HomeMy WebLinkAbout13-Development Services r CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION From: James Funk, Director Subject: Authorization to execute Agreement for Professional Services with Associated Development Services Engineers, Inc. for design of sanitary sewer O R ,G IN A L main replacement in Arrowhead Avenue December 2, 2003 from Mill Street to Chandler Place. Dept: Date: MCC Date: December 15, 2003 Synopsis of Previous Council Action: 5/05/03 Council rejected all proposals and directed staff to conduct a new RFP process to obtain Professional Services for design of sanitary sewer lines. 9/02/03 Council authorized the Director of Development Services to solicit proposals for Professional Civil Engineering Services for the design of a sanitary sewer line to replace or parallel approximately 5,176 linear feet of existing l2-inch main with a l5-inch sewer main in Arrowhead Avenue from Mill Street to Chandler Place, including CIP No. SW04-25; and that the new RFP format be authorized for use for future Public Works Projects. 9/15/03 Council approved the Capital Improvements Program containing Sewer Project No. SW04-25 known as Arrowhead Avenue Replacement/Parallel Sewer Main. Recommended Motion: Adopt Resolution. -~ rd-- Contact Person: James Funk, Director Phone: 5357 Supporting data attached: StaffRepart, 'Resa'; Agreement; Attachment itA" Service Agreement (including Exhibit 1); Attachment B andC Ward: 3 FUNDING REQUIREMENTS: Amount: $50,000 Source: (Acct. No.) ?4S-,/iS-SS04-7477 (Acct. Description) Finance: Council Notes: K~ ~ '2CDi\-.3 1t13 !j5jDtf CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION STAFF REPORT Subject: Authorization to execute Agreement for Professional Services with Associated Engineers, Inc. for design of sanitary sewer main replacement in Arrowhead Avenue from Mill Street to Chandler Place. Background: The Sewer Collection System Master Plan (SMP) was prepared under an agreement between the City and Psomas for the purpose of studying the City's existing sewer system capacity, integrity and the systems ability to handle future land use changes and redevelopment to the year 2020. It is anticipated that 5 to 10 year master plan updates will be required to review historical growth and future growth conditions. Psomas has made recommendations for improvements based on the new land use information provided by the City, population projections obtained from current census data, and data captures from temporary flow monitoring the City has contracted as part of this project. Hydraulic modeling was used to determine system deficiencies and determine sizing and alignments of new mains to eliminate deficiencies. With the complexity and time constraints of this project, a consultant would have greater resources to complete the designs needed in a timely manner. The consultant selected for this project will follow the city's design standards and prepare a complete working set of specifications and drawings ready for bidding. The adopted FY 2003/04 Capital Improvement Program (CIP) contains the proposed Arrowhead Avenue Main Sewer Line Project (SS04-25). The existing sewer line exceeds 100 percent capacity. The Sewer Collection System Master Plan identified this improvement as a priority in comparison to others. The project will replace approximately 5,176 linear feet of existing 12- inch main with I5-inch sewer main in Arrowhead Avenue from Mill Street to Chandler Place. Requests for Proposal (RFP) for Professional Services were sent to II civil engineering firms. Proposals were received from the following consultant entities: Location San Bernardino San Bernardino Uland Interviews were scheduled with the three responding firms. A selection committee consisting of Development Services Director James Funk, Acting City Engineer Mike Grubbs, Project Manager/Associate Engineer David Philips, and Senior Planner Aron Liang interviewed the three consultant firms. The reviewers/evaluators unanimously rated as number one the team of Transtech Engineering, Inc./Mapco Engineers, Inc. based on their qualifications and staffs previous experience with the firm. The City Council's approved evaluation criteria were used. The forms illustrating the - 2- r CITY OF scoring points po Phase I Review 0 This report contal Engineering, Inc. complete the sco Transtech/Mapco and Hall & Forem questions the pane Rater/Evaluator Director Senior PlamIer Engineering Asso City Engineer Average Company Transtech/Mapco Associated Engineers, Inc. Hall and Forman, Inc. *If needed but n **Transtech/Ma the "E" Street S awarded to them $9,827. SAN BERNARDINO REQUEST FOR COUNCIL ACTION STAFF REPORT - Continued ssible for each criterion are attached. See Attachment B to view the forms for f Proposals and Phase II Selection Interviews. ns the scores given to each consultant firm by each evaluator/rater. Transtech (known as the team of Transtech/Mapco) was evaluated as the best firm to pe of work. The evaluators gave an average rating score of 93 percent to , followed by Associate Engineers with an average rating score of 80 percent, an with an average rating score of 67 percent. Attachment "C" contains the I raters/evaluators posed to each consultant entity. ARROWHEAD MAIN SEWER LINE ARROWHEAD/MILL TO CHANDLER COMBINED RFP AND INTERVIEW SCORES Transtech/Mapco Associated Engineers Hall & Foreman 93.5% 76% 54% 93% 83.5% 72% c. 94% 73% 76% 90.5% 89% 64.5% 93% 80% 67% ARROWHEAD MAIN SEWER LINE PROPOSED FEES Base Price Potholing Soils Investigation * Total $80,340 $ 5,000 $5,000 $90,340 Not to Exceed $42,233 $ 6,000 No Specified Fee $48,433 Not to Exceed $76,325 $10,350 $6,030 $92,705 (Direct Cost) Fixed Fee ot likely to be needed. pco offered in its proposal to reduce its fees by 5 percent in the event both ewer Line Project and the Arrowhead Main Sewer Line Project were This would result in a reduction in the "not-to-exceed" fees totaling - 3- CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION STAFF REPORT - Continued Transtech/Mapco proposed a fee not to exceed the sum of $90,340, which includes $5,000 for potholing and $5,000 for soils investigation. Associated Engineers, Inc. proposed a fee not to exceed the sum of $48,433, which includes $6,000 for potholing and made no mention of soils investigation. Under the City's Municipal Code (Section 3.04.01OB3), the Mayor and Common Council are not required to award to the most qualified consultant; but, may award based on extenuating and/or compelling circumstances, such as a significant cost savings to the City. Associated Engineers, Inc. is qualified and capable of doing the required work; and, in comparison to the proposed fee ofthe number one rated consultant entity, at a significant savings to the City. The Development Services Director is recommending that the number two rated consulting entity (Associated Engineers, Inc.) be awarded the contract to design the main sewer line in Arrowhead Avenue. Financial Impact: A total of $1,314,000 for the project was approved in the FY 2003/04 CIP to cover consultant services, administration, inspection, and construction. The funding source is the Sewer Line Construction Fund, Account No. 245-365-5504-7422 (Replace sewer main in Arrowhead Avenue from Mill Street to Chandler Place). This award of contract would have the financial impact of as much as $50,000: A not-to-exceed fee of $48,433 for this project, plus a $1,567 contingency (in the event the scope of work is needed to be expanded), for a total of $50,000. Recommendation: Adopt Resolution. -4- e e e ------ --------r--- cc~r1f 1 RESOLUTION NO. 2 RESOLUTION OF THE CITY OF SAN BERNARDINO APPROVING A SERVICES AGREEMENT WITH ASSOCIATED ENGINEERS, INC. FOR DESIGN OF 3 SANITARY SEWER MAIN REPLACEMENT IN ARROWHEAD AVENUE FROM MILL 4 STREET TO CHANDLER PLACE. BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN BERNARDINO AS FOLLOWS: 5 6 7 8 the design of sanitary sewer main replacement and have provided the most advantageous and SECTION 1. Associated Engineers, Inc. is competent, experienced and able to perform 9 best proposal for provision of the design of sanitary sewer main replacement in Arrowhead 10 Avenue from Mill Street to Chandler Place, per Agreement for Professional Services, attached 11 hereto and incorporated herein as Exhibit A, for the not to exceed amount of $48,433, with a 12 13 14 15 16 contingency fee of $1,567 (in the event the scope of work needs to be expanded), for a total of $50,000. Pursuant to this determination, the Purchasing Manager is hereby authorized and directed to issue Purchase Orders for said services to said firm. The Mayor is hereby authorized and directed to execute said agreement on behalf of the City. 17 SECTION 2. The authorization to execute the above referenced Agreement is rescinded 18 19 III 20 21 ifit is not executed within sixty (60) days of the passage of this resolution. III 22 23 24 25 26 27 28 ~o .f3j ( 1--- /; ~l:J .3 - I - e e e . 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 RESOLUTION...APPROVING A SERVICES AGREEMENT WITH ASSOCIATED ENGINEERS, INC. FOR DESIGN OF SANITARY SEWER LINE REPLACEMENT IN ARROWHEAD AVENUE FROM MILL STREET TO CHANDLER PLACE. I HEREBY CERTIFY that the foregoing resolution was duly adopted by the Mayor and Common Council of the City of San Bernardino at a meeting thereof, held on the day of ,2003, by the following vote, to wit: Council Members: AYES NAYS ABST AIN ABSENT ESTRADA LONGVILLE MC GINNIS DERRY SUAREZ ANDERSON MC CAMMACK City Clerk The foregoing resolution is hereby approved this day of ,2003. Judith Valles, Mayor City of San Bernardino 22 Approved as to form and legal content: 23 24 25 26 27 28 JAMES F. PENMAN, City Attorney - 2 - e e e T ATTACHMENT "A" AGREEMENT FOR PROFESSIONAL SERVICES (FOR NON-FEDERALLY FUNDED PROJECTS) This AGREEMENT is made and entered into this day of 2003, by and between the CITY OF SAN BERNARDINO, California, a municipal corporation, hereinafter referred to as the "CITY" and Associated Engineers, Inc., hereinafter referred to as "CONS UL T ANT." WITNESSETH: A. WHEREAS, CITY has need for sanitary sewer design; and, B. WHEREAS, CONSULTANT is competent, experienced and able to perform said services; and, C. WHEREAS, CONSULTANT has provided the most advantageous and best proposal for the provision of such services; NOW THEREFORE, the parties hereto agree as follows: I. SCOPE OF SERVICES Consultant shall perform those services specified in the Proposal dated October 16, 2003, titled "Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead A venue from Mill Street to Chandler Place" for preparation of plans, specifications, and estimates for said project, attached and incorporated herein as Exhibit 1, and as directed by the City of San Bernardino. 