CITY OF SAN BER.RDINO -
From:
ROGER G. HARDGRAVE
REQUEST .R COUNCIL ACTION
File No. 1.857
Approval of Contract Change Order
No. I' - Street Widening Improve-
ments - Mill Street (South Side) ,
Pepper Ave. to Meridian Ave., per
Plan No. 8976 --- J.E.G.
CONSTRUCTION COMPANY, INC.
Subject:
Dept:
Public Works
Date:
5-24-95
Synopsis of Previous Council action:
June, 1994 - Allocation of $185,000 in 1994/95 Gas Tax Fund budget
approved to finance improvements.
05-02-94 -- Resolution No. 94-113 adopted authorizing execution of a
Common Use Agreement with San Bernardino County Flood
Control District.
11-07-94 Transfer of $15,000 to Account No. 126-356-57856, Pepper
Avenue (west side) south of Mill, approved.
11-21-94 Plans approved and authorization granted to advertise
for bids.
03-20-95 RESO 95-64 adopted awarding con+-.:""c+C for the low bid
price of $94,889.30.
Recommended motion:
That Change Order No.1 to the contract with J.E.G. Construction Co.,
Inc. for construction of street improvenents on th" south side of
Mill Street, from Pepper Ave. to Meridian Ave., in accordance with
Plan No. 8976, be approved to direct the Contractor to provide and
install a I, inch conduit for traffic signal interconnect; at an in-
creas" to the contract price of $9,700.00, froM $94,889.30 to
$104,589.30.
cc: Shauna Clark
{A~
Contact person:
Gene R. Klatt
Staff Report,
C.C.O. #1
Phone:
5125
Supporting data attached:
Ward:
3
FUNDING REQUIREMENTS:
Amount:
$9,700 (Gas Tax Fund)
Source: (Acct. No.)
126-369-5504-1402
(Acct. Description)
IMprovements to south side Mill
Finance;/~~~-
Street, Peoper to Meridian Avenue
(' luncil Notes:
,
,.
~.
:
-,
-
75-0262
'"
<
~
1'?,05f'C-
Agenda Item NO.I.$ , .
0'
~
-
CITY OF SAN BERreRDINO - REQUEST .R COUNCIL ACTION
STAFF REPORT
The additional rights-of-way required, for installation
of traffic signals at Mill Street and Meridian Avenue, have
recently been granted by adjoining property owners. Preparation
of the plans for installation of traffic signals at this location
has been commenced.
The existing traffic signals on Mill Street, at Pepper
Avenue and Eucalyptus Avenue, are interconnected in order to
provide progressive movement of traffic. We feel that it would
be advantageous for the new signals to be interconnected with the
two existing signals.
A contract has recently been awarded for the improvement
of the south side of Hill Street, from Meridian Avenue to a point
about 550 feet east of Pepper Avenue. The conduit for the
traffic signal interconnect cable could be installed at a lesser
price under this contract, than the future one for installation
of traffic signals.
The Contractor was accordingly requested to submit a
price quote for installation of conduit for the traffic signal
interconnect. A price quote of $9,700 was provided in response
to this request, which equates to about $6.90 per foot.
We have received this quote and found that it compares
very favorably with the normal price of about $10.00 per foot.
The total estimated project cost included an amount of
$15,560.70 for contingencies which can be used to finance the
cost of this extra work.
We recommend that installation of the traffic signal
conduit be authorized.
5-24-95
75-0264