RESOLUTION NO. 2000-316
RESOLUTION OF THE CITY OF SAN BERNARDINO AUTHORIZING THE
3 EXECUTION OF A COOPERATIVE AGREEMENT BETWEEN THE CITY OF SAN
4 BERNARDINO AND THE CITY OF HIGHLAND FOR REHABILITATION OF
PAVEMENT ON 6th FROM TIPPECANOE A VENUE TO VICTORIA AVENUE.
5
BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE CITY
6 OF SAN BERNARDINO AS FOLLOWS:
7
8
9
SECTION 1. The Mayor of the City of San Bernardino is hereby authorized and
directed to execute on behalf of said City, a cooperative agreement with the City of Highland
for the rehabilitation of pavement on 6th Street from Tippecanoe A venue to Victoria. A copy of
10
11 said cooperative agreement is attached as Exhibit "A" and made a part hereof.
12 SECTION 2. The authorization to execute the above referenced agreement is
13 rescinded if the parties to the agreement fail to execute it within sixty (60) days of the passage
14
of this resolution.
15
16 1//
17 //1
18
19
20
21
22
23
24
25
26
27
28
October 3, 2000 1
2000-316
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION OF THE CITY OF SAN BERNARDINO AUTHORIZING THE
EXECUTION OF A COOPERATIVE AGREEMENT BETWEEN THE CITY OF SAN
BERNARDINO AND THE CITY OF HIGHLAND FOR REHABILITATION OF
PAVEMENT ON 6th FROM TIPPECANOE AVENUE TO VICTORIA AVENUE.
I HEREBY CERTIFY that the foregoing resolution was duly adopted by the Mayor and
Common Council of the City of San Bernardino at a Joint Regular
meeting thereof
held on the 6th day of November
, 20~, by the following vote, to
wit:
Council Members: A YES
NAYES
ABSTAIN ABSENT
x
ESTRADA
LIEN
x
MC GINNIS
x
SCHNETZ
x
x
SUAREZ
ANDERSON
x
MC CAMMACK x
/-;r/1B , L
~rc:'.....
~1
City Clerk
~d:
day of November
The foregoing resolution is hereby approved this
2000
Approved as to form
and legal content:
{~C Ce. <-/
JUDITH ALLES, Mayor
( ty of San Bernardino
JAMES F. PENMAN
City Attorney
By: t.u,.,., ?l~
0&3,2000
2
2000-316
COOPERATIVE AGREEMENT
FOR
REHABILITATION OF PAVEMENT ON 6th STREET
Between
THE CITY OF HIGHLAND AND THE CITY OF SAN BERNARDINO
AGREEMENT
This Agreement is made and entered into this ....6..tL day of November, 2000 ,by
and between the CITY OF HIGHLAND, herein referred to as "HIGHLAND" and the
CITY OF SAN BERNARDINO, herein referred to as "SAN BERNARDINO",
RECITALS
I)
HIGHLAND and SAN BERNARDINO desire to partIcIpate III a
construction project for rehabilitation of pavement on 6th Street from
Tippecanoe Avenue to Victoria Avenue, hereinafter referred to as
"PROJECT",
2) HIGHLAND and SAN BERNARDINO desire to specify the terms of
participation in the costs to engineer and construct the planned
improvements,
SECTION I
HIGHLAND agrees:
I) To provide all necessary design, including plans, specifications, utility
identification and location, and all necessary construction engineering
services for PROJECT; To prepare contract documents and provide said
contract documents to SAN BERNARDINO for review and approval. Such
contract documents shall include appropriate provisions requiring contractor
to provide insurance and indemnification provisions satisfactory to
HIGHLAND and SAN BERNARDINO:
2) To submit to the City Engineer of SAN BERNARDINO, for plan check and
approval, all plans, specifications and construction estimates for the portions
of PROJECT within the City Limits of SAN BERNARDINO;
3) To advertise and solicit bids for PROJECT in accordance with state and
local laws:
4) To provide to the City Engineer of SAN BERNARDINO a set of bid plans
and specifications and to invite said City Engineer to any mandatory pre-bid
"Job Walk" with contractors, the bid opening, and the pre-construction
conference;
2000-316
eooperative Agreement for the Rehabilitation of Pavement on 6" Street
Page 2 of6
5) To provide copies of all bids to SAN BERNARDINO and, if bids indicate
that a cost overrun of no more than fifteen percent (15%) of the estimate
will occur, to award the contract to the lowest responsible bidder, after
consultation with the City Engineer of SAN BERNARDINO, HIGHLAND
shall retain the power to reject all bids in accordance with this agreement,
6) If, upon opening of the bids, it is found that a cost overrun exceeding fifteen
percent (15%) of the estimate will occur, HIGHLAND and SAN
BERNARDINO shall endeavor to agree upon an alternative course of
action. If, after 30 days, an alternative course of action is not agreed upon,
this Agreement shall be deemed to be terminated by mutual consent;
7) To provide SAN BERNARDINO proof of Liability Insurance for
HIGHLAND's Contractor covering injury or damage to persons or property
arising out of work for which legal liability may be found to rest upon
HIGHLAND's Contractor in a minimum amount of $1,000,000,00 and
naming SAN BERNARDINO as additional insured on the policy;
8) To obtain a "no fee" Public Works Construction Permit from the City
Engineer of SAN BERNARDINO prior to start of any construction within
the City Limits of SAN BERNARDINO;
9) Prior to, or concurrent with, the start of construction, to install information
signs at entry points mutually agreeable to both HIGHLAND and SAN
BERNARDINO identifying the project as "A cooperative project between
the City of Highland and the City of San Bemardino", or similar wording
agreeable to both agencies;
10) To permit inspection of the portion of the work within the City Limits of
SAN BERNARDINO by the City Engineer of SAN BERNARDINO, or his
duly appointed representative, during all phases of the work;
11) To obtain approval of the City Engineer of SAN BERNARDINO prior to
approval of any Change Order that will increase the cost of PROJECT to
SAN BERNARDINO;
12) To pay a percentage of the design, construction engineering and
construction costs, as shown on Exhibit "A", PROJECT COST ESTIMATE,
to be amended following final cost accounting, based on the proportional
share of the cost PROJECT in each jurisdiction;
13) Concurrent with award of construction contract for PROJECT, to bill SAN
BERNARDINO for 85% of SAN BERNARDINO's proportional share of
the cost of PROJECT based on the estimated total design, construction and
construction engineering costs as shown in Exhibit "A", PROJECT COST
ESTIMATE.