2. TERM OF AGREEMENT The services of Consultant are to commence after the City has authorized work to start by issuance of a Notice to Proceed. This Agreement shall expire one year from the date of this Agreement unless extended by written agreement of the parties. 3. STANDARD OF PERFORMANCE Consultant shall complete all work product and design in conformance with City of San Bernardino Standard Specifications and Standard Drawings. 4. CHANGES/EXTRA SERVICES A. Performance of the work specified in the Proposal is made an obligation of Consultant under this Agreement, subject to any changes made -1- ------~---- y--- Agreement for Professional Services with Associated Engineers, Inc. e subsequently upon mutual written agreement of the parties. Any change, which has not been so incorporated, shall not be binding on either party. 5. COMPENSATION A. The City shall reimburse the Consultant for actual costs (including labor costs, employee benefits, overhead, profit, other direct and indirect costs) incurred by the Consultant in performance of the work, in an amount not to exceed $48,433, with an additional contingency amount of$I,567, for a total amount of $50,000, except that reimbursement shall not include courier services, mileage or reimbursement for travel to the City to attend meetings or conduct the activities. Actual costs shall not exceed the estimated wage rates and other costs as set forth in the Proposal. B. Said compensation shall not be altered unless there is significant alteration in the scope, complexity or character of the work to be performed. e Any adjustment of the total cost of services will only be permitted when the Consultant establishes and City has agreed, in writing, that there has been, or is to be, a significant change. c. The Consultant is required to comply with all Federal, State and local laws and ordinances applicable to the work. 6. PAYMENT BY CITY A. The billings for all services rendered pursuant to this Agreement shall be submitted monthly by Consultant to City and shall be paid by City within thirty (30) days after receipt of same, excepting any amounts disputed by City. City retains the right to challenge all or any part of an invoice. All tasks as specified in Proposal shall be completed prior to final payment. 7. SUPERVISION AND ACCEPTANCE OF SERVICES A. The Director of Development Services of City or his designee, shall have the right of general supervision over all work performed by Consultant and shall be City's agent with respect to obtaining Consultant's compliance hereunder. No payment for any services rendered under this Agreement shall be made without prior approval of the Director of Development Services or his designee. e - 2 - e e e f Agreement for Professional Services with Associated Engineers, Inc. 8. COMPLIANCE WITH CIVIL RIGHTS LAWS AND AMERICANS WITH DISABILITIES ACT Consultant hereby certifies that it will not discriminate against any employee or applicant for employment because of race, color, religion, sex, marital status, national origin or disability. Consultant's hiring practices and employee policies shall comply with applicable Federal, State and local laws. Such action shall include, but not be limited to, the following: Recruitment and recruitment advertising, employment, upgrading and promotion. 9. TERMINATION OF AGREEMENT A. This Agreement may be terminated by either party upon thirty (30) days written notice in the event of substantial failure of the other party to perform in accordance with the terms of this Agreement. Each party shall have twenty (20) days following date of such notice within which to correct the substantial failure giving rise to such notice. Consultant hereby covenants and agrees that upon termination of this Agreement for any reason, Consultant will preserve and make immediately available to City, or its designated representatives, maps, notes, correspondence, or records related to work paid for by the City and required for its timely completion, and to fully cooperate with City so that the work to be accomplished may continue. Any subsequent use of such incomplete documents shall be at the sole risk of the City and City agrees to hold harmless and indemnify Consultant from any claim, losses, costs, including Attorney's fees, and liability arising out of such use. B. This Agreement may be terminated for the convenience of the City upon thirty (30) days written notice to Consultant. Upon such notice, Consultant shall provide work product to City and City shall compensate Consultant in the manner set forth above. C. Following the effective date of termination of the Agreement pursuant to this Section, the Agreement shall continue until all obligations arising from such termination are satisfied. 10. CONTINGENCIES In the event that, due to causes beyond the control of and without the fault or negligence of Consultant, Consultant fails to meet any of its obligations under this Agreement, and such failure shall not constitute a default in performance, the City may grant to Consultant such extensions of time and make other arrangements or additions, excepting any increase in payment, as may be reasonable under the circumstances. Increases in payment shall be made only under the "changes" provision of the Agreement. - 3- . . e .. Agreement for Professional Services with Associated Engineers, Inc. II. INDEPENDENT CONTRACTOR Consultant shall act as an independent contractor in the performance of the services provided for under this Agreement. Consultant shall furnish such services in its own manner and in no respect shall it be considered an agent or employee of the City. 12. ASSIGNMENT OR SUBCONTRACTING Neither this Agreement, nor any portion thereof, may be assigned by Consultant without the written consent of City. Any attempt by Consultant to assign or subcontract any performance of this Agreement without the written consent of the City shall be null and void and shall constitute a breach of this Agreement. 13. NOTICES All official notices relative to this Agreement shall be in writing and addressed to the following representatives of Consultant and City: Consultant Associated Engineers, Inc. 225 S. Del Rosa Drive San Bernardino, CA 92408-0111 Ph: (909) 382-0016 Fax: (909) 382-0026 City Mr. James Funk, Director Development Services Department City of San Bernardino 300 North "D" Street San Bernardino, CA 92418 14. RESPONSIBILITIES OF PARTIES Upon termination, or completion of all work under this Agreement, Consultant will transfer ownership and title to City of all programs, reports, documents, plans and specifications. 15. INDEMNITY Consultant shall indemnify, defend and hold CITY, its officers, employees and agents harmless from and against any and all claims, demands, suits, actions, proceedings, judgments, losses, damages, injuries, penalties, costs, expenses (including attorney's fees) and liabilities. of, by, or with respect to third parties, which arise from Consultant's negligent performance of services under this Agreement. Consultant shall not be responsible for, and City shall indemnify, defend and hold harmless Consultant from and against, any and all claims, demands, suits, actions, proceedings, judgments, losses, damages, injuries, penalties, costs, expenses (including attorneys' fees) and liabilities of, by or with respect to third parties, which arise from the City's negligence. With respect to - 4- e e e Agreement for Professional Services with Associated Engineers, Inc. any and all claims, demands, suits, actions, proceedings, judgments, losses, damages, injuries, penalties, costs, expenses (including attorneys' fees) and liabilities of, by or with respect to third parties, which arise from the joint or concurrent negligence of Consultant and City, each party shall assume responsibility in proportion to the degree of its respective fault. 16. LlABILlTYIINSURANCE A. Consultant's liability to the City for injury or damage to persons or property arising out of work performed by the Consultant and for which legal liability may be found to rest upon Consultant other than for professional errors and omissions, shall be a minimum of $1 ,000,000. For any damage or injury on account of any error, omission or other professional negligence, Consultant's liability shall be limited to a sum not to exceed $50,000 or Consultant's fee, whichever is greater. B. The City will require the Consultant to provide Worker's Compensation and Comprehensive General Liability Insurance, with coverage sufficient to insure the Consultant's liability, as above required; and, such insurance shall include the City, and each of it's officers, agents and employees as additional insured with exception to additional insured under Worker's Compensation. C. Consultant shall provide evidence of insurance with a 10-day notice to City of termination or material change. 17. VALIDITY Should any provision herein be found or deemed to be invalid, this Agreement shall be construed as not containing such provision, and all other provisions which are otherwise lawful shall remain in full force and effect, and to this end the provisions of this Agreement are declared to be severable. 