD1
ST
~",
[ ItAADT ~ '"
----,--- w,"'c
1-'1 ] HkRDT S1 ~1<:>BIt;; H40]
lJll ---m..----=.L----..1"}
[ GDul.'Ll $T ,:~::;;GOOLO t <, ~T
---:------- ---1"[ GOUlD Sl ,', .
l:tl. ~.,. i . ::!I ';:(
[ nljl~ ::L-i,t -"'.m' I'~ I' ~"'.
_ -- I," ,-- I DJWIIJSO~ .,!'l
",' u:;K;,.~-J._. tr iT-.,~"1.
(0\llS11J~ Sf '" ~,,"I I .~
-+=-. --~ cillut: LI-[~11!:i t.~ - _ _E~~lSTII~ ___~___~__--- ,Ql J
L ~.':-fd.i~.:?- t; t;: t:; 1!:: ;:. :;;:jOjUL5TDH ST
~_~_~~"~l;~' i.;l;_~$ if, !.II "I ~ ~8;1 ~
,. I U~ .-'-......;..' :::. ,. :::I :J: !
(") ~, rI'I - mllllllt LN~.., ~ 0 '" ..
'fi DR ~:... \~~., '-'
_ ____ ~ t
l ~lllDW ME l.N ...."-
HU>!-
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1_____________________________________________________-----------------------------------------------------------~
B~IEl(
iii
[
2~~
131
""
1';11
g
.1;;
<0 I
B~,~~~. mTtR, .ff
/ It; 'i~ I~
, 111001 Th~mas ~JIJ~, ~lpS
VICINITY
NT.S,
MAP
.
,
e
e
e
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
~~~~
RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SA'\
BER'\ARDINO AWARDING A CONTRACT TO DYE AND BROWNING
CONSTRUCTION, INC FOR THE INSTALLATION OF ClTRB, GUTTER,
SIDEWALK AND ASPHALT CONCRETE PAVIl'IG AT RICHARDSOl'l STREET
FROM HARDT STREET TO 400' NORTH (SS04-13) PER PLAl'I :'0/0.10663.
BE IT RESOLVED BY THE MAYOR AND COMMON COlTNCIL OF THE
CITY OF SAN BERNARDINO AS FOLLOWS:
SECTION 1. Dye and Browning Construction. Inc. at 7365 Carnelian Street. Suite 241,
Rancho Cucamonga, CA 91730 is the lowest responsible bidder for the Installation of Curb,
Gutter. Sidewalk and Asphalt Concrete Pa\'ing at Richardson Street from Hardt Street to 400'
North (SS04-131 per Plan No. 10663. A contract is awarded accordingly to said bidder, and
\\ai\'ing all minor irregularities with said bid. in a total amount of $35.690.60, with a
contingcncy amount of $9.000.00. but such award shall be effecti\'e only upon being fully
executed by both parties. All other bids, therefore. are hereby rejected. The Mayor is hereby
authorized and directed to execute said contract on behalf of the City: a copy of the contract is
on file in the office of the City Clerk and incorporated herein by reference as fully as though set
forth at length.
SECTIO:'o/ 2. This contract and any amcndment or modifications thereto shall not take
effect or become opcratiw until fully signcd and executed by the parties and no party shall bc
obligated hcrcundcr until the time of such full execution. No oral agreements, amendments,
modifications or wai\'crs are intended or authorized and shall not be implied from any act or
23
24 course of conduct of any party.
25 SECTION 3. This rcsolution is rescinded if the parties to the contract fail to executc it
26 within sixty (601 days of passage of the rcsolution.
27
28 IIII
l;7 D, /?
2/17/Df
.
.,'
e
e
e
RESOLUTION OF THE MAYOR AND COl\1l\lON COUNCIL OF THE CITY OF SAN
BERNARDINO AWARDING A CONTRACT TO DYE A:-ID BROWNING
CONSTRUCTION, INC. FOR THE INSTALLATION OF CURB, GlTTER,
SIDEWALK AND ASPHALT CONCRETE PAVI!\'G AT RICHARDSON STREET
FROM HARDT STREET TO 400' NORTH (SS04-13) PER PLAN NO. 10663.
