REQUEST FOR COMMISSION/COUNCIL ACTION
From:
Roger G. Hardgrave, Dir.
of Public Works/City Engr.
Subject: Approval of Plans &
Authorization to Ad-
vertise for Bids --
Construction of Rest-
room Building at
Nicholson Park, per
Plan No. 9215
Date:
5-16-95
-----------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
June, 1994 - Allocation of $137,800 approved in 1994/95 CDBG
Program.
-----------------------------------------------------~----------
Recommended Motion:
That the plans for construction of a restroom building at
Nicholson Park, in accordance with Plan No. 9215, be approved;
and the Director of Public Works/City Engineer be authorized to
advertise for bids.
cc:
Barbara Lindseth
Annie Ramos
aus, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roqer G. Hardqrave Phone: 5025
project Area: N/A Ward(s): 3
Supporting Data Attached: Staff Report
1994/95 CDBG
FUNDING REQUIREMENTS: Amount: $ 137,600 Source: Proqram
Budget Authority: Acct. #8064202
-------------------------------------------------------------~-- --
Commission/Council Notes: en j{J5- 1'1'1'7
I /
Agenda Item
NooR4
~
.
.
.
.
.
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Approval of Plans and Authorization
to Advertise for Bids
Construction of Restroom Building
at Nicholson Park
Plans for a restroom building at Nicholson Park have been pre-
pared by the Engineering Division, and the project is ready to be
advertised for bids. The project consists, in general, of
reMoving the existing restroom building, and constructing a new
building in accordance with current codes.
Below is an estimate of the total project cost:
Construction Contract $ 122,300
Engineering & Inspection (W.O. #1309) 10,000
Sub-Total $ 132,300
Contingencies (4%)I 5,300
TOTAL ESTIMATED PROJECT COST $ 137,600
All costs incurred for this project will be financed from the
$137,800 allocated in the 1994/95 CDBG Program.
We recommend that the plans be approved and authorization granted
to advertise for bids.
5-16-95
tJ