18. ENTIRE AGREEMENT This Agreement represents the entire and integrated understanding between the parties hereto and supersedes all prior and contemporaneous negotiations, representations, understandings and Agreements, whether written or oral, with respect to the subject matter thereof. This Agreement may be amended only by written instrument signed by both parties. III - 5 - e e e Agreement for Professional Services with Associated Engineers, Inc. IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the date shown below. Date: Date: ATTEST: Rachel Clark, City Clerk Approved as to form and legal content: James F. Penman City Attorney ASSOCIATED ENGINEERS, INC. by: Signature Print Name/Title CITY OF SAN BERNARDINO by: Judith Valles Mayor City of San Bernardino - 6- Exhibit 1 R.e'juest tor F raposal fublic Works Division Development Services Department Cit,y of San E:>ernardino Design ot Sanitar~ Sewer Line Replacement/Upgrade at Arrowhead Avenue trom Mill Street to Chandler Flace ., 5ubmitted by: Associated Engineers, Jnc. Consulting Civil Lngineers planning. designing. surve~ing ?? 1 1 E.. Shelb~ Street Ontario, California 91 76+-+872 Tel (909) 980-1982 Fax (909) 9+1-0891 www.assoc-eng.com I- I ." Associated Engineers, Inc. CONSUL liNG CIVIL ENGINEERS 225 S. DEL ROSA DRIVE. SAN BERNARDINO, CA 92408-0111 (909) 382-0016 FAX (909) 382-0026 October 16, 2003 City of San Bernardino Department of Development Services Division of Public Works 300 North "D" Street, 3rd floor San Bernardino, CA 92418 Attn: Mr. Michael Grubbs, Acting City Engineer Subject: Request For Proposal (RFP) for the Design of Sanitary Sewer Line ReplacementJUpgrade at Arrowhead Avenue from Mill Street to Chandler Place Dear Mr. Grubbs, {"'" , Ii-p -~ In accordance with your Request For Proposals, Associated Engineers, Inc. is pleased to submit four (4) copies of our proposal to provide engineering services for the design of above reference project. Mr. Jamey Dye, P.E. wil1 be our Project Manager and brings 17 years of municipal engineering experience, including 10 years as Senior Engineer with the City of San Bernardino Water Department. Associated Engineers, Inc. has been involved in municipal engineering since its inception in 1955. The services provided by the Associated Engineering team of professionals wil1 be timely, cost-effective, and of exceptional quality. This proposal is arranged according to the City's proposal format and within that format includes each of the checklist items with attention to the evaluation criteria. All project coordination and services will be provided from our office in San Bernardino, California, at 225 S. Del Rosa Drive, San Bernardino, California 92408. We look forward to the opportunity to discuss our qualifications and our approach to assisting you on your project. If you have any questions about our qualifications, or desire additional information, please do not hesitate to contact me at (909) 980-1982. Yours truly, };l)S !A.JI;D ENGINEERS, INe. ~Vr- . . I:. Jamey Dye, RCE Utilities Director encls: Four (4) Copies of Technical Proposal '" One (I) Copy of AE's City of San Bernardino Business License P21O-03 PLANNING DESIGNING SURVEYING O:\I'ROP\P\2003\P21(l.03\COVER lETTElldoc Cit.Y ot San 5emardino tf~.: ~~;'l. ,~ Associated Engineers, Inc. Re9uest tor r r o p o s a Design ot Sanitar,y Sewer Line Keplacement/ Upgrade at Arrowhead Avenue trom Mill Street to Chandler Flace " 1 1 Last Shelb'y Street Ontario, California 9 1 76+-+872 Section 1. Relevant Project Experience Section 2. Project Team . Organ~ationalChart . Resumes Section 3. Flow Chart Section 4. Previous Obligations . Staff Availability Section 5. Support Personnel Section 6. Sub-Consultants Section 7. Local Preference Eligibility . San Bernardino Business License Section 8. Request from City of San Bernardino Section 9. Project Approach Section 10. Additional Information Fhone: (909) 980-1982 Fax No. (909) 9+1-0891 / 6:<>;' /'::~~~1 ~-t... { \'C.. City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place RELEVANT PROJECT EXPERIENCE State Route 210, Segment 9, Sewer and Water Facilities Relocation, Rialto, California: Associated Engineers is currently preparing plans and specifications for the relocation of several water, and sewer facilities for the City of Rial to required for construction of the new SR-210 Freeway. The facilities will consist of I,SOO LF of water mains, and 3,000 LF of sewer main, including three sewer lift stations. Associated Engineers, Inc. is providing planning, plans, specifications, cost estimates, construction support, and coordination with Caltrans. The estimated cost of the facilities is $1,500,000. South Highland Avenue and Juniper Avenue Sewer Improvements, City of Fontana, California: This project consists of the design of 5,000 LF of 10-inch sanitary sewer for the City of Fontana. The engineering services included preliminary engineering to determine tributary areas and flows, sewer sizing analysis, plans and construction specifications. This project also includes dry utility coordination, construction support during bidding and construction inspection. The Colonies at San Antonio, Upland, California: The Colonies at San Antonio is a 400 plus acre master planned community in the City of Upland, which includes both residential and commercial development. Associated Engineers provided engineering, surveys, mapping, Right-of-Way engineering, utility coordination and construction staking services for domestic water, sewer, storm drain, new streets and site grading. This work included 51,900 LF of domestic water pipelines from 6-inch to 16-inch; 42,600 LF of S-inch sewer; and approximately 36,400 LF of storm drain from IS-inch to 72-inch. Extensive analysis and modeling was conducted to facilitate the additional demands on the systems as the project developed. Additional projects available upon request. O'IPROI'\P\2003IP21<Hl3l"""""",,,.doc I I , City of San Bernardino . Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place PROJECT TEAM Curt Ingraham, RCE, will serve as Project Oversight - Mr. Ingraham has been in general civil engineering practice including planning and design of residential and commercial subdivision projects, schools, hospitals, roadway projects, water distribution, sanitary sewer and storm drain projects, FAA improvement design and construction management for more than 17 years. Mr. Ingraham is currently working on design and construction for commercial & industrial buildings at San Bernardino International Airport (former Norton Air Force Base). ~."..< "".~.-::~..j ......-- j;,."F Jamey Dye, RCE, will serve as Project Manager - Mr. Dye has more than 17 years of experience in civil engineering, project managernent, and construction contract administration. He has experience in design, and construction management for residential, commercial and industrial subdivisions, water wells, booster stations and water treatment plants. Mr. Dye has worked as a Project Manager in both the public and private sectors. He is a State of Cali fomi a Certified Grade IV Water Treatment and Distribution Operator. Zack Isnasious, RCE, will serve as a Design Engineer - Mr. Isnasious's background also includes more than 24 years of engineering experience on design and supervision of water pipeline projects, wastewater systems, storm water systems and reclaimed water projects. He has been involved in the design, planning and construction of several remarkable projects". Mr. Isnasious carried out many water projects during his past experience overseas, as well as in the State of California. His experience includes water modeling, water system analysis, water system and pump stations technical evaluation, design of pump stations, and water distribution networks. Michael Guirguis, EIT, will serve as a Design Engineer - Mr. Guirguis has four year of civil engineering design experience in land development and water projects. He has provided engineering support for the preparation of several projects including grading, street, storm drain, sewer and water improvements. He has experience coordinating with multiple entities for effective processing of project plans through plan check. Mr. Guirguis was a Civil Engineering Intern at Montgomery Watson Harza, involved in Pipeline design, grading, and earth reinforcement. Carolann Stoney, will be responsible for Utility Coordination - Ms. Stoney has extensive experience in utility coordination, utility research and utility construction for public works projects. She manages a department of three people who conduct as-built utility confirmation studies, identify utility conflicts, assist utility owners in determination of relocation options, prepare utility conflict maps and work closely with utility purveyors to obtain final relocations. As a Utility Coordinator, she determines the cost percentage for the City, State or Agency, obtains permits and processes legal agreernents. She coordinates pre-construction meetings, schedules and maintains tight construction schedules between utility owners, project designers and construction personnel. Ms. Stoney has experience with cities, counties, Union Pacific Railroad, MetroLink, BNSF, Caltrans, local agencies and all major utility companies in Southern California. l' Jim Elliott, RCE, PLS, will serve as Survey Task Leader - Mr. Elliott is both a Licensed Civil Engineer and a Licensed Land Surveyor. He has 24 years of experience devoted to surveying, engineering and mapping in the Southern California area. Jim is responsible for mapping oversight at Associated Engineers and has provided a variety of surveying services on a wide range of projects including roadwayslhighways, commercial, industrial, and residential. He heads our Mapping Department and is involved with all map calculations. O:\PROP\P\2003\P210-03\PROJECT ~.doc ( Ei::-;;': '.'".