1
2
3
4
5
6
7
8
9
10 ESTRADA
I
I
I HEREBY CERTIFY that the foregoing Resolution was duly adopted by the tvlayor and I
meeting thereof, held on the
Common Council of the City of San Bernardino at a
day of
, 2004, by the following vote, to wit:
t\'AYS
ABSTAIN
ABSENT
Council Members:
AYES
11
12
13
14
15
16
17
18
19
20
LONGVILLE
MC GINNIS
DERRY
SUAREZ
ANDERSON
MC CAMMACK
City Clerk
21 The foregoing resolution is hereby approv'ed this
day of
,2004.
22
23
24
25
26
27
28
Judith Valles, Mayor
City of San Bemardino
Approved as to
fom1 and legal content:
~.
J<1111::~~ { '" !~'l:xs ,. b,'
En} Altvl'ney S p o"c ,..1 CO"~ ,e{
CITY OF SAN BERNARDINO
Interoffice Memorandum
CITY CLERK'S OFFICE
Records and Information Management (RIM) Program
DATE:
February 19, 2004
TO:
Leslie Crawford, Engineering Assistant I
FROM:
Michelle Taylor, Senior Secretary
RE:
Transmitting Documents for Signature - Resolution 2004-50
At the Mayor and Common Council meeting of February 17, 2004, the City of San Bernardino
adopted Resolution 2004-50 - Resolution awarding a contract to Dye and Browning
Construction, Inc., for the installation of curb, gutter, sidewalk and asphalt concrete paving at
Richardson Street from Hardt Street to 400' north (SS04-13), per Plan No.1 0663.
I am providing you with one certified copy of Resolution 2004-50 and four (4) sets of original
bound contracts. Please obtain signatures where indicated and return one fully executed original
contract to the City Clerk's office as soon as possible.
Please be advised that the resolution and contract will be null and void if not executed
within 60 days, or by April 19, 2004.
If you have any questions, please do not hesitate to contact me at ex!. 3206. Thank you.
e above mentioned documents.
Please sign and return.
Date:
.
Taylor Mi
From:
Sent:
To:
Subject:
Taylor_Mi
Monday, April 12, 2004 10:09 AM
Crawford_Le
Reminder - Contracts
Hello Leslie,
The contracts with Repipe-Califomia, Inc., and Dye & Browning Construction, Inc., are due on Monday,
April 19. If you have any questions, please give me a call at ext. 3206.
Thanks and have a blessed day!
Michelle Taylor
Sr. Secretary, CityOerk's Office
(909)384-5002, ext. 3206
TAYLO~MIIiiJSBaTY.ORG
1
f
. .
. ,
** FOR OFFICE USE ONLY - NOT A PUBLIC DOCUMENT **
RESOLUTION AGENDA ITEM TRACKING FORM
Meeting Date (Date Adopted): Q..-I 'l..-o~ Item # , t..j Resolution #
Vote: Ayes 1- '-1 \ (,,- 'I Nays kr Abstain S
Change to motion to amend original documents 0 Companion Resolutions
zoott- 50
Absent -€Y'
Null/VoidAfter: fc() days/ A-t"l-cf\
Resolution # On Attachments: 0" Note on Resolution of attachment stored separately: IT
PUBLISH 0
POST 0
RECORD W/COUNTY 0
By:
'2-- \ '6' '0 \.j
'2- - \ >>--{)'i
Date ofClerk/CDC Signature: 2-\q~
Date Sent to Mayor:
Date of Mayor's Signature:
Reso_ Log Updated:
Seal Impressed:
a-
g...
Date MemolLetter Sent for Signature: '2-19 -o'i Date Returned: L( -( L{-O"-( Not Returned: 0
I" Reminder Letter Sent: L\- \ L -a,-\ 2nd Reminder Letter Sent:
Request for Council Action & Staff Report Attached: YesL No By
Updated Prior Resolutions (Other Than Below): Yes No / By
Updated CITY Personnel Folders (6413, 6429, 6433,10584,10585,12634): Yes NoL By
Updated CDC Personnel Folders (5557): Yes No / By
Updated Traffic Folders (3985, 8234, 655, 92-389): Yes No? By
Copies Distributed to:
Animal Control 0 EDA 0 Information Services 0
City Administrator 0 Facilities 0 Parks & Recreation 0
City Attorney I!f Finance ~ Police Department 0
Code Compliance 0 Fire Department 0 Public Services 0
Development Services 0' Human Resources 0 Water Department 0
Others: ~~
Notes:
Ready to File: _
Date:
Revised 12/18/03