2000-316
Cooperative Agreement for the Rehabilitation of Pavement on 6th Street
Page 3 of6
14) To furnish promptly to SAN BERNARDINO upon completion of
PROJECT and all work incidental thereto, a report containing a detailed
statement of the total engineering and construction costs to be borne by
SAN BERNARDINO, including resolution of any construction related
claims which may have been filed by HIGHLAND's contractor;
15) Concurrent with filing of a "Notice of Completion" for project, to submit a
final bill to SAN BERNARDINO for the balance of SAN BERNARDINO's
share of the cost of PROJECT based on the detailed statement of total
engineering and construction costs,
16) To furnish promptly upon completion of PROJECT, "As Built" plans for
PROJECT;
17) To retain or cause to be retained for audit for SAN BERNARDINO or other
government auditors for a period of three (3) years from the date of final
payment all records and accounts relating to construction of the PROJECT;
18) To indemnify, defend, and hold harmless SAN BERNARDINO and their
agents, officers and employees from and against any and all liability,
expense and claims for damages of any nature whatsoever, including, but
not limited to, bodily injury, death, personal injury, or property damages
arising from or connected with HIGHLAND's operations, or its
performance under this Agreement.
SECTION II
SAN BERNARDINO agrees:
I) To pay HIGHLAND that percentage of the design, construction engineering
and construction costs, as SAN BERNARDINO's proportional share, as
shown on Exhibit "A", PROJECT COST ESTIMATE, to be amended
following final cost accounting, based on the proportional share of the cost
of PROJECT in each jurisdiction, to a maximum amount not to exceed
$115,000;
2) To promptly render payment for all billings submitted by HIGHLAND in
accordance with this agreement;
3) Prior to award of the construction contract for PROJECT, and in sufficient
time to allow HIGHLAND to reject all construction bids therefore, SAN
BERNARDINO may terminate this Agreement in writing, provided that
SAN BERNARDINO reimburses HIGHLAND for proportionate costs
incurred by HIGHLAND under this agreement prior to termination;
4) If termination of this Agreement is by mutual agreement, SAN
BERNARDINO will bear its proportionate share of all costs incurred prior
2000-316
eooperative Agreement for the Rehabilitation of Pavement on 6'" Street
Page 4 of6
to termination based on the Engineers Estimate of the cost of the portion of
PROJECT in the City Limits of SAN BERNARDINO;
5) To indemnify, defend, and hold harmless HIGHLAND and their agents,
officers and employees from and against any and all liability, expense and
claims for damages of any nature whatsoever, including, but not limited to,
bodily injury, death, personal injury, or property damages arising from or
connected with SAN BERNARDINO's operations, or its performance under
this Agreement.
SECTION III
It is mutually agreed:
/111111
IIIIIII
IIIIIII
IIIIIII
I) This Agreement will be construed and enforced under the Laws of the State
of California;
2) This Agreement may be executed in counter parts, each of which will be
deemed to be an original for all purposes but all of which will constitute one
in the same agreement.
2000-316
eooperative Agreement for the Rehabilitation of Pavement on 6'h Street
Page 5 of6
IN WITNESS WHEREOF, said parties have caused this instrument to be officially
executed and attested by their duly constituted officers,
APPROVED:
ATTEST:
APPROVED AS TO FORM:
CITY OF SAN BERNARDINO
(
APPROVED:
Judit\rVa les, -Mayor
ATTEST: ,rP.vl'.-L. C~..v^<-IL.
-;'~t:el Clark, City Clerk
\,
,
i/ f..L~/
APPROVED AS TO FORM AND LEGAL CONTENT:
7-.
es F, Penman, City Attorney
2000-316
eooperative Agreement for the Rehabilitation of Pavement on 6th Street
Page 60f6
. .
EXHIBIT "A"
PROJECT COST ESTIMATE
REHABILITATION OF PAVEMENT
6th STREET
FROM
TIPPECANOE AVENUE TO VICTORIA A VENUE
SAN HIGHLAND
DESCRIPTION TOTAL AMOUNT BERNARDINO SHARE
SHARE-
Proportional
Share of Cost in 100% 28.47% 71,53%
City Limits
Design Cost $12,676 $3,602 $9,094
Construction $310,108 $90,057 $220,051
Contract
Construction
Engineering & $22,218 $6,304 $15,914
Inspection
Total Project Cost $345,022 $99,963 $245,059
*Maximum participation by SAN BERNARDINO shall not exceed $115,000,