--''' ,<<';' c Request for Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place Carol ann Stoney Larry T aylar * Dalores Moreira * Priscilla Emperado * CITY OF SAN BERNARDINO Acting City Engineer Michael Grubbs Associated Engineers Project Manager Jamey G. Dye, R.C.E. Design Engineering Jamey G. Dye, R.C.E. Zack Z. Isnasious, R.C.E. Michael Guirguis, E.I.T * support staff Associated Engineers Project Oversight Curt Ingraham, R.C.E. James L. Elliott, L.S., R.C.E. Janeen Nedlik, L.S. * Marc Wilson, L.S.I.T. * , Jamey Dye, RCE Utilities Director Mr. Dye has more than 17 years of experience in civil engineering, project management, and construction contract administration. Mr. Dye had over 10 years of experience working as the Sr. Engineer for the City of San Bernardino Municipal Water Department. He has experience in design, and construction management for residential, commercial and industrial subdivisions, water wells, booster stations and water treatment plants. Mr. Dye has worked as a Project Manager in both the public and private sectors. He is a State of Califomia Certified Grade IV Water Treatment and Distribution Operator. Supervising and Engineering Section of the Water Department: As supervisor of the Engineering Section of the City of San Bernardino Water Municipal Department, Jamey was involved in all aspects of water utility management, his responsibilities included waterline design, backflow prevention, well maintenance, drilling, energy optimization, water quality, water discharge, emergency response, State drinking water permits, booster station design, development of standard drawings, and pipeline design. Newmark Groundwater Contamination Superfund Remedial Action: As a Project Manager for the City of San Bernardino Water Department, Mr. Dye was responsible for the design and construction management for four water treatment plants with a combined capacity of 40 million gallons, 30,000 feet of water main, 10 production wells, 30 monitoring wells, and associated water facilities. ,~: ~~i~? Former Norton Air Force Base. Water System Upgrade: Mr. Dye was responsible for the upgrade of the water system at the former Norton Air Force Base including, evaluating the existing water system, developing a proposed plan, completing grant applications, designing the pipelines, wells, and managing the construction. Enhanced Reliability Schedule of Improvements: Mr. Dye was a key member of a team of department staff and outside consultants who developed the first phase of a long-term master plan for the water system. This involved bringing together a large amount of information and developing a plan that included reservoirs, boosters, and pipelines to support long-term growth for the City of San Bernardino through 2055. This project included applying for and receiving funds. Upper Santa Ana Water Resources Association: During Mr. Dye's tenure at the City of San Bernardino Municipal Water Department, he was very involved in regional water management issues. He regularly attended the Upper Santa Ana Water Resources Association meetings and was involved on several focus committees for water issues including basin management, contamination cleanup, high groundwater mitigation, and water recharge. Project Manager for Nasland Engineering: As Project Manager for Nasland Engineering, Mr. Dye was responsible for the design of a large variety of residential and commercial projects with a diverse set of clients including McMillan Homes, Wal- Marl, McDonalds, the US Army, and the Immigration and Naturalization Services. c. Associated Engineers, Inc. 3311 E. Shelby Street Ontario, CA 91764-4872 0:\PROP\P\2003\P21(HJ3\ReSlImeslJamey WAT'ER.Orx Project Assignment Project Manager Years of Experience 17 Education California Poly Technical University, Pomona Professional Registration Registered Civil Engineer, California - #49004 California Grade IV Water Treatment Operator California Grade IV Water Distribution Operator Resume Tel. 909.980.1982 Fax 909.941.0891 Email: jameyd@assoc-eng.com Curt C. Ingraham, RCE Vice-President Mr. Ingraham has been in general civil engineering practice including planning and design of residential and commercial subdivision projects, schools, hospitals, roadway projects, water distribution, sanitary sewer and storm drain projects, FAA improvement design and construction management for more than 17 years. Mr. Ingraham is currently working on design and construction for commercial & industrial buildings at San Bernardino International Airport (former Norton Air Force Base). The California Speedway, San Bernardino County, California: Mr. Ingraham was the Senior Project Manger for civil works for the construction of this major motor sports facility. Design work included the development of demolition documents to clear the site of remnants of the former steel min, and design of the infrastructure for a spectator crowd of 100,000. He was responsible for the construction documents of development of the 550-acre site and the moving of 2,000,000+ cubic yards of earth, the refurbishment of an existing wastewater treatment plant and design of water, sewer, and storm drain improvements. Associated Engineers completed preliminary surveys and mapping for the site and provided construction staking for the project which held it's frrst race in June of 1997. South Upland Storm Drain, Upland, California: Mr. Ingraham performed design and specifications for the water line relocation plans for 20,000 feet of 8" through 30" waterlines in preparation for a large storm drain project. ,~;:~; ~ *'." ~;.. Snow Creek Pipeline & Hydroelectric Plant, Palm Springs, California: Mr. Ingraham performed a compete design and construction management service for over 24,000 feet of24" steel pipeline with a hydroelectric component. Desert Water Agency, Palm Springs, California;. Mr. Ingraham performed construction inspection and management services for a number of welded steel reservoirs from 1-5 MG including lining and welding inspection. City of Edmonton Water System Modeling and Evaluation, Alberta, Canada: Mr. Ingraham developed a water model for the City of Edmonton (population 720,000) including system calibration. l Associated Engineers, Inc. 3311 E. Shelby Street Ontario, CA 91764-4872 O:\PR0f\P\2003\P21(Hl3\Resumes\C - resume.doc Project Assignment Project Oversight Years Experience 17 Education B.S. in Civil Engineering - 1986 Wana Wana School of Engineering, Wana Wana, Wasbington Professional Registration Civil Engineer, California # 44780 Resume Tel. 909.980.1982 Fax 909.941.0891 Email: curti@assoc-eng.com Zack Z. Isnasious, RCE Design Civil Engineer Mr. Isnasious's background includes more than 24 years of engineering experience in design and supervision of water pipeline projects, wastewater systems, storm water systems and reclaimed water projects. Mr. Isnasious has completed many water projects in the state of California and in his experience overseas. His experience includes water modeling, water system analysis, water system and pump station technical evaluations, design of pump stations, and design of water distribution networks. The Colonies at San Antonio, City of Upland, California: The Colonies at San Antonio is a 400 plus acre master planned community in the City of Upland. It is both a residential and commercial development. Associated Engineers has provided engineering, surveys, mapping, Right-of-Way engineering, utility coordination and construction staking services. We have also designed domestic water, sewer and storm drain facilities, new streets, and site grading. This work included 51,900 LF feet of domestic water from 6-inch to 16-inch; 42,600 LF of S-inch sewer; and approximately 36,400 LF of storm drain from IS-inch to 72-inch. Extensive analysis and modeling was conducted to facilitate the additional demands on the systems as the project has developed. Mr. Isnasious was responsible for hydraulic modeling of the water system. 4. '. ..;<:".... ~~r.~~ City of Santa Monica, California: Mr. Isnasious designed 42" main sewer lines for the City of Santa Monica, mainly at Lincoln Boulevard. The project included a preliminary study on applying the pipe bursting system on busy city streets, hydraulic calculations and utility coordination. South Highland and Juniper Avenue Sewer Improvements - This project consisted of the design and construction management for one mile of 10- inch VCP sewer main. Prepared preliminary design report and pipe design calculations, prepared construction drawings, construction specifications, and cost estimates. Total construction cost $500,000. Water and sewer utilities relocation - City of Rialto - SR21 0 - Seg.9. Acted as the lead design engineer and the co-coordinating Engineer with Caltrans, the City, and the other Utility Owners, saved the client $SOO,OOO by redesigning the utility relocations, designed and prepared plans and profiles for the water and sewer lines and the Sewer Lift Stations (3 lift stations, 2.S5 cfs, 0.65 cfs, 0.31 cfs), prepared bid documents. Total Construction Cost $3,000,000 47 Jurupa Project- Designed and prepared Water, Sewer, Storm Drain, Erosion Control and Precise Grading Plans. Coordinated with the City of Ontario and the San Bernardino Flood Control district, Obtained grading permits, and flood control permits, prepared cost estimates and bid documents. t . ~ Associated Engineers, Inc. 3311 E. Shelby Street Ontario, CA 91764-4872 O:\I'IlOP\P\2OO3\p210-03\ReSUmtS\ZZI-RE&JME.doc: Project Assignment Design Engineer Years oC Experience 24 Education B.S. Civil Engineering Alexandria University Alexandria, Egypt ProCessional Registrations Registered Civil Engineer California # 65544 ProCessional Affiliates International Desalination Association (IDA) American Society oCPlurnbing Engineers (ASPE) Water Science and Technology Association (WSTA) American Water Works Association (AWWA) Water Reuse Association Resume Email: Tel. 909.980.1982 Fax 909.941.0891 zacki@assoc-eng.com I I .,. Michael M. Guirguis, EIT Design Engineer Mr. Guirguis has four year of civil engineering design experience in land development and water projects. He has provided engineering support for the preparation of several projects including grading, street, storm drain, sewer and water improvements. He has experience coordinating with multiple entities for effective processing of project plans through plan check. Mr. Guirguis was a Civil Engineering Intern at Montgomery Watson Harza, involved in Pipeline desigu, grading, and earth reinforcement. Cal Poly Parking Structure, Pomona, California: Mr. Guirguis was Project Engineer responsible for the all Civil Engineering work which included water lines for fIre and domestic service. storm drains, sewer, and street improvements. Ponderosa Industrial Building, Ontario, California: Mr. Guirguis was responsible for the grading and drainage work done on the parking lot and access ramps. Cal Poly Reservoir, Pomona, California: Mr. Guirguis aided in the design of a 1.27 Million Gallon Reservoir tank along with the associated piping and earthwork involved. ."-. ~i;! "'..:.~:-.,.., '-i::~ Colonies, Upland, California: Associated Engineers is providing the surveys, mapping and engineering for the 440-acre land development project. When completed, this project will have 100-acres of commercial development adjacent to the new SR-210 Freeway, l70-acres of single- family residential housing, and a IO-acre elementary school site. Additionally, it will have 35-acres of new roads, 73-acres of open-space that functions as a major flood-control basin and 41-acres of freeway interchange. Associated Engineers has been working with the City of Upland, State of California Department of Transportation, Metropolitan Water District, San Bernardino Public Works Department and the U.S. Army Corps. of Engineers on this multi-faceted project. Phase I consisting 305 Single-Family Residences is ahout to begin. Completed project build-out is scheduled for 2004. Mr. Guirguis desigued over I mile of sewer lines for a 294 acre development site. l Associated Engineers, Inc. Resume 3311 E. Shelby Street Ontario, CA 91764-4872 O,\PROP'\P'I2OOl\P2I0-0l\Rc:sumelIMMG - resume_dac Project Assignment Project Engineer Years of Experience 4 Education B.S. Civil Engineering, Environmental Engineering . California Polytechnic University Pomona, California Certifications Engineer-in- Training, California # 116787 Tel. 909.980.1982 Fax 909.941.0891 Email: michaelg@assoc-eng.com ( , ~?~:i<. '~';}-~jt ";;;." l. . . --. Carolann Stoney Senior Utility Coordinator Ms. Stoney has extensive experience in utility coordination, utility research and utility construction scheduling for conunercial, industrial and residential projects. She conducts easement deeds research, as-built confirmation studies, identifies utility conflicts, determines relocation options, prepares utility conflict maps and works closely with utility owners to complete relocations. As a utility coordinator she facilitates the preparation of relocation plans, determines the cost percentage for the agency or developer and processes legal agreements. She coordinates pre- construction meetings, schedules and maintains tight construction schedules between ntility owners, project designers and construction personnel. Ms. Stoney has experience with conunercial, industrial and residential developers, cities, counties, Caltrans, railroads and all major utility companies in Southern California. Colonies Crossroads, Upland, California: Ms Stoney was responsible for utility coordination for this 1,200 home resideutial site. The project has included coordination with the State Route 210 freeway ramps at New Campus A venue, and over I rnile of a new Rule 20 joint treuching facility with SCE, Verizon, Cable TV and The Gas Company. Ms. Stouey assisted the City of Upland to develop an LS-3 lighting district for the project site. She also managed the required on-site utility design and installation for three (3) developers to acconunodate 600 homes. Basel/ne Avenue Storm Drain, Fontana, California: Associated Engineers provided utility research and on-site confirmations. Ms. Stoney was responsible for utility relocation plans and utility base sheets provided by the design engineer. She attended all progress meetings at the city and coordinated the pre-construction meeting. During the construction phase she maintained utility construction schednles and assisted with utility issues requested by the resident engineer. Kaiser Ventures West End Master Plan, San Bernardino County, California: Associated Engineers provided engineering services, utility studies and design surveys to develop over 700 acres of the former Kaiser Steel Mill in Fontana, California. We directed a team of professional to complete demolition plans, master water, sewer and storm drain, dry utility facilities as well as interconnections to the 1-10 freeway and relocations at Valley Boulevard and Etiwanda Avenue. Associated Engineers provided tentative and final mapping of the entire site. Ms. Stoney was responsible for relocation coordination and final as-built utility maps. Guastl Plar.a, Ontario, California: Associated Engineers provided engineering studies, conceptual layouts, utility studies and preliminary design for an 80- acre mixed-use conunercial project on this historical site. The site will be developed over the next 20 years, during which time Associated Engineers will provide the surveying, mapping, right-of-way, utility coordination, and civil design, as well as providing opinions of probable cost for the various projects. Due to the historical status of the site, some of the historic buildings will be upgraded and incorporated into the project. Associated Engineers, Inc. 3311 E. Shelby Street Ontario, CA 91764-4872 0:\PR0P\P\2003\P210.03\ResUmeS\CAS-teSUITll!.doc: Project Assignment Utility Coordinator Years oC Experience 12 Education Chaffey College Conununications University of La Verne Public Administration Caltrans RIW Utility Relocation School - June 1993 ProCessional Affiliations Member, Jntemational Right-of- Way Association Resume Tel. 909.980.1982 Fax 909.941.0891 Email: c3rolanns@assoc-eng.com James L. Elliott, RCE, PLS Vice-President l { James L. Elliott is both a Licensed Civil Engineer and a Licensed Land Surveyor. He bas 24 years of experience devoted to surveying, engineering and mapping in the Southern California area. Jim is responsible for mapping oversight at Associated Engiueers and bas provided a variety of surveying services on a wide range of projects including roadwayslhighways, commercial, industrial, and residential. He heads our Mapping Department and is involved with all map calculations. Resel1loir lC Pipeline, Cucamonga County Water District Rancho Cucamonga, California: Associated Engineers staff provided engineering services to design a water transmission main connecting a future reservoir to the existing pipe network at Chino Basin Municipal Water District RegionaJ Plant No.4. As part of the project, Associated Engineers provided an anaJysis which recommended the most cost effective aJignment, developed the necessary easement documentation to acquire access for construction and maintenance, and provided flnaJ contract documents. Mr. Elliott provided calculations and mapping for this project. ~1"... '..,....: iL:~~ The California Speedway, Kaiser Penske Water and Sewer Facilities Fontana, California: This project inclnded the retrofit of an existing well and partially buried concrete reservoir, including the design and construction of over 12,000 LF of potable water main. The project also included an on-demand booster station for fire and domestic demand. Associated Engineers designed the detention basins, open channel and underground drainage facilities. Mr. Elliott provided caJculations and mapping services. On-Call Design and Construction SUl1leys, Los Angeles County Department of Public Works, Los Angeles County, California: Associated Engineers is providing on-call surveying for the County of Los Angeles' Public Works Department. Contract services support the construction, improvement, and maintenance of public roads, drainage systems, sewer and water lines. Mr. Elliott provides caJculations and mapping oversight for this work. State Route 30/ 210, Segments I, 4, 7 & 8, San Bernardino County, California: Associated Engineers, as a Prime ConsuJtant, was responsible for all calculations and mapping for surveying and Right-of- Way Engineering Services for SANBAGI Caltrans - District 8. These services supported the acquisition of public Right-of-Way and utility easements. Responsibilities included surveys, preparation of 90 f1naJ Right-of-Way maps, preparation of 340 legal descriptions, Deeds and Record of Surveys, along 9 miles of State Route 210. All Right-of-Way maps were prepared with duel units (English - Metric) in conformance with CaJtraDS Survey, Right-of-Way and Drafting Manuals. Mr. Elliott was responsible for mapping oversight and quality controL l Associated Engineers, Inc. 3311 E. Shelby Street Ontario, CA 91764-4872 O;\PllOP\P'\2003\P21ll-03\Re5UmeS\3E. WATER.DOC Project Assignment Survey Task Leader Years of ExperIence 24 Education B.A. Mathematics - 1980 University of California, San Diego Professional Registrations Civil Engineer, California #43907 Land Surveyor, California #6334 Resume Tel. 909.980.1982 Fax 909.941.0891 Email: jime@assoc-eng.com I ~ City of San Bernardino Design Schedule for Design of the Sanitary Sewer Main in Arrowhead Avenue from Mill Street to Orange Show Road 10 Task Name Preparing Base Sheets 2 Research 3 Field Survey 4 Draftin9 Base Sheets 5 Alignment Selection 6 Draft Preliminary Alignment 7 Field Walk with City Staff 8 Pothole Conflicts 9 Finalize Alignment 10 Draft Cost Est. & Traffic Cnti. Plans 11 Soillnvestiga~on (If ne~ssary) tt.,;;~ 12 ~;;~:;- City Staff Review 13 80% Design 14 80% Drawings 15 Cost Es~mates 16 Specifications 17 Traffic Plans 18 City Staff Review 19 Final Plan Submittal 20 Finalize Plans 21 Finalize Cost Estimates 22 Finalize Traffic Plans 23 Finalize Specifications 24 City Staff Review Addi~onal 3 weeks may be necessary for the combined project schedule. Thu 10/16/03 - 3:22 PM Dura~on Start November 2003 De~mber 2003 _ _~Janl!!!!YZ004 -< 0/2 11/211/9 1/1 1/2 1/312/7 211 2I~]J.itl1/411/111J11811g5' 10 days Man 11/3/03..... ' 10 days Man 11/3/03 Task Split Progress Milestone Summary 4 days Thu 11/6/03 3 days Wed 11/12103 13 days Man 11/17/03 2 days Man 11/17/03 1 day Wed 11/19/03 5 days Thu 11/20/03 5 days Man 11/24/03 3 days Wed 11/26/03 5 days Thu 11/27/03 10 days Wed 11/19/03 21 days Thu 12/4103 16 days Thu 12/4/03 3 days Tue 12/23/03 5 days Fri 12119/03 3 days Tue 12/23/03 5 days Fri 12126/03 15 days Fri 1/2/04 10 days Fri 1/2/04 3 days Tue 1/13/04 3 days Tue 1/13/04 3 days Tue 1/13/04 5 days Fri 1/16/04 1."",.,':0,',""',"',"","',"',"','l prof'ect Summary · .J :::::;::::;:::::::::::::::;::'::::::. .... External Tasks [~-___... ... .._-_-_--.~-::~,-,! 11.............11.. ---- ----.... . \. External Milestone + Deadline -0 .J schedule 8x11final.mpp Tl Q."., .,;,:,~~:... ..,[ ""-$,- w w ~ ~ a. Cl iii: a. W ;:) ... j:: Q Z ~ W J: ::Ii u W 0 ~ ~ a. Iii W W iii: iii: W Iii z ... ::iI;:;: ... 1Ii:....- W ::Ii ~ ~ 1/1 iii: >- ... ~ ~ ~ Z - W ! ~ ~ ~ Z J: 52 ~ 1/1 0 W iii: Q ~ \ ... Lt)CO~~"Ot~om~~~~~ ...J ~ o .... u g,c: H ell'" o ... ~ N N N ~ h ell d Ul N ~ ~ o"Ot~~ "OtNNN ~~ f~ f] ...~ ~w ... N N'" ~ ClONNN ................ d It'! eo...: o:Ul U N~ "OtNNN"OtCO CD N............N 0 ~ NN N" N CO"Ot"Ot"OtNN 0 .. N .. is ~i l1! z <> llJ tij - go wi ~ s ~ j ~ Ul~ ~ j i II::: II) 1! 1: .!! lldSg' j :i; III '-;' 11)"0.. a. &:: l:S ~ I.~ ~ j ~.~ ~.g - 13 .5 0 ~ .~ 'U !i rJ l! . ~ ,!i<>~~ ill 5 -~a:i~ e 8 ~~~i,"HHh~Ul~ ; n~'" ~c j Jlil~~~ Jl ~ u h .~j ." ~~"IE~'- :'e' 160:i ~8l!~e a..a. =' u.a. O)....I-oa. ii.....""":C\!~~~~""': ~N(") F ------- .. N ~ ... ~ ~ ~ . ~ ~ . E ~ ~ ~ 8 I ~ .. N u .... ~ .. ~ .. ~ :il ~ .. .. ~ ~ ;x ~ City of San Bernardino Proposal for the Design of Sanitary Sewer Line ReplacementlUpgrade at Arrowhead A venue from Mill Street to Chandler Place % OF AVAILABILITY OF KEY STAFF Associated Engineers is or will be involved on following projects listed below. We have provided a chart of anticipated staff availability for this City of San Bernardino project on the chart below. . San Bernardino International Airport . California State Polytechnic University, Pomona, Water System . Y orba Avenue Storm Drain, City of Chino . 91 Freeway widening, Riverside ~""" .:i-~~~ ./..,....:'" I 2003 I 2004 Staff ~..........-_.....-....._.-...T-......_...--......-.........r..-.....--....--.--.......- I November I December January , I Curt Ingraham, R.C.E. 20% 20% 20% Jamey Dye, R.C.E. 30% 40% 50% Zack Isnasious, R.C.E. 50% 60% 60% Carolann Stoney 40% 20% 20% Michael Guirguis, E.I.T. 40% 45% 60% Jim Elliott, R.C.E., PLS. 10% 10% 10% l O:\PROP\P\2003\P21\H)3\% STAff AVAILABIlITY.doc ! 11 City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place SUPPORT PERSONNEL The staff members identified with an asterisk wiIJ be supporting our key members. ~;~:. 'N-,_.: :.'..0 Carol ann Stoney Larry Taylor * Dolores Moreira * Priscilla Emperado * CITY OF SAN BERNARDINO Acting City Engineer , Michael Grubbs Associated Engineers Project Manager Jamey G. Dye, R.C.E. Design Engineering Jamey G. Dye, R.C.E. Zack Z. Isnasious, R.C.E. Michael Guirguis, E.I.T Associated Engineers Project Oversight Curt Ingraham, R.C.E. James L. Elliott, L.S., R.C.E. Janeen Nedlik, L.S. * Marc Wilson, L.S.I.T. * " City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place SUB CONSULTANTS Associated Engineers intends to utilize HP Communications as a sub-consultant for potholing services. HP Communications Owner: Nick Goldman 13341 Temescal Canyon Road Corona, CA 92883 Phone: 909.471.1919 Fax: 909.471.2427 Associated Engineers has been working with HP Communications for potholing services for the past 3 years. AE has found HP Communications to be cost effective and responsive. ~.=/, ., - -~.:! ..-::_ 4 O:\PROP\P\2003\P210-o3\SUb Consultants.doc ,., ! Fj;:A ~..., l , City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place LOCAL PREFERENCE ELIGIBILITY Associated Engineers is locally based in the City of San Bernardino at San Bernardino International Airport, 225 S. Del Rosa Drive, Building 702, San Bernardino, California 92408-0 III. This office is manned by Mike Stewart full time and Curt Ingraham on a part-time basis. Associated Engineers has worked on numerous projects within the City of San Bernardino. Approximately II of our employees are currently working in the City of San Bernardino. We have also included a list of current and past projects within the past two years that we are currently working on or have worked on within the City of San Bernardino. Client Project Name! Description Location Holiday Rock Baseline Street Improvement SB EL Yeager SB & 4th Street Improvements SB HOK Engineering! CSUSB Student Recreation Center, Cal State SB SB Robert Kite & Associates 5MBMI! Fire Station SB DMJM + Harris 1-215, Segment 5 SB San Bernardino County IS Dept. GIS Parcel Mapping SB City of SB Municipal Water On Call Services SB Gresham, Savage, Nolan & Tilden On Call Services SB R & S Development Corp., Inc. Sequoia Development SB Clerkin & Clerkin Commons Driveway (CSUSB) SB CSUSB Eco Pond SB CSUSB SIW Behavioral! Staking SB Kemp Bros. Construction CSUSB Science Annex SB CSUSB Misc. Parking Improvements SB CSUSB Science Annex - Phase 1 SB Bechtel IWL Surveys at SB International Airport SB Earth Tech Extraction Well, MEW-II Norton! SB CSUSB Sidewalk (EAS, SMP) SB CSUSB Student Union SB CSUSB GIS Mapping SB CSUSB Adrninstration Sidewalk Project SB CSUSB Storm Drain Improvements SB CSUSB Misc. Surveying (SMP) SB PM Realty Advisors Alta Survey Hospitality Lane SB Holmes & Narver (DMJM) 1-215, Segment I SB CSUSB Social & Behavioral Science Bldg. SB CSUSB Athletic Field Drainage SB CSUSB Observatory Site SB Taylor Ball San Manuel Bottling Plant SB City of San Bernardino Potholes Segment II SB O:\PROP\P\2003\P21()-{l3\local Preference E1lgibifity.doc CITY OF SAN BERNARDINO BU5INE55REGISTRA.TIONCERTIFICATE -N"RNlNGI 'HIS BUSINESS REGlSTRAl'ICtl CEFtT!FICAT€ 00ES NO::'T iNlJICAT:o The :.S,;;AL '..JfSF...nCN'::: -:l11S 6l,lSlfiE'3,s.Hl1"'1S LOC,J;'I'!CI'l "mER AfIPAOVAi,.S 6'( OTHERClrt DE?~~TMENTS. 3"CH~S;>l.,.;.\NNING ,J;NC 3UIll":iNG SEflVlC~.:;. IAAY Sf" "~Ot.JIRIiC !3.. ~mmenL.CodB.Secllcn,:37~O~.2I;1o); ,;hlS Collldn:a1e ,$ ;s.$uec ....'thou! -1'lf..tOC'lll"" 'bHhlO ""r1d~at.. ,s'suoioK1 III or ....,...:.c-4omtiun>;lI'i!Jl:Iym"SIlIl.~.Catdi'ltf\lll . CERTIFICATE EXFlRE31 Mat' 04 ~;::""~~O.... Jtil..,. Lr OFRCE OF THE JJl) ClTYClF.~1!' R~ n.8U$ifWsso- i','<I5p<l<>sliole 1'J<flim~"'I 'lW"wai NOI ;smlivir:<} '1,.in~.....;:tiJ\(;Il"',,;!cr ."''1 ,~Ofl. ~-r1<)I relie'l~ ,~ibMly 1a,1lmefy payn_l, !f 1101 pal<lWII~un jOd:lv~ ~rt~~ 1l1lil,rd!+on-;Ia:.. on;;..n. J 3Go..;.""'l:Illy wee Imp::>a'id. 'liter 3Cl ja~i This Buslnes!l Aegistration Car1iflcala i$ not trn(loStaracle 10 Mctnllr ()Wiler. (SBMC;.04..0201 C!.ASS O~I" I NEER BUSINES::t;;,,",. BUSINESS AD""ESS225S DEL ROSA DR SAN BERNARDINO. CA 92408 QWN~FL.: . .US~;~~OC IATEDENQINEERS. INC MAIUNti3311 E SHELBY ST AOORES'DNTARIO. CA 91764 POST IN A CONSPiCUOUS PLACE I1F THE BUSINESS PREMISES ARE CPE~HO THE PUBliC} r.~ ~_:."- ',< .~{}~.: Cash Receipt Number: 214651 roo CREDIT PENALTY T<:)TAL ~~=c~. ~ , PHOroCOP[ES NOT VALID ' '2939.91 $ $2939.91 , t' .'> <..-';.;,:.; -: ~--,;,...,! ,;.;.", '''-., "P City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead A venue from Mill Street to Chandler Place REQUEST FROM THE CITY OF SAN BERNARDINO Associated Engineers would request the folIowing items, actions or information to be provided from the City of San Bernardino. . Attend Alignment selection meeting . Provide review of the Alignment Study and 80% Plans . Provide final Project approval . Provide AE with existing records of Sewer and Storm Drain . Provide information for street center ties and bench marks O:\PR0f'\P\2003\P21D-03\ADOmONAL INFO FROM CITY.doc lC City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place PROJECT APPROACH Meet with City Staff - Associated Engineers will meet with City of San Bernardino staff to discuss final design details and visit the job site to take digital pictures. Sewer Main Sizing - Associated Engineers will review the design flow requirements and master plan documents to determine size and points of connection. Research Existing Records - Associated Engineers utility research group will develop a list of utilities in the area through the use of the Underground Service Alert system, walking the job site and looking for surface evidence, knowledge of the local utilities in the area, existing as-built drawings, and discussions with City staff. The Associated Engineers staff will also collect the horizontal and vertical control information such as benchmarks, subdivision maps, and centerline ties necessary for the project. Once a list of agencies is compiled, the utility team will collect as-builts and Atlas drawings from each utility through mail requests, phone conversations, and physically visiting each utility as necessary to obtain the appropriate information. The City staff will be provided copies of correspondence and the results of the research phase of the project, as desired. ,<:~.. t,;~.< ~--::-~ Preparing Base Sheets - The existing utility and right-of -way information will be compiled into a composite base map for use in surveying and the basic layout phase of the project. Field Surveying - With the knowledge collected by the research tearn, the surveyors will be able to quickly collect the field data needed to perform the final design. The field data will include surveying ground surface elevations, all visible utility facilities, dipping all sewer and storm drain manholes, surveying the depth to the nut on water facilities, location and elevations of surface features, utility vaults, any overhead lines, trees, paint striping or other facilities that may impact ultimate alignments, traffic control, and construction activities. Associated Engineers does not recommend the additional expense and time delays associated with aerial mapping. Alignment Selection (1st Submittal) - After the survey data has been compiled and reconciled with the record utility information, Associated Engineers will develop a preliminary alignment for review by the City of San Bernardino staff. This will be in the form of20-scale plan and profile sheets showing a single line plan and profile of the proposed water line alignment. Existing utilities will be shown in both the plan and profile view. Utilities of unknown depth such as gas, water, and electrical, will be shown in profile as a vertical line only. Once the City has received the preliminary alignment drawing, Associated Engineers would recommend walking the full length of the alignment with City staff to identif'y potential conflicts and select potholing locations. Major considerations during the alignment selection include: . The ability to install, and test the new system without putting the existing system out of service. . Excavator access. . Spoils pile locations. . Traffic Impacts. . Minimize the amount of asphalt removed. f \ O:\PROP\P\2003\P21D-03\PROJ APPROACH.DOC T City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place Cost Estimates - Associated Engineers would develop a construction estimate to be submitted with the first submittal for review by the City of San Bernardino. In addition to material size and type, Associated Engineers will consider the following items during cost estimate development: . Completed projects of similar size and type. . Condition and extent of asphalt impacted. . Traffic Conditions. . The existence of concrete underpayment. . General soil conditions. Potholing - Associated Engineers recommends potholing in the following situations: . Points where the record drawings show potential conflicts. . Points where there is a large bank of electrical or communications conduits (in the event that they have been incased in a large block of concrete). . Points where the location of the utility is not well know. ~.'i1 .~-';;;'., w.' Associated Engineers recognizes that potholing is expensive and often adds unnecessary cost and time delays to the project and would therefore keep the number and location of the potholes at a minimwn. Associated Engineers is proposing to use HP Communications for potholing services. Soils Investigation - It is unlikely that soils investigation will be necessary for this project. Whether soils borings are required will depend on the number and size of the potholes and the condition of the existing soils encountered during potholing activities. Soils investigation costs are excluded from the project scope. If soils investigations are determined necessary, Associated Engineers will be able to recommend a soils engineer and evaluate the results of the soils report. Draft Design Submittal (2nd Submittal) and Draft Traffic Control Plan - After receipt of all the City's comments and the data from the potholes, Associated Engineers staff will proceed with final design drawings and specifications. The 80% design and specifications would then be submitted to the City for the second design review. It is anticipated that this product would be submitted to utility companies and impacted agencies for review prior to fmal acceptance by the City. Any comments on the Draft Design Submittal would be compiled and discussed prior to finalizing the plans and specifications. . Final Design Drawings, Construction Specifications, Cost Estimates, and Traffic Control Plan - Based on the comments and feed back from the Draft Design Submittal, Associated Engineers would prepare final drawings, specifications, cost estimates, and traffic control plans for review and approval by the City. Construction Management - Associated Engineers has an experienced team of construction inspectors and contract managers available to provide construction support, if requested by the City of San Bernardino. Construction Management services has been excluded from the project scope. \. O:\PROP\P\2003\P210-o3\PROJ APPROACH.DOC 'f City of San Bernardino Proposalfor the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place PROFILE Associated Engineers maintains an office in the City of San Bernardino and has engaged in civil engineering, surveying, Right-of-Way engineering, and construction administration for public and private clients since 1955. The firm's 46 employees include, eleven (II) registered civil engineers, seven (7), licensed land surveyors, CADD operators, survey/ mapping technicians, civil designers, and administrative staff who support these services. Projects have included all aspects of civil engineering design, construction management, surveys, studies, planning, and utility coordination. Survey capabilities include boundary, topographic, AL T A and utility mapping, aerial control surveys, right-of-way mapping and construction staking. Associated Engineers' clientele include highway and airport authorities, industrial, commercial and residential developers, municipalities, flood control districts, school districts, water agencies, utility companies and various State and Federal agencies. ;t;:. \i;9 Over the years, Associated Engineers has built a strong reputation for quality work and professional integrity. Due to this reputation for providing a quality work product, we have had the opportunity to be involved in many high profile engineering and surveying projects. Associated ver the years, Associated Engineers has built a strong reputation for quality work and professional integrity. Due to this reputation for providing a quality work product, we have had the opportunity to be involved in many high profile engineering and surveying projects. Associated Engineers continues to maintain state-of-the-art computer capabilities. We currently network over 50 PC workstations to a file server with a capacity of 130 gigabytes of storage, which is copied to backup tape nightly. Over 30 PC stations are configured for CADD applications including MicroStation, InRoads, AutoCAD, as well as hydrology, hydraulics applications, Microsoft Office and others. Two HP DesignJet 1055C color network plotters assist with all plotting requirements, including draft and final plan mylars, together with 36-inch wide color photo and presentation quality plots. To achieve maximum efficiency in the field, Associated Engineers uses fast, accurate and dependable survey equipment. We utilize Geodimeter System 600 total stations as our mainstay survey instrument. When remote and safe data gathering are required, we have a Geodimeter Reflectorless 610 GR200 instrument. We have two Lieka Series 3000 digital bar-code reading levels for precision differential level runs and Trimble 5700 GPS receivers for large scale control surveying or fast RTK data collecting. We also are able to trace underground utility locations using our two Metrotech 810 Line Tracers. Associated Engineers, a Woman owned business, prides itself on a tradition of quality engineering services. ( O:\PROP\P\20D3\P210-o3\PROFILE.doc l' ~ May 19, 2003 Metropulitan Transportation Authority Ms. April Morris Associated Engineers, Inc. 3311 East Shelby Street Los Angeles, CA 91764 One Galeway Plaza Los Angeles. CA 900 12.2952 SUBJECT: WBE CERTIFICATION APPROVAL Dear Ms. Morris: Pursuant to provisions of the Woman Business Program of the Los Angeles County Metropolitan Transportation Authority (MT A), Associated Engineers, Inc. has been granted approval for Woman Business Enterprise (WBE) certification status. The North American Industry Classification System (NAICS) codes used in determining your firm's eligibility are: NAICS 120021 541330 541370 DescriDtion Engineering Services/Civil Engineering Land Surveying/Mapping Services Only work in the above NAICS codes will be counted as WBE participation on MTA projects. @..'<..... "'$':, ~~+ MT A reserves the right to withdraw this certification if at any time it is determined that certification was knowingly obtained by false, misleading, or incorrect information. MTA also reserves the right to request additional information and/or conduct on-site visits at any time during the certification period. The firm of Associated Engineers, Inc. thereby consents to the examination of its books, records, and documents by MT A. This certification is valid for a period of two years. To continue doing business with MT A as a WBE, a recertification affidavit and current Federal Tax Returns must be submitted orior to the firm's certification exoiration date of Mav 19, 2005. If there are any changes in the ownership or control of the firm during the certification period, ~enr"'" ,.1:'\......:..<'\.... to ~O.I.&,..I-'"':s ~ffi-a :.....,..,.,ed.'-t::o.'....... 1')"3\ "'2" 2Cf\n 'c. .~\;i '....I.j"""........ 1~_~.I~~._.~'1I '"", '" :.1111. g,.<C;11 en \.&..' I OJ "'- ~..Vu. Sinc,erely, ( ~) -, /~'.' /1/. ;. ./ /' , ,"1 -'lV' / Cf U/t.--/.:---- "---- . . -iZ-d...i.i.. .p ~ Da ene Williams '-) Diy'ersity & Economic Opportunity Representative l C;\MTA Filos'CERnFlCATIONlCen_WordlDu\elle WiUi.....>Conific'lliofl Ldten\A.D fi.....'AJso. EngiMcn weE.Joe- ~ i3 r , i ~'.\ -.-;f:;.-! .4-.... t . City of San Bernardino Proposal for the Design of Sanitary Sewer Line Replacement/Upgrade at Arrowhead Avenue from Mill Street to Chandler Place PROFESSIONAL LIABILITY INSURANCE Associated Engineers agrees and accepts the City of Chino Hills' Professional liability insurance requirements. We will carry professional liability insurance in the amount not less than one million dollars. O:\PROP\P\2003\P21D-03\1NSURANCE.doc ~, CII.nt#: 5084 ASSOCENGI1 ACORDN CERTIFICATE OF LIABILITY INSURANCE DATE (MMlDDlVYYYI 09/03/03 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTlACATE HOLDER. THIS CERTIACATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POUCIES BELOW. PRODUCER Dealey, Renton & Associates 199 S Los Robles Ave Ste 540 'asadena, CA 91101 J26 844-3070 Associated Engine.rs, Inc. 3311 E. Shelby Str.et Ontario, CA 91764 INSURERS AFFORDING COVERAGE INSURER A, 51. Paul Fire & Marine Ins. CO. INSURERS, Greenwich Insurance Company INSURER c: INSURER D: INSURER E: NAIC# INSURED COVERAGES THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING my REQUIREMENT, TERM OR CONDITION OF my CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. LTR NSR TYPE OF INSURANCE POUCY NUMBER "rf'AI:li~:tf~~reIE P~lifJ ~JJ,~N LIMITS ~NERAL UA81UTY EACH OCCURRENCE , COMMERCIAL GENERAL LIABIUTY DAMAGE TO RENTED , I CLAIMS MADE D OCCUR MEO ex, (Any one person) , - PERSONAL & ADV INJURY S - GENERALAQGREGATE , ~'lAGG~n LIMiT .\PAS PER: PRODUCTS. COMPIOP AGG , POLICY I ~~,Qr LOC ~UTOMOBILE UA8lUTY COMBINED SINGlE LIMIT , ANY AUTO (Eaacclclent) - - ALL OWNED AUTOS BOQll Y INJURY (Per person) , - SCHEDULEO AUTOS - HIRED AUTOS BOOIL Y INJURY (Peracciclent) S - NON..QWNEO AUTOS ~. PROPERTY DA ~,uGE I' ,." (Peracciceni ~~GE LIABILITY AUTO ONLY. EA ACCIDENT , ANY AUTO OTHER THAN EA ACC , AUTO ONLY: AGG S ::=JESS/UMBRELlA UABIUTY EACH OCCURRENCE S OCCUR 0 CLAIMS MACE AQGREGA TE , s =J ,DEDUCTISLE , RETENTION S , A WORKERS COMPENSAnON AND WVA7726603 09/01/03 09/01/04 X I we STATU; I IO~ EMPLOYERS' UABlUTY ,1 000 000 ANY PROPRIETORIPARTNERlEXECUTlVE E.l. EACH ACCIDENT OFFICERlMEMBER EXCLUDED? E.l. DISEASE. EA EMPLOYEE ,1 000,000 If ~es. describe undel" ,1,000,000 S ECIAL PROVISIONS below E.L. DISEASE. POLICY LIMIT B OTNER Professional PECOO14562 07/15/03 07/15/04 $1,000,000 per claim Liability $2,000,000 annl aggr. DESCRIPTION OF OPERATIONS f LOCATlONS I VEHICLES I exCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS (, For Proposal Purpose. Only CA CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POUCIES BE CANCELLED BEFORE THE EXprRA nc~, DATE THEREOF, THE rasUING INSURER WILL. ENDEAVOR TO MAIL ....30.... OAYS WRITrE~ NonCE TO THE CER'MFtCATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO so SHALL IMPOSE NO 08UGAnOH OR UABtUTY OF ANY KIND UPON THE INSURER, ITS AGENTS OR REPRI!S!NTATIV!S. AUTMORIZID RlP-:~! CERTIFICATE HOLDER ACORD 25 (2001108) 1 of 1 JMV Ii) ACORD CORPORATION 1981 "M91598 '1[- CITY OF SAN BERNARDINO DEVELOPMENT SERVICES DEPARTMENT RATING SHEET SEWER PROJECT-NON FEDERAL AID PROJECTS PHASE I - REVIEW OF PROPOSAL Attachment "B" PROJECT: CONSULTANT: No. Max. Description Ratin!! Points 1. 20 Experience - For example, what similar recent projects has this firm done and how many years of similar experience does this company possess. Is the company background solid and does the company possess sufficient financial resources to engage this project? 2. 20 Proiect Personnel - For example, does each individual possess adequate experience in this type of work? Will the assigned personnel be able to devote adequate time to meet the proposed schedule? Does the design team appear to be balanced in the appropriate disciplines necessary to accomplish the work envisioned by this RFP? 3. 5 Estimated Time of Completion For example, does this firm's proposed schedule for the project seem realistic and does it tie closely to the work involved? Is the staffing level adequate to meet the schedule? 4. 5 Past Experience in Dealin!! with Firm - For example, has this firm worked for the City in the past? Did the firm competently complete the work and would you recommend the firm? 5. 15 Abilitv to Meet Contract Obli!!ations - For example, does this firm appear capable of meeting the obligations as related to budget and time? From a financial and organizational standpoint, does this firm appear capable of fully complying with the terms of the proposed Agreement? 6. 15 Depth of Understandin!! of the Proiect - For example, do the principal personnel understand what is expected on this Project? Do they appear aware of the complexities involved? Does their proposal indicate a depth of knowledge and recent experience or do they appear to be saying whatever it takes to get the job? Has this firm done its homework? 7. 5 Completeness of Information Submitted - For example, does the proposal meet all requirements of the RFP and does it provide sufficient information to complete your evaluation? Did this firm indicate insight into the project that was lacking in the other firm's proposals? 8. 10 Score for Sealed Proposed Fee , i 9. 5 Local Preference - Does the consultant h~ve an office inside the city limits, possess a City business license and have a minimurrl of one (I) owner or employee assigned to the office? (Working in the office or in the field but stationed at the office). POINT TOTAL FROM REVIEW OF PROPOSALS (POSSIBLE 100 POINTS) COMMENTS Page 1 of 3Rater: Date CITY OF SAN BERNARDINO DEVELOPMENT SERVICES DEPARTMENT RATING SHEET FOR SEWER PROJECT -NON-FEDERAL AID PROJECTS PHASE II - SELECTION INTERVIEW THE THREE CONSULTANTS WITH THE MOST HIGHL Y SCORED PROPOSALS PROJECT: CONSULTANT: 1. Past Experience on Similar Projects. (20 Points Max.) Comments: 2. Experience managing meetings between Staff, Consultant and the Public. (5 Points Max.) Comments: 3. Adequacy of Principal Staff Specifically Assigned to Project (Resumes). (20 Points Max.) Comments: 4. Adequacy and availability of consultant's in-house support staff. (15 Points Max.) Comments: 5. Adequacy of proposed Sub-consultants to be used and working arrangements with them on similar projects. If no sub-consultants are proposed then the adequacy of consultants in-house staff to meet all project needs will be evaluated. (J 0 Points Max.) Comments: 6. Flow (Time) Chart for Completion of tasks identified. (5 Points Max.) Comments: 7. Depth of Understanding of the Project. (J 0 Points Max.) Comments: 8. Local preference credit. (5 Points Max.) Comments: 9. Score for Sealed Proposed Fee. (J 0 Points Max.) Comments: POINT TOTAL FROM INTERVIEW PHASE (J 00 Points possible). Evaluator's Name: Evaluator's Signature: Date: Page 2 of3 .: CITY OF SAN BERNARDINO DEVELOPMENT SERVICES DEPARTMENT RATING SHEET SEWER PROJECT-NON FEDERAL AID PROJECTS SUMMARY SHEET PROJECT: CONSULTANT: SCORE FROM REVIEW OF PROPOSALS - SHEET 1 (loa Points Possible) SCORE FOR INTERVIEW - PHASE II (l00 Points Possible) GRAND TOTAL SCORE (200 Points Possible) PERCENTILE SCORE = Page 3 of3 Attachment "C" PHASE II SELECTION INTERVIEW Interview Questions I. If you have an initial presentation you would like to give prior to our commencement of questions, we would be happy to receive the presentation now. Please make sure in your presentation that you comment on your firm's experience as it relates to the proposed projects. 2. Please tell us about your project personnel and how their respective disciplines benefit the work necessary to complete the project. 3. What is your estimated time for completion of the project? 4. What projects, if any, have you completed in the City of San Bernardino? 5. Do you know of any issues impacting your capability to meet the obligations of the scope of work as related to budget, time, and from a financial and organizational standpoint? 6. Some of the sewer lines are located within State (Caltrans) right-of-way. Please tell us your experience working with Caltrans and how you intend to obtain encroachment permits. 7. What items do we need for the completion of the design that are not covered in your scope of work? 8. What type of field review did you conduct in preparation for responding to the RFD and designing the facilities? 9. What are some of the complexities involved in the project? Are there unusual features or problems regarding this project? 10. Do you have suggestions to improve the finished product contemplated in the scope of work? II. Are there incentives/benefits to the City in the event both projects (the Arrowhead Sewer Line Project, and the "E" Street and six other Projects) were to be awarded to your company? OFFICE OF THE CITY CLERK RACHEL G. CLARK, C.M.C. - CITY CLERK 300 North "D" Street. San Bernardino' CA 92418-0001 909.384.5002' Fax: 909.384.5158 www.ci.san-bernardino.ca.lis 8M January 7,2004 Associated Engineers, Inc. 225 S. Del Rosa Drive San Bernardino, CA 92408-0111 At the Mayor and Common Council meeting of January 5, 2004, the City of San Bernardino adopted Resolution 2004-3 - Resolution approving a services agreement with Associated Engineers. Inc., for design of sanitary sewer main replacement in Arrowhead Avenue from Mill Street to Chandler Place. Enclosed is one (1) original agreement. Please sign in the appropriate location and return the original agreement to the City Clerk's Office, Attn: Michelle Taylor, P.O. Box 1318, San Bernardino, CA 92402, as soon as possible. Please be advised that the resolution and agreement will be null and void if not executed within 60 days, or by March 5, 2004. Please retain a copy of the agreement for your jiles. If you have any questions, please do not hesitate to contact me at (909)384-5002. Sincerely, (j?JI~L(6 .:J,t<g/6 . Michelle Taylor Senior Secretary Enclosure CITY OF SAN BERNARDINO ADOPTED SHARED VALVES: Integrity' Accountability' Respect for Human Dignity' Honesty OFFICE OF THE CITY CLERK RACIlEL G. CLARK, C.M.C. - CITY CLERK 300 North "0" Street. San Bernardino' CA 92418-0001 909.384.5002' Fax: 909.384.5158 www.ci.san.bernardino.ca.us 8M January 23,2004 Associated Engineers, Inc. 3311 E. Shelby Street Ontario, CA 91764-4872 At the Mayor and Common Council meeting of January 5, 2004, the City of San Bernardino adopted Resolution 2004-3 - Resolution approving a services agreement with Associated Engineers, Inc., for design of sanitary sewer main replacement in Arrowhead Avenue from Mill Street to Chandler Place. Enclosed is one (I) duplicate original agreement. Please sign in the appropriate location and return the original agreement to the City Clerk's Office, Atto: Michelle Taylor, P.O. Box 1318, San Bernardino, CA 92402, as soon as possible. Please be advised that the resolution and agreement will be null and void if not executed within 60 days, or by March 5, 2004. Please retain a copy of the agreement for your files. If you have any questions, please do not hesitate to contact me at (909)384-5002. Sincerely, /h 'C(~I:;( <- :1; (["'-- Michelle Taylor Senior Secretary Enclosure CITY OF SAN BERNARDINO ADOPTED SHARED VALUES: Integrity' Accountability' Respect for Human Dignity' Honesty CITY OF SAN BERNARDINO Interoffice Memorandum CITY CLERK'S OFFICE Records and Information Management (RIM) Program DATE: January 30, 2004 TO: Mary Freiberg, Senior Admin. Ops. Supervisor FROM: Michelle Taylor, Senior Secretary RE: Resolution 2004-3 - Associated Engineers, Inc. CC: Veronica Martinez, Senior Secretary Attached is a fully executed copy of the agreement with Associated Engineers, Inc., for design of sanitary sewer main replacement in Arrowhead A venue from Mill Street to Chandler Place. The original agreement is on file in the City Clerk's Office. If you have any questions, please call me at ext. 3206.